Process Costing and Equivalent Units

Process Costing and Equivalent Units

Costing methods: job order versus process costing

Managerial accounting uses different costing systems depending on how a company makes its products.

Job order costing

Job order costing tracks costs separately for each identifiable job, customer, or custom order. It is appropriate when production consists of distinct jobs or relatively small batches.

  • A job cost sheet records the materials, labor, and manufacturing overhead assigned to that job.

  • Costs from different departments are gathered on the same job cost sheet as the job moves through production.

  • The company typically uses a separate work in process account for each job.

  • Examples include custom orders and made-to-order products.

Process costing

Process costing is used when a company repeatedly produces large quantities of standardized products through a continuous or long-running production process.

  • Costs are accumulated by department or production process rather than by individual job.

  • Each production department has its own work in process account.

  • A department records the costs it adds and the costs it receives from the prior department.

  • When units are completed in one department, their costs are transferred to the next department.

  • Process costing does not usually require a separate cost sheet for each unit or batch.

A manufacturer producing millions of identical cookies is a strong example of a process-costing setting. Cookie production might involve mixing, shaping, baking, filling, assembling, and packaging departments. By contrast, a home baker making small batches of different cookie flavors might use job order costing, depending on how the work is organized.

The central distinction: Job order costing traces costs to individual jobs; process costing accumulates costs by department for large volumes of similar products.


Product costs and production costs

Production costs are accumulated as materials are used and work is performed. The basic manufacturing cost categories are:

  • Direct materials: Materials that become part of the product and can be traced to it, such as wood used to make drumsticks.

  • Direct labor: Labor directly involved in making the product.

  • Manufacturing overhead: Other manufacturing costs, such as factory electricity, rent, insurance, and indirect production costs.

  • Conversion costs: Direct labor plus manufacturing overhead. These costs convert raw materials into finished products.

  • Prime costs: Direct materials plus direct labor.

Shipping and administrative costs are not production costs. Selling and administrative expenses are generally period costs, which are expensed in the period incurred rather than included in inventory.

In process costing, materials can be relatively straightforward to track: a quantity of wood sufficient for a specified number of drumstick pairs identifies the batch of units being produced. A department may also add materials later, such as shrink wrap, cardboard boxes, or labels. Adding these materials increases the product’s cost but does not by itself increase the number of product units being made.

Conversion costs are more difficult to assign to units still in production. Labor is incurred as employees work, and overhead costs such as electricity and rent continue over time. As a result, some units may be finished while others remain only partly converted at the end of an accounting period.


How production costs move through departments

Costs accumulate as products move through production.

For example, a drumstick manufacturer may use two departments:

  1. Shaping department: Receives wood, shapes it into drumsticks, and adds its labor and overhead.

  2. Packaging department: Receives the shaped drumsticks and adds packaging materials, labor, and overhead.

The shaping department transfers the costs of completed units to the packaging department. The packaging department adds its own costs to the costs received. When packaging is complete, the accumulated costs are transferred to finished goods.

Costs therefore build up cumulatively. The costs transferred into a department are not a replacement for that department’s own costs: the department retains the incoming costs and adds its own costs to them.

Department-level work in process

Each department has a separate work in process account. This allows managers to determine how much cost each department adds and to evaluate departmental performance. A company with three production departments would generally maintain a separate work in process account for each one.

Generic journal-entry flow

The cost flow can be represented with entries such as:

  • When materials are used: debit the relevant department’s work in process and credit raw materials.

  • When labor and overhead are assigned: debit the department’s work in process and credit the relevant payroll or overhead accounts.

  • When completed units move to the next department: debit the receiving department’s work in process and credit the sending department’s work in process.

  • When the final department completes the units: debit finished goods and credit that department’s work in process.

The same product costs are carried forward as the units move through the production process.


Equivalent units of production

Why equivalent units are needed

At the end of a period, a department may have both completed units and partially completed units. Partially completed units cannot be treated as fully finished for conversion-cost purposes, because they have not received all the labor and overhead required by the department.

Equivalent units express partially completed production as the number of fully completed units that would represent the same amount of work.

For example, if 200200200 units are each 50%50\%50% complete for conversion, their conversion work is equivalent to 100100100 fully converted units:

200×50%=100 equivalent units200 \times 50\% = 100 \text{ equivalent units}200×50%=100 equivalent units

The equivalent-unit idea is similar to combining partial items: several partly completed units can represent the work required to complete a smaller number of whole units.

Equivalent units for materials and conversion

Materials and conversion may have different completion levels.

  • In the examples discussed, materials are treated as 100% complete for all units because the relevant materials are introduced at the start of production. Material equivalent units therefore equal the number of units being accounted for.

  • Conversion equivalent units depend on how much labor and overhead have been applied to the ending work in process.

  • The ending work in process’s conversion percentage is the percentage needed for the calculation. A percentage describing beginning inventory is not used for this ending-inventory calculation.

In actual production settings, material completion depends on when materials are added. If materials are introduced at a later production stage, their equivalent units may not equal the total units.

Calculation

For ending work in process:

Ending conversion equivalent units=Ending units in process×Conversion completion percentage\text{Ending conversion equivalent units} = \text{Ending units in process} \times \text{Conversion completion percentage}Ending conversion equivalent units=Ending units in process×Conversion completion percentage

Total conversion equivalent units are:

Total conversion equivalent units=Units completed and transferred out+Ending conversion equivalent units\text{Total conversion equivalent units} = \text{Units completed and transferred out} + \text{Ending conversion equivalent units}Total conversion equivalent units=Units completed and transferred out+Ending conversion equivalent units

The four-step process-costing calculation

A department’s production costs can be assigned by working through the following steps in order.

1. Determine the physical units to account for

Units to account for consist of beginning work in process plus units started or transferred into the department during the period:

Units to account for=Beginning work in process units+Units started or transferred in\text{Units to account for} = \text{Beginning work in process units} + \text{Units started or transferred in}Units to account for=Beginning work in process units+Units started or transferred in

2. Determine how the units are accounted for

The units to account for must equal the units completed and transferred out plus the ending work in process:

Units accounted for=Units completed and transferred out+Ending work in process units\text{Units accounted for} = \text{Units completed and transferred out} + \text{Ending work in process units}Units accounted for=Units completed and transferred out+Ending work in process units

These two totals must match. This relationship can be used to find a missing number.

3. Calculate equivalent units and cost per equivalent unit

Calculate equivalent units for materials and conversion separately. Then divide the relevant total costs by the equivalent units for each cost category:

Material cost per equivalent unit=Total material costMaterial equivalent units\text{Material cost per equivalent unit} = \frac{\text{Total material cost}} {\text{Material equivalent units}}Material cost per equivalent unit=Material equivalent unitsTotal material cost​
Conversion cost per equivalent unit=Total conversion costConversion equivalent units\text{Conversion cost per equivalent unit} = \frac{\text{Total conversion cost}} {\text{Conversion equivalent units}}Conversion cost per equivalent unit=Conversion equivalent unitsTotal conversion cost​

The total cost per completed unit is the sum of the material and conversion costs per equivalent unit:

Total cost per unit=Material cost per equivalent unit+Conversion cost per equivalent unit\text{Total cost per unit} = \text{Material cost per equivalent unit} + \text{Conversion cost per equivalent unit}Total cost per unit=Material cost per equivalent unit+Conversion cost per equivalent unit

The method shown combines beginning work in process costs with costs added during the period, then divides by the applicable equivalent units. This is a weighted-average style calculation.

4. Assign costs to completed units and ending work in process

Completed units are fully complete for the department’s materials and conversion. Their cost can be calculated using the total cost per unit:

Cost transferred out=Completed units×Total cost per unit\text{Cost transferred out} = \text{Completed units} \times \text{Total cost per unit}Cost transferred out=Completed units×Total cost per unit

Ending work in process must be costed separately for materials and conversion, because the equivalent units may differ:

Ending WIP material cost=Material equivalent units in ending WIP×Material cost per equivalent unit\text{Ending WIP material cost} = \text{Material equivalent units in ending WIP} \times \text{Material cost per equivalent unit}Ending WIP material cost=Material equivalent units in ending WIP×Material cost per equivalent unit
Ending WIP conversion cost=Conversion equivalent units in ending WIP×Conversion cost per equivalent unit\text{Ending WIP conversion cost} = \text{Conversion equivalent units in ending WIP} \times \text{Conversion cost per equivalent unit}Ending WIP conversion cost=Conversion equivalent units in ending WIP×Conversion cost per equivalent unit
Total ending WIP cost=Ending WIP material cost+Ending WIP conversion cost\text{Total ending WIP cost} = \text{Ending WIP material cost} + \text{Ending WIP conversion cost}Total ending WIP cost=Ending WIP material cost+Ending WIP conversion cost

The total costs assigned to completed units and ending work in process should equal the costs available to account for. Small differences can result if per-unit costs are rounded before all calculations are completed.


Worked examples

Shaping department: units started and partly converted

A shaping department starts 8,7008{,}7008,700 pairs of drumsticks. It completes and transfers out 7,5007{,}5007,500 pairs, leaving 1,2001{,}2001,200 pairs in ending work in process. The ending units are 35%35\%35% complete for conversion.

The physical units reconcile:

8,700=7,500+1,2008{,}700 = 7{,}500 + 1{,}2008,700=7,500+1,200

Ending conversion equivalent units are:

1,200×35%=4201{,}200 \times 35\% = 4201,200×35%=420

Total conversion equivalent units are:

7,500+420=7,9207{,}500 + 420 = 7{,}9207,500+420=7,920

If materials are fully added at the start, material equivalent units are 8,7008{,}7008,700. The material and conversion cost rates must be calculated using their respective equivalent-unit totals; the total physical units should not be used as the conversion denominator when some units are only partly converted.

Direct unit cost already provided

A company starts 100,000100{,}000100,000 units and has 20,00020{,}00020,000 units in ending work in process. The material cost is 6 per unit and the conversion cost is 8 per unit.

Completed and transferred-out units are:

100,000−20,000=80,000100{,}000 - 20{,}000 = 80{,}000100,000−20,000=80,000

The total cost per completed unit is:

$\6 + 8 = 14

Therefore,thecosttransferredoutis:Therefore, the cost transferred out is:Therefore,thecosttransferredoutis:

80{,}000 \times 14 = 1{,}120{,}000 $$

The ending work in process is stated to be 75%75\%75% complete for conversion, but that percentage is not needed to calculate the transferred-out cost when both per-unit cost amounts are already given. It would be relevant if conversion equivalent units or ending work in process conversion cost had to be calculated.

Paint department: calculating costs from total costs

A paint department has 8,7008{,}7008,700 units to account for, completes and transfers out 7,5007{,}5007,500, and leaves 1,2001{,}2001,200 units in ending work in process. The ending work in process is 30%30\%30% complete for conversion. Total material cost is 10,353, and total conversion cost is 26,970.

Ending conversion equivalent units are:

1,200×30%=3601{,}200 \times 30\% = 3601,200×30%=360

Total conversion equivalent units are:

7,500+360=7,8607{,}500 + 360 = 7{,}8607,500+360=7,860

Material cost per equivalent unit is:

$\frac{\10{,}353}{8{,}700} = 1.19

Conversioncostperequivalentunitisapproximately:Conversion cost per equivalent unit is approximately:Conversioncostperequivalentunitisapproximately:

\frac{26{,}970}{7{,}860} \approx 3.43 $$

Using the rounded rates, the total cost per completed unit is approximately 4.62. The cost transferred out is therefore approximately:

$7{,}500 \times \4.62 = 34{,}650

Endingworkinprocessiscalculatedbycostcategory:Ending work in process is calculated by cost category:Endingworkinprocessiscalculatedbycostcategory:

1{,}200 \times 1.19 = 1{,}428

360 \times 3.43 = 1{,}234.80

1{,}428 + 1{,}234.80 = 2{,}662.80 $$

The unrounded conversion rate should be used when exact reconciliation is required, because rounding the cost per equivalent unit can produce small differences.

Packaging department: costs received from another department

A packaging department has 750750750 units in beginning work in process and receives 7,5007{,}5007,500 units from the shaping department. It therefore has:

750+7,500=8,250 units to account for750 + 7{,}500 = 8{,}250 \text{ units to account for}750+7,500=8,250 units to account for

It completes and transfers out 6,5006{,}5006,500 units, leaving:

8,250−6,500=1,750 units in ending work in process8{,}250 - 6{,}500 = 1{,}750 \text{ units in ending work in process}8,250−6,500=1,750 units in ending work in process

The ending work in process is 40%40\%40% complete for conversion:

1,750×40%=700 conversion equivalent units1{,}750 \times 40\% = 700 \text{ conversion equivalent units}1,750×40%=700 conversion equivalent units

Total conversion equivalent units are:

6,500+700=7,2006{,}500 + 700 = 7{,}2006,500+700=7,200

The department includes costs carried in from shaping as well as costs added in packaging. For example, packaging may add its own materials, such as shrink wrap or boxes, and its own labor and overhead. Costs are divided by the appropriate equivalent units to find cost per unit, then assigned to units transferred out and ending work in process.

Units-only example with beginning inventory

A department has 1,7001{,}7001,700 units in beginning inventory and starts 8,5508{,}5508,550 additional units. It transfers out 9,0009{,}0009,000 units. Ending work in process is 60%60\%60% complete for conversion.

Units to account for are:

1,700+8,550=10,2501{,}700 + 8{,}550 = 10{,}2501,700+8,550=10,250

Ending work in process is:

10,250−9,000=1,25010{,}250 - 9{,}000 = 1{,}25010,250−9,000=1,250

Ending conversion equivalent units are:

1,250×60%=7501{,}250 \times 60\% = 7501,250×60%=750

Total conversion equivalent units are:

9,000+750=9,7509{,}000 + 750 = 9{,}7509,000+750=9,750

If materials are fully added at the start, material equivalent units are 10,25010{,}25010,250. The 40%40\%40% completion figure for beginning inventory, if provided, is not used to calculate equivalent units for ending work in process.

Department receiving transferred-in costs

A department may receive 10,000 of material costs and 10,000 of conversion costs from a prior department, then add its own material and conversion costs. If the equivalent units are already given as 20,00020{,}00020,000 for materials and 18,00018{,}00018,000 for conversion, the department first combines incoming and added costs within the relevant categories. It then divides total material cost by material equivalent units and total conversion cost by conversion equivalent units.

The incoming costs remain part of the product’s accumulated cost; they are added to, not substituted for, the costs incurred in the receiving department.


Review of prime costs, conversion costs, and period costs

A separate cost example has 1,450 of direct materials, 909090 direct labor hours at 15.50 per hour, manufacturing overhead equal to 150%150\%150% of direct labor cost, and 2,500 of selling and administrative expenses.

Direct labor cost is:

$90 \times \15.50 = 1{,}395

Primecostsaredirectmaterialsplusdirectlabor:Prime costs are direct materials plus direct labor:Primecostsaredirectmaterialsplusdirectlabor:

1{,}450 + 1{,}395 = 2{,}845

Manufacturingoverheadis:Manufacturing overhead is:Manufacturingoverheadis:

1{,}395 \times 150 = 2{,}092.50

Conversioncostsaredirectlaborplusmanufacturingoverhead:Conversion costs are direct labor plus manufacturing overhead:Conversioncostsaredirectlaborplusmanufacturingoverhead:

1{,}395 + 2{,}092.50 = 3{,}487.50

Totalproductcostsaredirectmaterials,directlabor,andmanufacturingoverhead:Total product costs are direct materials, direct labor, and manufacturing overhead:Totalproductcostsaredirectmaterials,directlabor,andmanufacturingoverhead:

1{,}450 + 1{,}395 + 2{,}092.50 = 4{,}937.50 $$

Selling and administrative expenses are period costs, totaling 2,500. If 1,4501{,}4501,450 units are produced, the material cost per unit is:

$\frac{\1{,}450}{1{,}450} = 1 \text{ per unit} $$


Practical checks and common errors

  • Reconcile physical units first. Units to account for must equal units completed and transferred out plus ending work in process.

  • Use the ending work in process conversion percentage to calculate ending conversion equivalent units.

  • Do not treat partially converted units as fully converted. Multiply the ending units by their conversion percentage.

  • Keep materials and conversion separate. They may have different equivalent-unit totals and different cost-per-unit rates.

  • Do not divide total costs by total physical units to get conversion cost per unit when some units are only partly converted. Use total conversion equivalent units.

  • Completed and transferred-out units are fully complete for the sending department. Their unit count is the same in the total, materials, and conversion columns.

  • Carry transferred-in costs forward. A receiving department adds its own costs to the costs received from the prior department.

  • Use unrounded unit costs when possible. Rounding too early can cause assigned costs to differ slightly from the total costs available.

  • Do not confuse product costs with period costs. Manufacturing costs become part of inventory; selling and administrative expenses are period costs.