Topic: Capital Budgeting Foundations

What is capital budgeting?

43 questions

  1. 1

    What is capital budgeting?

    1. A

      A process for deciding which long-term projects a company should undertake

    2. B

      A process for recording the daily operating expenses of a company

    3. C

      A process for choosing how much inventory to sell each month

    4. D

      A process for measuring the historical accounting income of a company

    Correct answer
    A

    A process for deciding which long-term projects a company should undertake

    Explanation

    Capital budgeting is the process companies use to make decisions about long-term projects, including which projects to undertake and in what order.

  2. 2

    Why can capital budgeting decisions help determine a company's future?

    1. A

      The projects a company undertakes guarantee that all future costs will fall

    2. B

      The projects a company undertakes help shape what the company will become

    3. C

      The projects a company undertakes determine how it records past transactions

    4. D

      The projects a company undertakes eliminate the need for business strategy

    Correct answer
    B

    The projects a company undertakes help shape what the company will become

    Explanation

    A company's projects influence its future activities and direction, so capital budgeting decisions can help define the company's future.

  3. 3

    Which decision illustrates how capital budgeting ideas can apply below the level of major long-term projects?

    1. A

      Calculating the number of shares already issued

    2. B

      Recording a completed equipment purchase

    3. C

      Preparing a report of last year's net income

    4. D

      Deciding how much inventory to purchase

    Correct answer
    D

    Deciding how much inventory to purchase

    Explanation

    Although capital budgeting is generally associated with long-term projects and investments, its concepts can also inform decisions such as inventory purchases or whether to lease equipment.

  4. 4

    What is the central valuation approach used in capital budgeting?

    1. A

      Project cash flows and discount them to assess whether the project adds value

    2. B

      Compare project revenues with historical revenues without adjusting for timing

    3. C

      Project accounting income and add it to the company's reported assets

    4. D

      Estimate the project's market share and compare it with competitors' shares

    Correct answer
    A

    Project cash flows and discount them to assess whether the project adds value

    Explanation

    Capital budgeting valuation principles involve projecting cash flows and discounting them to determine whether a project adds value.

  5. 5

    Which other types of valuation use principles that are also applied in capital budgeting?

    1. A

      Tax reporting and cost allocation

    2. B

      Market research and product design

    3. C

      Inventory valuation and payroll valuation

    4. D

      Equity valuation and fixed-income valuation

    Correct answer
    D

    Equity valuation and fixed-income valuation

    Explanation

    The cash-flow projection and discounting principles used in capital budgeting are also used in equity and fixed-income valuation.

  6. 6

    Which management objective are corporate budgeting decisions intended to support?

    1. A

      Minimizing all spending regardless of its benefits

    2. B

      Maintaining the same business activities over time

    3. C

      Maximizing the number of projects undertaken

    4. D

      Maximizing shareholder value

    Correct answer
    D

    Maximizing shareholder value

    Explanation

    The capital budgeting process is consistent with management's objective of maximizing shareholder value.

  7. 7

    A company is deciding whether to lease equipment or purchase it. What does this example demonstrate about capital budgeting concepts?

    1. A

      They apply only when a company builds a new factory

    2. B

      They can inform decisions beyond large-scale construction projects

    3. C

      They are relevant only when the company reports an accounting loss

    4. D

      They cannot be used unless a project lasts several decades

    Correct answer
    B

    They can inform decisions beyond large-scale construction projects

    Explanation

    Capital budgeting concepts can be applied to lower-level choices, including whether to lease equipment, as well as to major long-term projects.

  8. 8

    What is the first step in the capital budgeting process?

    1. A

      Conduct a post-audit of completed projects

    2. B

      Select projects that align with company strategy

    3. C

      Monitor projects that are already underway

    4. D

      Generate ideas for possible projects

    Correct answer
    D

    Generate ideas for possible projects

    Explanation

    The process begins by generating ideas and identifying possible projects for the company to consider.

  9. 9

    After identifying possible projects, what is the purpose of analyzing the individual projects?

    1. A

      To replace the company's strategy with a project-by-project ranking

    2. B

      To confirm that every proposed project should be accepted

    3. C

      To determine which projects have already met their objectives

    4. D

      To identify potentially profitable projects and decide which to execute and in what order

    Correct answer
    D

    To identify potentially profitable projects and decide which to execute and in what order

    Explanation

    The second step analyzes individual projects to identify profitable options and determine which projects to execute and in what order.

  10. 10

    Why might a project that appears profitable on its own be treated differently during planning and capital budgeting?

    1. A

      Its benefits may be reduced when it is considered alongside other projects

    2. B

      Its cash flows become irrelevant once another project is proposed

    3. C

      Its accounting income must be substituted for its expected cash flows

    4. D

      Its individual profitability proves that it must be undertaken immediately

    Correct answer
    A

    Its benefits may be reduced when it is considered alongside other projects

    Explanation

    A project may appear profitable in isolation but less beneficial when evaluated alongside other projects and broader company considerations.

  11. 11

    What is a key purpose of the planning and capital budgeting stage?

    1. A

      To verify the assumptions of projects that have already been completed

    2. B

      To generate as many ideas as possible without evaluating them

    3. C

      To choose profitable projects that fit company strategy and broader priorities

    4. D

      To assess each project without considering the company's other activities

    Correct answer
    C

    To choose profitable projects that fit company strategy and broader priorities

    Explanation

    Planning and capital budgeting considers the list of profitable projects, their fit with company strategy, and larger issues affecting the company.

  12. 12

    When should a company monitor a project to check whether its objectives are being met?

    1. A

      Only after the company has selected its next project

    2. B

      While the project is underway

    3. C

      Only after all future cash flows have ended

    4. D

      Only before any project ideas have been generated

    Correct answer
    B

    While the project is underway

    Explanation

    Monitoring takes place after a project begins so the company can check whether the objectives identified initially are being met.

  13. 13

    What is the main purpose of a post-audit after a project is complete?

    1. A

      To replace the company's future project-selection process

    2. B

      To decide whether the original project idea should be generated

    3. C

      To check whether the assumptions held and the objectives were met

    4. D

      To ensure that the project had the lowest possible initial cost

    Correct answer
    C

    To check whether the assumptions held and the objectives were met

    Explanation

    A post-audit verifies whether the original assumptions were valid and whether the project's objectives were achieved.

  14. 14

    If a post-audit finds that assumptions did not hold or objectives were missed, what should the company do?

    1. A

      Identify lessons that can be applied to future projects

    2. B

      Treat the original assumptions as correct regardless of outcomes

    3. C

      Ignore the results because the project has already ended

    4. D

      Automatically repeat the same project without changes

    Correct answer
    A

    Identify lessons that can be applied to future projects

    Explanation

    When a project does not meet expectations, the company should identify lessons that can improve future projects.

  15. 15

    A company can reduce maintenance costs by replacing an old machine, but the new machine requires an investment. What question should guide the replacement decision?

    1. A

      Has the old machine produced accounting income in every prior year?

    2. B

      Will the new machine eliminate the need to evaluate future projects?

    3. C

      Can the company avoid considering the timing of the savings?

    4. D

      Do the expected maintenance savings justify the new machine's cost?

    Correct answer
    D

    Do the expected maintenance savings justify the new machine's cost?

    Explanation

    A replacement decision weighs the cost of the new machine against the maintenance savings it is expected to produce.

  16. 16

    A company already makes a product and is considering expanding its factory or building another factory to make the same product. What category is this?

    1. A

      A mandatory project

    2. B

      A replacement project

    3. C

      An expansion project

    4. D

      A new-products project

    Correct answer
    C

    An expansion project

    Explanation

    Expansion projects involve increasing production of an existing product, such as by expanding a factory or building another one.

  17. 17

    A company considers diversifying into related products or services. Which project category best describes this decision?

    1. A

      A new products and services project

    2. B

      A replacement project

    3. C

      An expansion project involving only existing production

    4. D

      A mandatory project

    Correct answer
    A

    A new products and services project

    Explanation

    New products and services projects concern whether a company should diversify or offer additional, often related, products or services.

  18. 18

    Why might a company conduct relatively little analysis of a mandatory project?

    1. A

      The project replaces the need to follow company strategy

    2. B

      The project has no costs that could be compared

    3. C

      The project is required by a government or regulatory authority

    4. D

      The project is guaranteed to produce positive cash flows

    Correct answer
    C

    The project is required by a government or regulatory authority

    Explanation

    Mandatory projects are required by government or regulators, so the decision about whether to undertake them is generally limited.

  19. 19

    If several methods can satisfy a regulatory requirement, how might capital budgeting help?

    1. A

      It can remove the need to compare the methods' costs

    2. B

      It can determine which method allows the company to avoid the requirement

    3. C

      It can show that every method must be adopted simultaneously

    4. D

      It can help identify which method meets the requirement at the lowest cost

    Correct answer
    D

    It can help identify which method meets the requirement at the lowest cost

    Explanation

    When multiple approaches can meet a requirement, the company may use capital budgeting to choose the method that can be executed at the lowest cost.

  20. 20

    Why should capital budgeting decisions generally use cash flows rather than accounting income?

    1. A

      Accounting income always excludes costs, while cash flows always include every cost

    2. B

      Accounting income measures only future cash, while cash flows measure only past events

    3. C

      Accounting income relies on accrual-based assumptions, while decisions concern actual cash generated

    4. D

      Cash flows do not change over time, while accounting income changes each period

    Correct answer
    C

    Accounting income relies on accrual-based assumptions, while decisions concern actual cash generated

    Explanation

    Accounting income is based on assumptions and accrual accounting, whereas capital budgeting decisions focus on the actual cash a project generates.

  21. 21

    Two projects each return 200, but one pays at the end of year 1 and the other at the end of year 10. Why is the earlier payment generally more valuable?

    1. A

      Receiving cash sooner increases its value because timing matters

    2. B

      Receiving cash sooner means the project has no opportunity cost

    3. C

      Receiving cash later eliminates the need to consider discounting

    4. D

      Receiving cash sooner makes the later project's stated amount smaller

    Correct answer
    A

    Receiving cash sooner increases its value because timing matters

    Explanation

    The timing of cash flows is crucial because of the time value of money. Receiving the same amount sooner makes it more valuable.

  22. 22

    When a capital budgeting problem assumes that cash flows during a year occur at the end of that year, what is the effect?

    1. A

      It generally produces a more conservative, lower NPV than recognizing earlier cash flows

    2. B

      It generally produces a higher NPV because cash flows are delayed

    3. C

      It converts all future cash flows into accounting income

    4. D

      It makes the timing of cash flows irrelevant to the decision

    Correct answer
    A

    It generally produces a more conservative, lower NPV than recognizing earlier cash flows

    Explanation

    Placing intermediate cash flows at the end of the period delays their assumed receipt and generally lowers NPV compared with recognizing that they occur earlier.

  23. 23

    If a project has a positive NPV even when its within-year cash flows are assumed to arrive at year-end, what follows if those cash flows actually arrive earlier?

    1. A

      The project must have a negative NPV when evaluated using actual timing

    2. B

      The project is likely to be more profitable than the conservative estimate suggests

    3. C

      The project's NPV must be unchanged because the amounts are the same

    4. D

      The project should be rejected because early cash flows cannot be discounted

    Correct answer
    B

    The project is likely to be more profitable than the conservative estimate suggests

    Explanation

    Earlier receipts have greater present value. Therefore, a positive NPV under the conservative year-end assumption implies that earlier actual receipts would make the project more profitable.

  24. 24

    What is an opportunity cost?

    1. A

      A cost that appears only in a company's accounting statements

    2. B

      A financing payment that is included in the discount rate

    3. C

      The value of the next-best alternative that is given up

    4. D

      A cost that was incurred in the past and cannot be recovered

    Correct answer
    C

    The value of the next-best alternative that is given up

    Explanation

    An opportunity cost is the value of the next-best alternative that is forgone when a choice is made.

  25. 25

    A person uses a gifted shop for a business earning net cash flow of 40 per month, even though the shop could be rented out for 50 per month. How should the rental opportunity affect the decision?

    1. A

      Treat the forgone rental income as an opportunity cost, making the business's net advantage negative 10 per month

    2. B

      Add the rental income to the business cash flow, making the net advantage 90 per month

    3. C

      Ignore the rental income because it is not an explicit payment, leaving a net advantage of 40 per month

    4. D

      Treat the rental income as a sunk cost, making the business's net advantage positive 10 per month

    Correct answer
    A

    Treat the forgone rental income as an opportunity cost, making the business's net advantage negative 10 per month

    Explanation

    The shop's rental value is an opportunity cost even though no rent is paid. Comparing the business's 40 monthly cash flow with the 50 forgone rental income gives a net advantage of negative 10.

  26. 26

    Which cash flow should be used in capital budgeting when taxes are due on a project's returns?

    1. A

      The project's accounting income before depreciation

    2. B

      The cash flow before taxes

    3. C

      The cash flow remaining after taxes

    4. D

      The project's revenue before operating costs

    Correct answer
    C

    The cash flow remaining after taxes

    Explanation

    Capital budgeting analysis should use after-tax cash flows because taxes reduce the cash available to the company.

  27. 27

    Why are financing costs generally not subtracted from project cash flows in capital budgeting?

    1. A

      They have no effect on the value of a project under any circumstances

    2. B

      They are already included in the project's accounting income in every case

    3. C

      They are reflected in the discount rate, so subtracting them separately would double-count them

    4. D

      They are never paid by companies undertaking long-term projects

    Correct answer
    C

    They are reflected in the discount rate, so subtracting them separately would double-count them

    Explanation

    Financing costs are incorporated into the discount rate. Subtracting them from cash flows as well would count them twice.

  28. 28

    A company has already spent 100 on a project. It can invest another 100 now to receive future cash flows with a present value of 150. Which comparison is relevant to the current decision?

    1. A

      Compare the future value of 150 with the total historical and new spending of 200

    2. B

      Compare the future value of 150 with the original spending of 100 only

    3. C

      Compare the new investment of 100 with the past spending of 100 only

    4. D

      Compare the future value of 150 with the new investment of 100

    Correct answer
    D

    Compare the future value of 150 with the new investment of 100

    Explanation

    The first 100 has already been spent and is a sunk cost. The current decision should compare the future benefit of 150 with the new investment of 100.

  29. 29

    Why should a sunk cost be excluded from a current investment decision?

    1. A

      It will be repaid automatically if the project is rejected

    2. B

      It represents the project's expected future cash inflow

    3. C

      It has already been incurred and cannot be recovered by changing the current decision

    4. D

      It is always equal to the project's opportunity cost

    Correct answer
    C

    It has already been incurred and cannot be recovered by changing the current decision

    Explanation

    Sunk costs are past costs that cannot be recovered. The current choice should depend on future costs and benefits that can still be affected.

  30. 30

    If a project has a large past sunk cost, but its future benefits exceed the additional investment required now, how should the company decide?

    1. A

      Reject the project whenever total historical spending exceeds future benefits

    2. B

      Continue only if the original sunk cost can first be recovered

    3. C

      Add the sunk cost to the discount rate before evaluating future cash flows

    4. D

      Evaluate the future benefits against the additional investment, ignoring the sunk cost

    Correct answer
    D

    Evaluate the future benefits against the additional investment, ignoring the sunk cost

    Explanation

    A past cost should not determine a current decision. The company should compare the additional cost now with the benefits expected in the future.

  31. 31

    An old machine costs 100 per period to maintain, while a new machine would cost 75 per period to maintain. What is the incremental maintenance benefit of replacing it?

    1. A

      A cost increase of 25 per period

    2. B

      A cost increase of 100 per period

    3. C

      A saving of 75 per period

    4. D

      A saving of 25 per period

    Correct answer
    D

    A saving of 25 per period

    Explanation

    The incremental saving is the difference between the old and new maintenance costs: 100 minus 75, or 25 per period.

  32. 32

    For the machine replacement described, which cash flows should be included in the evaluation?

    1. A

      The new machine's cost of 200 and the maintenance savings of 25 per period

    2. B

      The new machine's cost of 200 and the old maintenance cost of 100 per period

    3. C

      The old machine's maintenance cost of 100 and the new maintenance cost of 75, without the purchase cost

    4. D

      The new machine's maintenance cost of 75 and the old machine's purchase cost

    Correct answer
    A

    The new machine's cost of 200 and the maintenance savings of 25 per period

    Explanation

    Incremental analysis includes the new machine's investment cost and the change in maintenance cost. The relevant benefit is the 25-per-period saving.

  33. 33

    A replacement project produces annual maintenance savings for 10 periods. What else is needed to complete an NPV evaluation?

    1. A

      An assumption about the discount rate

    2. B

      A forecast of accounting income for unrelated products

    3. C

      The old machine's original purchase price as a sunk cost

    4. D

      The company's total number of employees

    Correct answer
    A

    An assumption about the discount rate

    Explanation

    The investment cost and incremental savings are not enough to calculate NPV; the analysis also requires a discount rate.

  34. 34

    A chips business is expected to create cash flow of 100 per period and also increase cash flow from the company's soft-drink business by 20 per period. How should the additional 20 be treated?

    1. A

      Subtract it because it is not generated by the chips product itself

    2. B

      Include it as a positive externality caused by the chips project

    3. C

      Exclude it because it arises from a different product line

    4. D

      Treat it as a sunk cost from the soft-drink business

    Correct answer
    B

    Include it as a positive externality caused by the chips project

    Explanation

    The chips project creates a positive effect on the existing soft-drink business. This positive externality should be included when evaluating the project.

  35. 35

    A company introduces a diet beverage that generates cash flow but reduces sales of its regular beverage. How should the lost sales be treated?

    1. A

      Exclude the lost sales because they come from an existing product

    2. B

      Ignore the effect because only the new product's cash flow matters

    3. C

      Treat the lost sales as a positive externality of the new product

    4. D

      Include the negative externality, also known as cannibalization

    Correct answer
    D

    Include the negative externality, also known as cannibalization

    Explanation

    The new product's negative impact on the existing product is a negative externality, often called cannibalizing sales, and should be included in the decision.

  36. 36

    What pattern defines a conventional cash flow?

    1. A

      A sequence containing only inflows and no initial investment

    2. B

      An initial inflow followed by outflows, with multiple sign changes

    3. C

      An initial investment outflow followed by inflows, with only one sign change

    4. D

      Inflows and outflows that alternate sign in every period

    Correct answer
    C

    An initial investment outflow followed by inflows, with only one sign change

    Explanation

    A conventional cash flow begins with an initial investment, shown as a negative amount, and is followed by inflows. It has only one sign change.

  37. 37

    A project requires an initial investment, produces inflows for several years, and then requires another investment. How should its cash-flow pattern be classified?

    1. A

      Non-conventional, because it has more than one sign change

    2. B

      Independent, because it has several cash-flow periods

    3. C

      Mutually exclusive, because a later investment is required

    4. D

      Conventional, because every project begins with an investment

    Correct answer
    A

    Non-conventional, because it has more than one sign change

    Explanation

    A cash-flow pattern with an investment outflow, subsequent inflows, and another outflow has more than one sign change, making it non-conventional.

  38. 38

    What makes two projects independent?

    1. A

      The two projects must generate identical cash flows

    2. B

      The company must choose exactly one of the two projects

    3. C

      The projects must be completed in a particular sequence

    4. D

      The decision to undertake one project does not affect the decision to undertake the other

    Correct answer
    D

    The decision to undertake one project does not affect the decision to undertake the other

    Explanation

    Independent projects can be evaluated and accepted separately because the decision about one does not depend on the decision about the other.

  39. 39

    Projects C and D are mutually exclusive. What does that imply?

    1. A

      The company can evaluate neither project without evaluating a third

    2. B

      The company must undertake C before it can consider D

    3. C

      The company must undertake both if either has positive NPV

    4. D

      The company can undertake one of them, but not both

    Correct answer
    D

    The company can undertake one of them, but not both

    Explanation

    Mutually exclusive projects are alternatives: the company chooses one project rather than undertaking both.

  40. 40

    A factory can install either a conveyor belt or a fleet of forklift trucks for the same purpose, and it generally does not make sense to use both. How are the choices classified?

    1. A

      As mutually exclusive projects

    2. B

      As conventional cash flows

    3. C

      As independent projects

    4. D

      As mandatory projects

    Correct answer
    A

    As mutually exclusive projects

    Explanation

    The conveyor belt and forklift fleet are alternatives where choosing one generally rules out choosing the other, so they are mutually exclusive projects.

  41. 41

    What does project sequencing mean?

    1. A

      Choosing exactly one project from a set of alternatives

    2. B

      Accepting every profitable project at the same time

    3. C

      Undertaking one project and using its results and economic conditions to inform a later project

    4. D

      Ignoring later project decisions until the company has spent all its funds

    Correct answer
    C

    Undertaking one project and using its results and economic conditions to inform a later project

    Explanation

    Projects may be sequenced over time: the company undertakes one project and then uses its results and economic conditions to guide a later decision.

  42. 42

    What does a company with unlimited funds have the capacity to do, according to the capital budgeting distinction?

    1. A

      Undertake any positive-NPV projects it wants

    2. B

      Fund projects only when they are legally mandatory

    3. C

      Undertake only the single project with the lowest initial cost

    4. D

      Avoid evaluating projects' cash flows and discount rates

    Correct answer
    A

    Undertake any positive-NPV projects it wants

    Explanation

    Unlimited funds means the company has sufficient funding to engage in any positive-NPV projects it wants.

  43. 43

    What characterizes capital rationing?

    1. A

      The company is required to undertake every proposed project

    2. B

      The company has limited capital and must allocate it among projects

    3. C

      The company has enough funds for every project with positive NPV

    4. D

      The company can fund projects only after completing a post-audit

    Correct answer
    B

    The company has limited capital and must allocate it among projects

    Explanation

    Under capital rationing, the company has a limited budget and must decide how to allocate that capital among competing projects.