Capital Budgeting Techniques
Capital Budgeting Techniques: Discounted Evaluation Methods
Capital budgeting methods evaluate whether a long-term investment project should be accepted or rejected. These methods are broadly divided into:
Non-discounting techniques: Do not consider the time value of money.
Payback period
Accounting rate of return (ARR)
Discounting techniques: Consider the time value of money by converting future cash flows into present values.
Discounted payback period
Profitability index (PI)
Net present value (NPV)
Internal rate of return (IRR)
Discounting techniques are generally preferred because a sum received today is worth more than the same sum received in the future.
Discounted Payback Period
The discounted payback period is the time required to recover the initial investment from the present value of future cash inflows.
Unlike the ordinary payback period, discounted payback period accounts for the time value of money. Future cash inflows are discounted using a required rate of return or discount rate.
Calculation process
Identify the initial cash outflow.
Determine the appropriate discount rate.
Calculate the present value factor for each future year:
where:
r = discount rate
t = number of years into the future
Multiply each cash inflow by its present value factor:
Add the discounted cash inflows cumulatively until the initial investment is recovered.
If recovery occurs during a year, calculate the fractional year required.
Example using a 10% discount rate
At a discount rate of 10%:
Present value factor in Year 0 = 1.00
Present value factor in Year 1:
If the Year 1 cash inflow is $30:
The same process is applied to all future cash inflows. In the examples discussed, the discounted payback periods were approximately:
4.05 years for one project
3.21 years for another project
Interpretation
A shorter discounted payback period generally indicates faster recovery of the investment. However, it does not necessarily identify the project that creates the greatest total wealth because cash flows received after the payback period are ignored.
Profitability Index
The profitability index (PI) is the ratio of the present value of future cash inflows to the present value of the initial cash outflow.
For a conventional project, the initial investment is usually the primary cash outflow.
Decision rule
PI greater than 1: Accept the project.
PI equal to 1: The project is financially indifferent; it earns exactly the required return.
PI less than 1: Reject the project.
A PI greater than 1 means that the present value of the expected inflows exceeds the present value of the investment.
Net profitability index
The net profitability index expresses the excess of the profitability index over the break-even value of 1:
For example, if:
then:
This indicates that the present value of inflows exceeds the present value of the outflow by 25% relative to the investment.
Example
Using a 10% discount rate, a project was calculated to have:
Present value of cash inflows = 40.56 in the relevant units
NPV = positive
PI = 1.25
Because the PI is greater than 1 and the NPV is positive, the project should be accepted.
Another project produced:
PI = 1.189
NPV = 26.51
This project should also be accepted because both measures indicate that it creates value.
Net Present Value
The net present value (NPV) is the difference between the present value of cash inflows and the present value of cash outflows.
More generally:
where:
CFt = cash flow in year t
r = discount rate
n = project life
C0 = initial investment
Decision rule
NPV greater than 0: Accept the project.
NPV equal to 0: The project earns exactly the required return; acceptance depends on other considerations.
NPV less than 0: Reject the project.
A positive NPV means that the project is expected to add wealth after covering the initial investment and the required return.
Difference between NPV and PI
NPV and PI use the same discounted cash-flow information, but they express the result differently:
NPV: Measures the absolute amount of value added.
PI: Measures the value created per unit of investment.
Thus:
whereas:
Advantages of NPV
Considers all cash flows
NPV includes every project cash flow, including cash flows received after the payback period. This is an important advantage over the ordinary and discounted payback methods.
Considers the time value of money
Future cash flows are discounted to their present values. Cash flows received at different times are therefore compared on a consistent basis.
Supports wealth maximization
The central objective of NPV is to maximize the wealth of the firm’s shareholders or stakeholders by accepting projects that add value.
Satisfies value additivity
NPVs of individual projects can be added together. This is known as the value additivity principle, and it allows the value contribution of multiple projects to be evaluated collectively.
Limitation of NPV
The major limitation is that the discount rate must be known in advance. The analyst must determine an appropriate required rate of return or cost of capital before calculating NPV.
Example of NPV and PI calculation
Suppose a project has cash inflows over several years and a discount rate of 10%. The present value factors are approximately:
Year 0: 1.00
Year 1: 0.90
Year 2: 0.82
Year 3: 0.75
Year 4: 0.68
Year 5: 0.62
Each cash flow is multiplied by its corresponding factor. The discounted cash flows are then added and compared with the initial investment.
If the calculation produces:
NPV = 40.56 in the relevant units
PI = 1.25
then the project is accepted because the NPV is positive and the PI exceeds 1.
Internal Rate of Return
The internal rate of return (IRR) is the discount rate at which the project’s NPV equals zero.
At this rate, the present value of the project’s cash inflows exactly equals the present value of its cash outflows.
Decision rule
The project’s IRR is compared with its cost of capital:
IRR greater than cost of capital: Accept the project.
IRR equal to cost of capital: The project is financially indifferent.
IRR less than cost of capital: Reject the project.
The cost of capital represents the minimum return required by investors and lenders for providing funds to the project.
Relationship between discount rate and NPV
As the discount rate increases, the present value of future cash inflows decreases. Consequently, NPV also decreases.
At a relatively low discount rate, NPV may be positive.
As the discount rate rises, NPV moves downward.
At the IRR, NPV equals zero.
At discount rates above the IRR, NPV becomes negative.
This relationship is generally nonlinear. However, over a small interval between two nearby discount rates, the curve can be approximated as a straight line. This permits interpolation.
Calculating IRR Through Trial and Error
IRR is usually calculated through a trial-and-error process:
Select a discount rate.
Calculate the project’s NPV.
If NPV is positive, increase the discount rate.
If NPV is negative, decrease the discount rate.
Continue until two rates are found:
One producing a slightly positive NPV
One producing a slightly negative NPV
Interpolate between the two rates.
The two rates should be as close together as practical so that the linear approximation is more accurate.
Interpolation formula
The approximate IRR is:
where:
r0 = lower discount rate producing a positive NPV
r1 = higher discount rate producing a negative NPV
NPV0 = positive NPV at r0
NPV1 = negative NPV at r1
An equivalent form is:
The difference between the two NPVs is used to estimate the point at which NPV crosses zero.
IRR Calculation Example
Consider a five-year project with the following cash flows:
Initial investment: −160
Year 1 inflow: 30
Year 2 inflow: 40
Year 3 inflow: 50
Year 4 inflow: 60
Year 5 inflow: 100
Trial at an 18% discount rate
The present value factors are approximately:
Year 0: 1.000
Year 1: 0.847
Year 2: 0.718
Year 3: 0.609
Year 4: 0.516
Year 5: 0.437
The discounted cash flows are approximately:
Year 0: −160.00
Year 1: 30×0.847=25.42
Year 2: 40×0.718=28.73
Year 3: 50×0.609=30.43
Year 4: 60×0.516=30.95
Year 5: 100×0.437=43.71
The resulting NPV is approximately:
Therefore, the NPV is slightly negative at 18%.
Trial at a 17% discount rate
The present value factors are approximately:
Year 0: 1.000
Year 1: 0.855
Year 2: 0.731
Year 3: 0.624
Year 4: 0.534
Year 5: 0.456
The discounted cash flows are approximately:
Year 0: −160.00
Year 1: 30×0.855=25.64
Year 2: 40×0.731=29.22
Year 3: 50×0.624=31.22
Year 4: 60×0.534=32.02
Year 5: 100×0.456=45.61
The resulting NPV is approximately:
Therefore:
At 17%, NPV is positive.
At 18%, NPV is negative.
The IRR lies between 17% and 18%.
Interpolation
Using:
r0=17%
r1=18%
NPV0=3.71
NPV1=−0.76
the approximate IRR is:
Thus, the project’s internal rate of return is approximately 17.83%.
Verifying an IRR
A discount rate cannot be called the IRR merely because it produces a positive or negative NPV. It must produce an NPV equal or very close to zero.
For example, if a project evaluated at an 8% discount rate produces an NPV of $419,500, then 8% is not the IRR because:
If the discount rate is increased to 25% and the discounted cash inflows equal the initial outflow, the NPV becomes zero:
Therefore, 25% would be the IRR for that project.
Limitations of IRR
Does not reflect project size
IRR is a percentage measure. It does not show the absolute amount of value created.
For example:
A small project may have a 30% IRR but create only a small amount of value.
A large project may have a 20% IRR but create substantially more total wealth.
Because of this, IRRs from projects of different sizes cannot always be compared meaningfully.
Assumes a constant reinvestment rate
IRR implicitly assumes that interim cash flows can be reinvested at the same rate as the project’s IRR. In reality, future cash flows may be reinvested at different rates depending on market conditions and available projects.
May produce multiple solutions
When cash flows are non-normal, meaning they change signs more than once, the NPV profile may cross the horizontal axis multiple times. In such situations, more than one IRR may exist, making the decision ambiguous.
Choosing Among Capital Budgeting Methods
There is no single method that is best for every practical situation. Some methods perform better than others depending on the purpose of the analysis and the information available.
Firms increasingly rely on discounted cash-flow methods rather than only non-discounted methods because discounted methods recognize the time value of money.
Use of multiple methods
Organizations commonly use several methods together rather than relying on only one:
A project may first be screened using a simple method such as payback period.
Projects that pass the initial screening may then be evaluated using NPV, PI, and IRR.
Management may use additional practical and strategic criteria before making the final decision.
Payback period and ARR are often used as supplementary evaluation methods, while NPV and IRR provide more rigorous financial analysis.
Relative standing of NPV and IRR
NPV is generally considered superior to IRR because it:
Measures actual value added.
Uses the opportunity cost of capital as the discount rate.
Supports the objective of maximizing stakeholder or shareholder wealth.
Avoids some reinvestment and multiple-solution problems associated with IRR.
When all other conditions are equal, NPV and IRR may lead to the same accept-or-reject conclusion. However, they can disagree when projects differ in size, timing of cash flows, or cash-flow patterns.
Why NPV Is Generally Preferred to IRR
Different reinvestment assumptions
IRR assumes that interim project cash flows can be reinvested at the project’s own IRR. This assumption may be unrealistic, particularly when the IRR is very high.
NPV uses the cost of capital or opportunity cost of funds as the discount rate, which is usually a more realistic reinvestment assumption.
Multiple IRRs for non-normal cash flows
If project cash flows change signs multiple times, the project may have several IRRs. NPV does not suffer from this problem because it evaluates the project at a specified discount rate and produces one value.
Better measure of wealth creation
NPV directly measures the amount of value added to the firm. IRR only provides a percentage rate of return and does not indicate how much total wealth the project creates.
Assessment of Capital Budgeting Methods
Capital budgeting methods can be assessed using theoretical and practical criteria.
Theoretical criteria
Consideration of all cash flows
NPV: Considers all project cash flows.
IRR: Considers all project cash flows.
Payback period: Ignores cash flows received after the payback period.
ARR: May not fully reflect all relevant cash flows because it is based on accounting information.
Discounting at the opportunity cost of funds
NPV: Discounts cash flows at the opportunity cost or required rate of return.
IRR: Does not directly use the opportunity cost as its calculation rate; it produces a project-specific rate.
Payback period and ARR: Do not discount cash flows.
Value additivity
The value additivity principle means that the values of separate projects can be combined to determine the total value added by a group of projects.
NPV: Satisfies value additivity.
IRR, payback period, and ARR: Do not provide the same additive value measure.
Wealth maximization
The method most directly aligned with maximizing shareholder or stakeholder wealth is:
NPV: Yes
IRR: Not as directly as NPV
Payback period: No
ARR: No
NPV performs most strongly on the major theoretical criteria because it considers all cash flows, discounts them using the opportunity cost of funds, satisfies value additivity, and directly measures wealth creation.
Practical criteria
Simplicity
Payback period: Usually the simplest method.
ARR: Relatively simple because it uses accounting information.
NPV: More involved because it requires discounting each cash flow.
IRR: Can be more complicated because it often requires trial and error or financial software.
Use with limited information
Payback period: Can be used when only basic cash-flow information is available.
ARR: Can also be used with relatively limited information.
NPV and IRR: Require more detailed cash-flow estimates and a suitable discount rate or cost of capital.
Relative versus absolute measurement
IRR: Provides a relative percentage measure.
ARR: Provides a relative accounting return.
NPV: Provides an absolute measure of value added.
Payback period: Provides a time-based recovery measure rather than a return measure.
Across the theoretical and practical criteria, NPV receives the strongest overall assessment, although other methods remain useful for screening, communication, and supplementary analysis.
Practical Use of Capital Budgeting Techniques
A firm can evaluate the actual popularity of different methods by surveying organizations and asking which capital budgeting techniques they use.
A useful survey process would be:
Prepare a list of available methods, such as:
Payback period
ARR
Discounted payback period
PI
NPV
IRR
Ask firms whether they use each method.
Ask them to rank the methods by frequency or importance.
Compare the rankings across firms or industries.
Such surveys typically show that firms use multiple methods. Discounted techniques, especially NPV and IRR, are widely used, while payback period and ARR often continue to serve as supplementary screening tools.
A sound capital budgeting decision usually combines NPV with other methods rather than relying on a single measure. NPV is generally the strongest primary method because it measures value creation using all discounted project cash flows.

Ask anything
We've read this whole study set, so questions about it get the best answers.