Project Management Simplified
- 27Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
What is the definition of a project according to PMI?
27 questions
- 1
What is the definition of a project according to PMI?
Model answer
A project is a temporary endeavor undertaken to create a unique product, service, or result.
Explanation
The key characteristics are that it has a defined beginning and end (temporary) and produces something unique.
- 2
What is the main difference between a project and operations?
Model answer
A project is temporary and ends upon completion, while operations are ongoing and repetitive.
Explanation
Projects are finite with a specific goal, whereas operations are continuous business activities.
- 3
Define a program in project management.
Model answer
A program is a group of related projects managed together to achieve benefits not available from managing them individually.
Explanation
Programs coordinate multiple projects to deliver broader outcomes.
- 4
Define a portfolio in project management.
Model answer
A portfolio is a collection of programs, projects, and other work grouped to facilitate effective management and meet strategic business objectives.
Explanation
Portfolios are at the highest level, aligning initiatives with organizational strategy.
- 5
What two methodologies are needed to run any project?
Model answer
A project life cycle and project management process groups.
Explanation
The project life cycle defines the phases of the project, while process groups define the management activities.
- 6
What is a project life cycle?
Model answer
A project life cycle is a set of sequential phases that a project passes through from initiation to closure; it is unique and customizable to the project.
Explanation
Phases vary by industry and organization; examples include conceiving, birth, childhood, etc. for human development, or design, coding, testing for IT.
- 7
List the five process groups in project management according to PMI.
Model answer
Initiation, Planning, Executing, Monitoring and Controlling, and Closing.
Explanation
These process groups are applied in a fixed order and are not customizable, though processes within them can be adapted.
- 8
Why is it incorrect to say that a project life cycle consists of initiation, planning, executing, monitoring and controlling, and closing?
Model answer
Because those are process groups, not the project life cycle; the life cycle consists of unique phases specific to the project, while process groups are management phases applied to each phase (or to the whole project).
Explanation
Confusing the two is a common cause of PMP exam failure.
- 9
What are the two key processes in the initiation process group?
Model answer
Developing the project charter and identifying stakeholders.
Explanation
The project charter authorizes the project, and stakeholder identification creates a register of all parties affected.
- 10
What is the purpose of a project charter?
Model answer
To gain buy-in from the project sponsor and senior leadership to proceed with planning; it serves as a checkpoint to approve or kill the project early.
Explanation
The charter is a high-level document outlining objectives, scope, rough cost and time, key stakeholders, and milestones.
- 11
What is a stakeholder register and who is typically the primary stakeholder?
Model answer
A stakeholder register is a list of all stakeholders; the primary stakeholder is the project sponsor.
Explanation
Stakeholder identification is kept simple during initiation; detailed analysis occurs in planning.
- 12
What three main questions does the planning process group aim to answer?
Model answer
What are we going to do? How are we going to do it? How will we know when the project is done?
Explanation
The output is a comprehensive project plan covering requirements, scope, WBS, schedule, cost, and quality.
- 13
What is the goal of collecting requirements?
Model answer
To understand what stakeholders want from the project.
Explanation
Methods include meetings, interviews, Delphi technique, and nominal group technique; it's best to get stakeholders together to resolve contradictions.
- 14
What is included in a project scope statement?
Model answer
Product scope, project scope, deliverables, product acceptance criteria, exclusions (what is not part of the project), constraints, and assumptions.
Explanation
The scope statement defines the boundaries of the project and must be specific to avoid ambiguity.
- 15
What three components make up the scope baseline?
Model answer
The project scope statement, the Work Breakdown Structure (WBS), and the WBS dictionary.
Explanation
The scope baseline is used to measure and control scope throughout the project.
- 16
What is a Work Breakdown Structure (WBS)?
Model answer
A WBS is a hierarchical decomposition of the total scope into smaller, manageable work packages; it is deliverable-oriented (things, not actions) according to PMI.
Explanation
Each level breaks down further until cost and time can be confidently estimated.
- 17
What is the purpose of a WBS dictionary?
Model answer
To define each work package in detail, preventing scope creep by clarifying what is included.
Explanation
The dictionary describes the work package, deliverables, acceptance criteria, and other relevant information.
- 18
What is scope creep?
Model answer
Scope creep is the uncontrolled expansion of project scope without adjustments to time, cost, or resources.
Explanation
It often occurs when stakeholders add requirements after planning; project managers must protect the scope baseline.
- 19
What is the process for estimating time in project management?
Model answer
Estimate durations for each work package (or activity if further decomposed), then sequence the activities to create a schedule, often using a Gantt chart.
Explanation
If you cannot confidently estimate a work package, break it down further to the activity level.
- 20
Define fast tracking and crashing in project scheduling.
Model answer
Fast tracking means performing activities in parallel to shorten the schedule; crashing means adding resources to activities to reduce durations, which increases cost.
Explanation
Both are schedule compression techniques; crashing always increases cost.
- 21
How is cost estimating typically performed using the WBS?
Model answer
By bottom-up estimating: each work package is estimated for cost, then rolled up to the project level.
Explanation
Contingency reserves (often 20% in practice) are added to create the cost baseline; management reserves are added for the budget.
- 22
What is the main focus of the executing process group?
Model answer
To complete the work defined in the project management plan and meet project objectives; the project manager guides the team and manages stakeholder expectations.
Explanation
Execution is where the actual work is done; a good plan makes execution smooth.
- 23
What is gold plating in project management?
Model answer
Gold plating is making changes or adding features that are outside the agreed project scope without proper authorization.
Explanation
It is a form of scope creep that project managers must resist during execution.
- 24
What is the purpose of the monitoring and controlling process group?
Model answer
To measure project performance against the plan, manage change requests, and ensure KPIs are met; it runs parallel to execution.
Explanation
Activities include monitoring scope, schedule, cost, quality, risks, and procurement.
- 25
How is earned value calculated?
Model answer
Earned value = Total project budget × percentage of work completed.
Explanation
For example, a 1Mprojectthatis20200,000.
- 26
Why might earned value not be accurate for all projects?
Model answer
Because many projects exhibit exponential growth rather than linear progress, so value is not evenly distributed over time.
Explanation
Earned value assumes linear progression, but real projects often have compounding results.
- 27
List five activities typically performed during the closing process group.
Model answer
Hand over the product to the client and obtain sign-off; finish procurements and make final payments; gather lessons learned; release resources; and celebrate.
Explanation
Closing ensures all project work is completed and administrative closure is achieved.