What is a project?

Tap to flipClick to flipspace

A time-limited endeavor that creates a unique product, service, or result.

Or swipe the card

106 cards

  1. What is a project?

    A time-limited endeavor that creates a unique product, service, or result.

  2. Why should a project create a unique result?

    To achieve a specific business goal.

  3. What is project management?

    Applying skills, knowledge, and tools to increase a project’s chances of achieving its business objective.

  4. What are the start and end of a project useful for understanding?

    They define the project’s time limits; most project work happens between them.

  5. What is a project life cycle?

    The phases into which a project is divided to make it more manageable.

  6. Why can project phases require different management approaches?

    Phases may involve work of different kinds, so their processes and tools may need to differ.

  7. What phases might appear in a large software project?

    Pre-sales, initiation, concept development, prototyping, planning, requirements definition, UI design, development, integration, testing, deployment, hypercare, maintenance, and handoff, closure, or support.

  8. How do phases typically differ between large and small projects?

    Large-project phases may each last weeks or months and act like subprojects; on small projects, phases often blend together.

  9. How should a project manager choose life cycles and approaches to learn?

    Focus on the typical life cycles used in the industry and niche where they plan to work; often only two or three are needed.

  10. Why must project management fit the organization’s environment?

    Organizations have their own processes, policies, and tools; ignoring them creates friction and inefficiency.

  11. Is there one standard project management approach that every company uses?

    No. Companies tailor their approaches to their own needs.

  12. What does the content suggest about project management certifications and real-world effectiveness?

    A popular certification alone does not necessarily make someone a better real-world project manager.

  13. Who is a project stakeholder?

    An individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a project decision, activity, or outcome.

  14. Who are examples of project stakeholders?

    Clients, project owners, the project manager’s boss, team members, and subject matter experts.

  15. Why should a project manager identify stakeholders?

    Stakeholders may gain or lose because of the project, and they may provide important requirements.

  16. What are the basic tools and activities for managing stakeholders?

    Record stakeholder information in a stakeholder register, analyze stakeholders, and decide how to interact with each one.

  17. What two broad kinds of requirements can stakeholders provide?

    Requirements for the product or service, and requirements for the project management approach used in their environment.

  18. Who is responsible for collecting project requirements from stakeholders?

    The project manager is responsible for ensuring that all stakeholder requirements are collected.

  19. Why should key stakeholders be identified early and revisited throughout a project?

    Early identification helps surface important requirements, while continued attention catches stakeholders who emerge later.

  20. Which external stakeholders may need attention?

    Stakeholders from the client side and from the project’s industry or niche who may affect the project.

  21. What is a possible consequence of missing an environmental stakeholder on a construction project?

    The project may violate environmental policies, requiring fines, rework, extra expense, or changes such as replacing a heating system.

  22. What typically begins the pre-sales phase in a client-vendor project?

    A client with a business need contacts a vendor’s sales team because it lacks the expertise or human resources to meet that need.

  23. What is negotiated during pre-sales?

    The client and vendor negotiate the contract’s terms and conditions.

  24. How might a project manager support the sales team during pre-sales?

    By doing high-level planning to estimate project duration and budget and help make the proposed terms realistic.

  25. When should risk management begin?

    In the pre-sales phase, and it should continue throughout the project.

  26. What is a simple way to identify risks during project activities?

    Ask the team and stakeholders, “Do you see any risk here?” and record identified risks in a risk register.

  27. What usually results from the pre-sales phase?

    A contract signed with the client.

  28. If a project manager did not participate in pre-sales, what should they obtain?

    Access to the relevant notes, emails, and agreements from that phase.

  29. What contract details can become constraints on a project?

    A strict deadline or a total budget.

  30. What is project initiation?

    The transition from sales and contract negotiations into project management.

  31. What three things should be identified when initiating a project?

    The business objective, the unique result to be produced, and the project boundaries.

  32. What is a project charter?

    A brief document containing high-level information about a project before detailed planning begins.

  33. What information does a project charter commonly include?

    Project description, business case, objectives, preassigned resources, stakeholders, known requirements, major deliverables, assumptions, constraints, and known risks.

  34. How detailed should a project charter be?

    It should be concise—generally no more than five pages, with shorter being better.

  35. How can a project charter be created and shared?

    It can be a simple text document, such as a Word or Google document, an email, or information kept in a project management tool.

  36. How does discussing the project charter with project owners help?

    It builds common understanding, reduces miscommunication, and helps manage client expectations about scope, boundaries, and constraints.

  37. How should the project charter guide later project decisions?

    Future efforts should align with its business goal and case; question work that does not align.

  38. What should a project manager consider when selecting a management approach after charter approval?

    The charter, contract, organizational environment, and available tools, processes, and templates.

  39. How should a project manager choose a project management framework?

    Choose among the options available in the organization’s established life cycles and approaches, then adjust them as needed for the project.

  40. Does every project require a fully written project management plan?

    No. Some industries require a formal plan, but many projects can use a less formal plan if stakeholders understand how the project will be managed.

  41. What is a useful exercise for learning how a project management system works?

    List the organization’s processes, tools, templates, and workflows across project management domains, then show how they interact.

  42. Which project management domains are suggested for mapping in that exercise?

    Integration, scope, time, cost, budget, quality, risk, stakeholders, communication, resources, and procurement management.

  43. What are the two fundamental principles for project planning?

    Plan specifically to reach the charter’s objective, and elaborate on the high-level information captured in the charter.

  44. How should clients change project objectives after planning has begun?

    They should update the project charter, allowing the project manager to renegotiate scope, budget, and timeline.

  45. Why should planning stay within the project’s agreed purpose and boundaries?

    To avoid spending resources on work the client did not request and to keep expanding demands within the project’s constraints.

  46. What is rolling wave planning?

    A progressive planning technique that details imminent requirements while keeping more distant requirements at a high level.

  47. What should rolling wave planning include for future requirements?

    High-level plans for scope, budget, schedule, risks, and other project aspects, with enough time and resources allowed for uncertainty.

  48. How does rolling wave planning affect detailed planning effort?

    The team plans the next few weeks in detail and keeps the rest at a higher level, updating the plan during execution.

  49. What is the purpose of collecting business requirements?

    To understand what the client needs the project to achieve.

  50. Whose requirements should be gathered during project planning?

    Business requirements from clients and stakeholder requirements from clients and relevant subject matter experts.

  51. How are high-level requirements developed into more detailed requirements?

    Break them into smaller pieces and, when needed, create specifications, user stories, mockups, or wireframes.

  52. What is the role of project team members and subject matter experts in requirements work?

    They help develop solutions and specific product or system requirements.

  53. Why does stakeholder identification continue during planning?

    New stakeholders may emerge and provide additional requirements.

  54. What is a requirements traceability matrix?

    A spreadsheet that maps requirements to their requesting stakeholders, project objectives, WBS elements, and other project aspects.

  55. Why is requirements traceability useful when assigning requirements to deliverables?

    It helps map requirements to specific deliverables so requirements are not overlooked.

  56. Who may be specifically trained to collect requirements professionally?

    A business analyst.

  57. How does quality relate to project scope?

    Product quality is part of the project scope.

  58. What is a project deliverable?

    A tangible result or part of the project that the team creates.

  59. What determines which deliverables a project should produce?

    The industry and nature of the project influence common deliverables, while the team must decide which requirements belong in each deliverable.

  60. What is a project scope statement?

    A clear description of all project deliverables and how they will be created.

  61. Why should clients review and ideally sign the project scope statement?

    To confirm that they understand and agree to the deliverables and believe those results will help achieve the business objectives.

  62. What is project scope in practical terms?

    The description of all the work the project team must do to create the agreed deliverables.

  63. What is a work breakdown structure (WBS)?

    A tool for breaking down the project scope and identifying all of the project work.

  64. What should be transferred into the WBS after the scope statement is approved?

    The agreed deliverables from the scope statement.

  65. What are the main levels or components of a WBS?

    Major deliverables are decomposed into smaller work packages, which are then broken down into tasks.

  66. What qualities should WBS deliverables and work packages have?

    They should be tangible results that can be completed and tested; work packages are smaller pieces of those results.

  67. How should WBS elements be identified and arranged?

    Give them unique identifiers that clearly show their position in the structure.

  68. What is a practical rule of thumb for sizing a work package?

    Make it small enough to fit within a reporting period.

  69. What does it suggest if a piece of work cannot logically be placed under a major WBS deliverable?

    The project scope may not have been fully identified, which can be a warning sign of scope creep.

  70. What is a practical guideline for sizing a task?

    Ideally, one team member should be able to complete it from start to finish; a preferred duration is no more than about three working days.

  71. What is a make-or-buy decision?

    A decision about whether to produce a project deliverable using the organization’s own resources or outsource it.

  72. Why should project information generally be kept in one project management tool?

    It helps centralize information and manage the many task attributes and dependencies more efficiently than manual tracking.

  73. Why should a project manager understand the principles behind project management software?

    The software only processes what users enter; incorrect planning principles can produce a misleading picture.

  74. Why should project managers preserve client-approved deliverable names in the WBS?

    It helps retain the meaning the client agreed to in the scope statement.

  75. What resource categories should be considered when planning a task?

    People and their skills and expertise, as well as equipment, materials, and tools.

  76. What should a project manager do about people resources if the team is not yet assembled?

    Create role descriptions for recruitment and identify when the roles are needed.

  77. How might an organization provide people for a project?

    The project manager may negotiate for people from an internal pool or hire them.

  78. What is a human resources acquisition plan?

    A list of vacant project roles and the dates when those roles need to join the team.

  79. What is a procurement management plan?

    A plan for how and when the project will acquire equipment, tools, and materials.

  80. Why do resource acquisition plans affect the project schedule?

    Hiring people or obtaining equipment and materials can take time, so resources may need to be acquired well before their tasks begin.

  81. Who should estimate task duration when a project team is already in place?

    The team members who will perform the work.

  82. Who should help estimate task duration when the project team has not yet been assembled?

    A preassigned expert.

  83. When estimating duration, whose productivity should be considered?

    The average productivity of the role at the identified experience level, not the unusually high productivity of an expert estimator.

  84. What information supports building a draft project schedule?

    Task durations and dependencies between tasks.

  85. How does bottom-up estimating produce a draft project budget?

    Estimate each task, summarize task estimates into work packages, and then summarize work packages into deliverables.

  86. When might a software team use effort estimates instead of estimating each task’s resources, duration, and cost separately?

    When a prepared team is already available or the organization uses in-house resources and focuses on leveling effort.

  87. What is qualitative risk analysis?

    An assessment of identified risks that helps determine which risks are most critical to address.

  88. What is the basic sequence for managing project risks?

    Identify risks, record them, analyze them, select critical risks, develop responses, then monitor risks and implement responses during execution.

  89. What is a risk response plan?

    A specific action plan for addressing a risk, including who will carry it out and what resources it requires.

  90. How should risk responses be incorporated into the project plan?

    Add the response work to the project scope, schedule, and budget.

  91. What should be checked when a risk response introduces new processes or tools?

    Check that they work with existing processes and tools and that stakeholders accept the changes.

  92. What should happen after risk responses change the project management plan?

    Validate that the updated plan is still feasible by revisiting the relevant planning checks.

  93. What is a project baseline?

    The final approved version of the project scope, schedule, and budget.

  94. How do baselines help project managers control a project?

    They provide planned values to compare with actual values and help track progress toward the original goal.

  95. What should a project manager do when actual performance deviates from the plan?

    Work to bring performance back toward the baseline; seek a baseline change only when the deviation is too large to manage within the existing plan.

  96. What kinds of project baselines may need to change through a change request?

    The project’s deadlines, budget, or scope of work.

  97. What should be checked before approving a major baseline change?

    Confirm that the revised plan is feasible and is unlikely to require another change request for the same problem soon afterward.

  98. Why is a project management plan not sufficient by itself to execute a project?

    It outlines the work but does not solve technical problems, resolve conflicts, or motivate people.

  99. What are core project manager responsibilities during execution?

    Facilitate interactions, motivate the team, help resolve technical problems, resolve conflicts, remove impediments, and track progress.

  100. What should a project manager focus on each day and a few days ahead?

    Ensure the team is working on the right tasks today and check ahead for blockers.

  101. What is a daily project information maintenance routine?

    A regular period—up to about half an hour—to ensure team members record progress, time, expenses, risks, and other performance data in the project tool.

  102. What is the purpose of a daily team sync-up?

    Team members report progress and problems, giving the project manager a chance to correct the team’s work if needed.

  103. Why hold regular sync-ups with clients and project owners?

    To keep them informed and engaged in the project.

  104. What is a daily motivational routine?

    Set aside time to connect meaningfully with one or two team members each day rather than waiting for a special occasion.

  105. How can a project manager make email and meeting communication more manageable?

    Reply to emails at a few intentional times each day and batch meetings to preserve blocks of time for focused work.

  106. What does ongoing rolling wave planning require during execution?

    Continue working with the team to collect requirements, identify needed roles, estimate future tasks, and add detail to the schedule and budget.