Capital Budgeting Techniques

Speaker 1Speaker 2

Capital Budgeting Techniques

8:58
0:00-8:58
  1. Michael

    Good morning, everyone. In our earlier discussion of capital budgeting, we divided techniques into two broad groups: non-discounting techniques and discounting techniques. Payback period and accounting rate of return, or ARR, are non-discounting methods, and both have important drawbacks.

  2. Corey

    Right. The discounting methods try to correct one of those major weaknesses by recognizing the time value of money. In other words, cash received in the future is converted into its present value using a discounting factor.

  3. Michael

    The first discounting method is discounted payback period. Instead of simply adding future cash inflows, we first calculate the present value of each inflow. For example, with a ten-percent discount rate, the present value factor for the initial year is 1, and for the first year it is 1 divided by 1.10, or about 0.90.

  4. Corey

    So if the first-year cash inflow is 30, its present value is 30 multiplied by 0.90, which equals 27. We do the same calculation for each later year, accumulate the discounted cash inflows, and determine when the original cash outflow has been recovered.

  5. Michael

    Exactly. That recovery time is the discounted payback period. In the examples discussed, the discounted payback periods were 4.05 years and 3.21 years. The important distinction is that these figures use discounted cash flows rather than the original undiscounted amounts.

  6. Corey

    The next method is profitability index, or PI. PI is a ratio: the present value of cash inflows divided by the present value of cash outflows.

  7. Michael

    The decision rule is straightforward. If profitability index is 1 or greater, the project is considered profitable and should be accepted. If it is below 1, the project should not be accepted. Net profitability index is calculated as profitability index minus 1.

  8. Corey

    Let’s connect that with an example. In one question, after discounting the cash inflows at ten percent, the total present value was 40.56, and the profitability index was 1.25. Since the index exceeded 1, the project was accepted.

  9. Michael

    Another example produced a profitability index of 1.189 and a net present value of 26.51. Both results support accepting the project: the profitability index is above 1, and the NPV is positive.

  10. Corey

    That brings us to net present value, or NPV, the third discounted capital budgeting technique. NPV is the difference between the present value of cash inflows and the present value of cash outflows.

  11. Michael

    That is the key contrast with PI. PI gives us a ratio of present-value inflows to present-value outflows, while NPV gives us the absolute difference between them. A positive NPV means the present value of inflows exceeds the present value of outflows.

  12. Corey

    NPV is widely used because it considers all cash flows, including cash flows received after the payback period. It also considers the time value of money, and its objective is to maximize the wealth of stakeholders.

  13. Michael

    There is, however, a limitation: you need to know the discount rate in advance. That discounting factor is an input to the NPV calculation, so not knowing it makes the method difficult to apply.

  14. Corey

    In the ten-percent example, the present value factors for years one through five were approximately 0.90, 0.82, 0.75, 0.68, and 0.62. Multiplying each cash flow by its corresponding factor and adding the results gave an NPV of 40.56, which was positive.

  15. Michael

    And because the profitability index in that example was 1.25, the conclusion was the same under both methods: accept the project. This shows how the calculations differ while the decision can agree.

  16. Corey

    Now let’s move to internal rate of return, or IRR. IRR is the discount rate at which a project’s NPV becomes exactly zero.

  17. Michael

    The decision rule is to accept a project when its IRR exceeds the cost of capital. If IRR is less than the cost of capital, the project should be rejected. So IRR compares the project’s calculated rate of return with the return required by the cost of capital.

  18. Corey

    The relationship between the discount rate and NPV is important here. As the discount rate increases, NPV decreases. On a graph, discount rate appears on the horizontal axis and NPV on the vertical axis, and the IRR is the point where the curve reaches NPV equal to zero.

  19. Michael

    The relationship is not actually linear. But for calculation purposes, we can take a small section of the curve and treat that section as approximately linear. That is why interpolation is used after finding two discount rates: one that produces a positive NPV and another that produces a negative NPV.

  20. Corey

    The process is basically trial and error. We keep changing the discount rate until we find two consecutive rates that place NPV on opposite sides of zero. Then we interpolate between them.

  21. Michael

    In the interpolation formula, r0 is the rate at which NPV is just positive, NPV0 is that positive NPV, and NPV1 is the negative NPV at the higher rate. The estimate can be written as: IRR equals r0 plus NPV0 divided by NPV0 minus NPV1, multiplied by the difference between the two rates.

  22. Corey

    Let’s apply it to the five-year example. The initial cash outflow was 160, followed by inflows of 30, 40, 50, 60, and 100 in years one through five.

  23. Michael

    At an eighteen-percent discount rate, the present value factors were approximately 0.847, 0.718, 0.609, 0.516, and 0.437 for years one through five. After multiplying each inflow by its factor and including the initial outflow, the NPV was negative 0.76.

  24. Corey

    Then the same calculation at seventeen percent produced an NPV of positive 3.71. So the IRR lies between seventeen and eighteen percent.

  25. Michael

    Interpolating between those two rates gives an IRR of approximately 17.83 percent. Notice why both rates are needed: one gives a positive NPV and the other gives a negative NPV, allowing us to estimate the rate where NPV would be zero.

  26. Corey

    There was another example where an eight-percent discount rate produced an NPV of 419,500. That rate cannot be called the IRR because the NPV is positive rather than zero.

  27. Michael

    When the rate was changed to twenty-five percent, the discounted cash flows produced an NPV of zero. That confirms the definition: the discount rate at which NPV becomes zero is the project’s IRR.

  28. Corey

    IRR is useful, but it has complications. First, it does not account for the size of the project. A small project and a large project can each have an IRR, but those percentages alone do not make the projects directly comparable.

  29. Michael

    Second, IRR assumes that cash flows can be reinvested at a constant rate. In real life, cash may be invested at different rates, so that assumption may not hold. Also, when cash flows are not normal, IRR can sometimes produce multiple solutions.

  30. Corey

    That helps explain why NPV is often preferred to IRR. IRR assumes the same rate of return is available for other projects, while NPV uses the opportunity cost of funds as the discount rate.

  31. Michael

    When all other conditions are held constant, NPV and IRR may lead to the same project findings. Even so, NPV generally ranks higher because it considers all cash flows, discounts them at the opportunity cost of funds, satisfies the principle of value additivity, and directly supports maximizing stakeholder or shareholder wealth.

  32. Corey

    The methods can also be compared using practical criteria. Payback period is the simplest method, and ARR and payback can be used when information is limited. NPV and IRR require more information, especially an appropriate discount rate.

  33. Michael

    IRR and ARR provide relative measures, while NPV provides an absolute value measure. In the comparison across seven theoretical and practical criteria, NPV received a positive assessment on five, which is why it was described as the best among the methods considered.

  34. Corey

    Still, the conclusion is not that one method must replace every other method. There is no single best method for every situation. Firms often use multiple evaluation methods, with one method used for initial screening and another for a second level of screening.

  35. Michael

    In practice, firms increasingly use discounting techniques rather than only non-discounting techniques. IRR remains one of the most popular evaluation methods, while payback period and ARR are often used as supplementary methods.

  36. Corey

    A useful way to study actual business practice would be to survey different firms. Give them a list of the capital budgeting methods covered, ask which ones they use, and have them rank the methods from most to least widely used.

  37. Michael

    So the main takeaway is this: discounted payback adjusts payback for the time value of money; PI compares present-value inflows with present-value outflows; NPV subtracts present-value outflows from inflows and focuses on wealth creation; and IRR is the rate that makes NPV zero.

  38. Corey

    And when choosing among methods, remember the broader conclusion: NPV has the strongest theoretical support, IRR is widely used but has important limitations, and payback period and ARR can still serve as supplementary or screening tools.