What is a project, and what makes its result distinctive?
85 questions
- 1
What is a project, and what makes its result distinctive?
Model answer
A project is a time-limited endeavor that creates a unique product, service, or result to achieve a specific business goal.
Explanation
Projects have a defined beginning and end, and their intended results are unique and connected to a business objective.
- 2
How is project management defined in relation to a project's business objective?
Model answer
Project management applies skills, knowledge, and tools to increase the likelihood that a project will achieve its business objective.
Explanation
The purpose is not simply to produce something, but to help the project reach its intended business goal.
- 3
Why should project managers focus on business goals rather than producing deliverables for their own sake?
Model answer
Connecting project work to business goals helps produce results that matter, improves client satisfaction, and supports project success.
Explanation
A project can create a product or service yet still fail if that result does not help achieve the intended business objective.
- 4
What is a project life cycle, and why is a project divided into phases?
Model answer
A project life cycle is the sequence of phases through which a project proceeds. Dividing work into phases makes a project more manageable and groups work that produces parts of the project.
Explanation
Phases organize a project into more manageable segments, often with different kinds of work and specific outputs.
- 5
Name several possible phases of a large software development project.
Model answer
Possible phases include pre-sales, initiation, concept development, prototyping, planning, requirements definition, UI design, development, integration, testing, deployment, hypercare, maintenance, handoff, and closure or support.
Explanation
These are examples of phases that may occur; a project does not necessarily use every phase.
- 6
How can phase size and phase boundaries differ between large and small projects?
Model answer
A phase in a large project may take weeks or months and be managed like a small subproject. In a small project, phases may overlap or be difficult to distinguish.
Explanation
The scale and organization of a project affect how clearly its phases can be separated.
- 7
Why might a project manager use different processes or tools in different phases of one project?
Model answer
Phases can involve different kinds of work, so each may need processes, tools, or project management approaches suited to that work.
Explanation
For example, an iterative approach may suit software implementation, while task and due-date tracking may be sufficient for a handoff phase.
- 8
How do an industry and professional niche influence the project life cycles a project manager should learn?
Model answer
They influence which life cycles and project management approaches are commonly available, so a project manager can focus on the few typical cycles relevant to that work.
Explanation
The content suggests that someone working mainly in one industry may need to learn only two or three typical life cycles.
- 9
Why must a project manager align the project approach with the organization where the project is run?
Model answer
Organizations have their own processes, policies, and tools; ignoring them can create friction and inefficiency.
Explanation
A project is conducted within an organizational environment rather than in isolation.
- 10
Why is there no single standard project management approach used identically by every organization?
Model answer
Organizations tailor their project management approaches to their own needs, processes, policies, and tools.
Explanation
The resulting approaches differ between organizations rather than forming one universal, seamless method.
- 11
How does an in-house project differ from a project conducted in a client-vendor relationship?
Model answer
An in-house project mainly has one organizational environment to account for. A client-vendor project must reconcile the practices and requirements of both the performing organization and the client's organization.
Explanation
The two organizations in a client-vendor relationship may operate in very different ways.
- 12
What kinds of support can an organizational environment provide to a project?
Model answer
It may provide workspace, hiring support, templates, project management software, lessons learned, best practices, and access to subject matter experts.
Explanation
This support can reduce the burden of organizing workplace resources and let the project manager focus on project work.
- 13
Who qualifies as a project stakeholder?
Model answer
A stakeholder is an individual, group, or organization that may affect, be affected by, or perceive itself to be affected by a project decision, activity, or outcome.
Explanation
Stakeholders may gain or lose because of the project, including people who believe they could be affected.
- 14
Give examples of stakeholders beyond a project's client or owner.
Model answer
A project manager's boss, team members, and subject matter experts can also be stakeholders.
Explanation
Stakeholders are not limited to the people who commission or own the project.
- 15
What tools and activities help a project manager manage stakeholder information?
Model answer
The project manager records stakeholder information in a stakeholder register, analyzes stakeholders, and decides how to engage with each one.
Explanation
Identification, recording, analysis, and planned interaction help organize stakeholder management.
- 16
What two broad kinds of requirements can stakeholders provide?
Model answer
They can provide requirements for the product or service and requirements for the project management approach used in their environment.
Explanation
Stakeholder input can shape both what the project creates and how the project is managed.
- 17
Who is responsible for collecting requirements from all project stakeholders, and what can happen if important requirements are missed?
Model answer
The project manager is responsible for ensuring that requirements are collected. Missing an important stakeholder's requirements can cause rework, extra cost or time, plan changes, and even project failure.
Explanation
An overlooked stakeholder may later use their authority to demand that requirements be added.
- 18
How does failing to identify an environmental organization as a stakeholder affect a house-building project?
Model answer
The project may violate environmental policies, leading to a fine, a required change such as replacing the heating system, extra expense, and rework.
Explanation
The example shows how overlooked stakeholder requirements can create consequences late in a project.
- 19
When should project stakeholders be identified, and which sources of stakeholders should be considered?
Model answer
Key stakeholders should be identified early, with continued searches throughout the project. The project manager should consider internal stakeholders as well as external stakeholders from the client and relevant industry or niche.
Explanation
Stakeholder identification is ongoing because new stakeholders may emerge or become relevant during the project.
- 20
What is a requirements traceability matrix, and what information can it connect?
Model answer
It is a tool, often a spreadsheet, that maps requirements to their stakeholders, the objectives they support, work breakdown structure elements, and other project aspects.
Explanation
The mapping helps track where requirements came from and how they are represented in project work.
- 21
What is the role of a business analyst in requirements work?
Model answer
A business analyst is a role specifically trained to collect requirements professionally.
Explanation
The project manager should work with this dedicated expertise rather than assuming they must personally collect every requirement.
- 22
Why is product quality considered part of project scope?
Model answer
The project must include the work, time, and resources needed to ensure quality and fix defects in its product or service.
Explanation
Quality work must be planned as part of creating the intended project result.
- 23
Why should project managers build working relationships with internal stakeholders before a project begins?
Model answer
Existing relationships help project managers understand and work with internal stakeholders throughout the project, rather than engaging them only at its start.
Explanation
Stakeholder relationships need ongoing attention, not just one-time contact during project initiation.
- 24
What typically triggers the pre-sales phase in a client-vendor project?
Model answer
A client with a business need but without the required expertise or human resources contacts a vendor's sales team for help.
Explanation
Pre-sales begins as the client and potential vendor start exploring a possible engagement.
- 25
How can a project manager contribute during pre-sales?
Model answer
The project manager can help the sales team develop realistic contract terms by doing high-level planning to estimate project duration and budget.
Explanation
This early planning provides visibility before detailed project planning begins.
- 26
Why should risk management begin during pre-sales rather than only during later project planning?
Model answer
Risks can exist before a project starts, including urgent threats that could surface during execution or eliminate the opportunity to proceed.
Explanation
Early risk action can address problems before they become more damaging or undermine project viability.
- 27
Describe a continuous risk management process from identification through execution.
Model answer
Identify risks, record them in a risk register, analyze them qualitatively and, when useful, quantitatively, select critical risks, develop responses, and monitor and implement those responses during execution.
Explanation
Risk management continues throughout the project, although early stages often emphasize identifying urgent and critical risks.
- 28
How can a project manager begin identifying risks in ordinary project activities?
Model answer
The project manager can repeatedly ask the team and stakeholders whether they see any risks and then record identified risks in the risk register.
Explanation
This is a simple way to make risk identification part of ongoing project work.
- 29
What should a project manager know about the pre-sales contract and any agreements made before joining the project?
Model answer
The project manager should understand the contract's terms, constraints such as deadlines or total budget, and the client's goals and agreements discussed during pre-sales.
Explanation
Because a contract may not contain all project details, a project manager who missed pre-sales should seek access to relevant notes, emails, and agreements.
- 30
What is project initiation, and what three fundamental matters should it clarify?
Model answer
Initiation is the transition from sales and contract negotiations into project management. It should clarify the business objective, the unique result to be produced, and the project's boundaries.
Explanation
These matters establish what the project is intended to achieve and the limits within which it will operate.
- 31
What is a project charter, and when is it used?
Model answer
A project charter is a high-level document that captures essential project information before the planning process begins.
Explanation
It provides an initial shared understanding of the project rather than a comprehensive plan.
- 32
What information does a project charter usually contain?
Model answer
It usually includes the project description, business case, objectives, preassigned resources, stakeholders, known requirements, product or service and major deliverables, assumptions, constraints, and risks.
Explanation
These elements capture key information needed to understand the project at a high level.
- 33
Why should a project charter be concise rather than a complete description of the project?
Model answer
The charter is a high-level reference, not a detailed plan, and should be no more than five pages; shorter is preferable.
Explanation
Its purpose is to establish a common understanding before detailed planning.
- 34
How does discussing and approving the project charter help manage client expectations?
Model answer
It clarifies scope, boundaries, and constraints, reveals miscommunication early, and helps determine whether the expected results are realistic.
Explanation
Reviewing the charter with project owners builds a shared understanding before substantial work begins.
- 35
How should the project charter guide decisions made later in the project?
Model answer
Future work should align with the charter's business case and goals, and proposed work that does not align should be questioned.
Explanation
The charter serves as an early reference for keeping project effort focused on its intended objective.
- 36
What should a project manager consider when selecting a project management approach after charter approval?
Model answer
The manager should consider the project life cycle, charter, client, organizational environment, and available tools, processes, and templates, then choose and tailor an available organizational approach.
Explanation
The approach is generally selected from a small number of options in the organization rather than invented from scratch.
- 37
What is the main purpose of a project management plan, and must it always be a formal document?
Model answer
It explains how the project will be managed. Some industries require a formal plan, but many projects can use an informal plan as long as stakeholders understand the approach.
Explanation
The required level of documentation depends on the project's context and organizational or industry requirements.
- 38
What can a project manager learn by mapping organizational processes, tools, templates, and workflows against major project management knowledge areas?
Model answer
The exercise can reveal weaknesses and inefficiencies, systemize the manager's knowledge, and clarify how the organization's project management system works as a whole.
Explanation
It links knowledge areas such as scope, schedule, cost, quality, risk, stakeholders, communication, resources, and procurement to the organization's practices.
- 39
What two principles should guide project planning?
Model answer
Plan specifically to achieve the objective in the charter, and elaborate on the high-level information captured there.
Explanation
These principles help focus project resources on agreed goals and limit uncontrolled expansion of demands.
- 40
How should a project manager respond when clients want to change project objectives?
Model answer
The clients should update the charter so that the project manager can renegotiate scope, budget, and timeline.
Explanation
Changing objectives can be acceptable, but the plan and its constraints need to be reconsidered accordingly.
- 41
How are high-level requirements developed into more detailed requirements during planning?
Model answer
The team breaks high-level requirements into smaller pieces and develops details, potentially using specifications, user stories, mockups, or wireframes.
Explanation
Planning elaborates on the initial requirements so the project team can understand what to create.
- 42
How do business, stakeholder, and product or system requirements relate to one another?
Model answer
The project first gathers business requirements from clients, identifies stakeholder requirements from relevant stakeholders and experts, and then works with the team and experts to define product or system requirements and solutions.
Explanation
This sequence develops specific solutions from business needs and stakeholder input.
- 43
What is rolling wave planning, and when can it be useful?
Model answer
Rolling wave planning details imminent requirements while keeping future requirements at a higher level. It is useful when implementation must begin before all requirements and planning are complete.
Explanation
The approach lets work proceed without requiring detailed planning of the entire project in advance.
- 44
In rolling wave planning, what should still be planned at a high level for future work?
Model answer
Future requirements should still be considered in terms such as scope, budget, schedule, and risks, with enough time and resources allocated to address current uncertainty.
Explanation
Future work is not ignored; it is planned less precisely until more information is available.
- 45
How does rolling wave planning affect project management as execution proceeds?
Model answer
The team plans the near-term work in detail, keeps later work at a high level, and elaborates the plan piece by piece during execution.
Explanation
The project approach and its processes and tools need to accommodate this continuing planning effort.
- 46
What is a project deliverable, and why can mapping requirements to deliverables be challenging?
Model answer
A deliverable is a tangible result or part of the project. Deciding which deliverables contain which requirements can be difficult, but a requirements traceability matrix and work breakdown structure can help map them.
Explanation
The mapping helps ensure requirements are represented in the results the project will produce.
- 47
What does a project scope statement describe, and why should clients understand it?
Model answer
It describes the project deliverables and how they will be created in language clients can understand. This helps confirm that the deliverables are what clients need to achieve their business objectives.
Explanation
Clients may not share the project team's technical or industry knowledge, so the intended results must be made clear.
- 48
Why should clients ideally approve the project scope statement?
Model answer
Approval confirms that clients understand and accept the deliverables the project will spend its allocated resources creating.
Explanation
The scope statement is a checkpoint for agreement before detailed implementation planning.
- 49
What is the work breakdown structure, and what is its relationship to project scope?
Model answer
The work breakdown structure decomposes the entire project scope into organized pieces. Project scope is the description of all work needed to create the deliverables.
Explanation
The WBS turns the agreed scope into a structured representation of project work.
- 50
Why should the names and meanings of deliverables in the work breakdown structure remain consistent with the scope statement?
Model answer
Keeping the client's wording preserves the agreed meaning of deliverables as they are transferred into the work breakdown structure.
Explanation
Consistency helps maintain the connection between what clients approved and the work being planned.
- 51
Why is dedicated project management software useful for planning and tracking a project with many tasks?
Model answer
It can manage task attributes, dependencies, and Gantt charts more efficiently than tracking them manually in a spreadsheet, and it makes plan changes easier to handle.
Explanation
The work breakdown structure commonly provides the starting point for using project management software.
- 52
Why should a project manager understand project management principles instead of relying on software outputs alone?
Model answer
Project management software follows the instructions and data it receives; incorrect principles or inputs can produce a misleading picture of the project.
Explanation
The software is a tool, not a substitute for understanding how to structure and manage project work.
- 53
What are the main components of a work breakdown structure, and how are they arranged?
Model answer
It contains major deliverables and smaller work packages, each with a unique identifier showing its place in the structure. Deliverables from the scope statement form the first decomposition level.
Explanation
Each deliverable is then decomposed into smaller components.
- 54
What characteristics should a work package have, and how small should it generally be?
Model answer
A work package should be a tangible, finishable, and testable piece of work, small enough to fit within a reporting period.
Explanation
This size makes progress easier to report and the work easier to manage.
- 55
What might it indicate if a piece of work cannot be placed under any major deliverable in the work breakdown structure?
Model answer
It may indicate that the project scope is incomplete or that scope creep is occurring.
Explanation
The work breakdown structure is intended to represent all project scope under the agreed deliverables.
- 56
How should work packages be decomposed into tasks, and what task size is suggested in the content?
Model answer
Work packages are broken into tasks that one team member can ideally complete from start to finish; a practical preference is tasks no longer than three working days.
Explanation
This level of decomposition can improve the accuracy of planning and tracking.
- 57
What is a make-or-buy decision, and what is a major consideration in making it?
Model answer
It is a decision about whether to outsource project deliverables or produce them within the organization. A major consideration is whether the organization has the resources and expertise to do the work itself.
Explanation
The decision is considered while planning how project deliverables will be produced.
- 58
What resources should be considered when estimating the work required for a task?
Model answer
Consider people and their skills and expertise, as well as required equipment, materials, and tools.
Explanation
Understanding these needs supports resource planning and task estimation.
- 59
What information does a human resources acquisition plan contain?
Model answer
It lists the vacant project roles and the dates when those roles need to join the team.
Explanation
The plan identifies the project's expected staffing needs over time.
- 60
What does a procurement management plan address?
Model answer
It plans how and when the project will acquire equipment, tools, and materials.
Explanation
The project manager may need to coordinate this planning with the organization's procurement department or manager.
- 61
Why must resource acquisition be considered when developing the project schedule?
Model answer
Hiring people and obtaining equipment or materials can take time, so the schedule must include dates for when resources are needed and expected to be available.
Explanation
Required resources may not be obtainable immediately; hiring, for example, may take months.
- 62
Who should estimate task durations, and whose productivity level should inform those estimates?
Model answer
The project team should estimate its tasks, or a preassigned expert should help if the team is not yet available. Estimates should reflect the average productivity of the role and experience level, not an exceptional expert's speed.
Explanation
The estimator's expertise should not lead to unrealistic assumptions about the average person who will do the work.
- 63
How do task dependencies contribute to the project schedule?
Model answer
Once task information is available, dependencies can be assigned to show how tasks relate and to create a draft project schedule.
Explanation
The draft schedule is then adjusted until it is realistic.
- 64
How does bottom-up estimating produce a draft project budget?
Model answer
Estimate each task's cost, summarize task estimates at the work package level, and then summarize work packages at the deliverable level.
Explanation
The total cost can be built from the smaller work estimates upward.
- 65
How can task estimates differ in organizations that use a prepared team or only in-house resources?
Model answer
Instead of estimating assigned resources, duration, and cost for each task, the team may estimate effort in person-hours for an average role and focus on leveling resources against available effort.
Explanation
This approach may suit software teams already allocated for a period or organizations that use only internal resources.
- 66
Why are the schedule and budget initially considered drafts rather than final plans?
Model answer
Risk management and risk responses may require changes to the project scope, schedule, or budget before the plan can be finalized.
Explanation
The draft estimates need to be revisited after project risks are analyzed and addressed.
- 67
What additional risk management work should be done using a draft project management plan?
Model answer
Conduct dedicated risk identification sessions, complete the analysis, select risks to address, and develop response plans.
Explanation
The draft plan provides a basis for identifying risks associated with the planned project work.
- 68
What makes a risk response plan more than just a proposed idea?
Model answer
It specifies actions and someone to carry them out, and may require money or other resources; those actions and resources must be incorporated into the project plan.
Explanation
A response needs to be planned and executed, not merely recorded.
- 69
How should a risk response plan be represented in the project plan?
Model answer
Its work should be added to project scope and schedule, with any needed time or money included in the budget.
Explanation
Responses may also add processes or tools, which should be checked for compatibility with existing practices and stakeholder acceptance.
- 70
What should a project manager do after updating a plan to include risk responses?
Model answer
Recheck whether the updated plan is feasible by reviewing the relevant planning decisions and assumptions.
Explanation
Risk responses can change the plan enough to require another feasibility check.
- 71
What are project baselines?
Model answer
They are the final approved versions of the project scope, schedule, and budget.
Explanation
Baselines provide approved reference points for tracking project progress.
- 72
How does the planned-route analogy explain the purpose of project baselines?
Model answer
A plotted route gives a ship a path against which to track progress and correct course. Without a route, even a small deviation can lead somewhere unintended.
Explanation
Similarly, project baselines make it possible to compare progress with an approved plan rather than relying only on a general direction.
- 73
What should a project manager compare during execution, and what should happen when the project deviates from its plan?
Model answer
The manager should compare actual values with planned values across project aspects, such as quality, communication, stakeholder engagement, team motivation, and resources. For manageable deviations, corrective action should aim to return to the plan.
Explanation
A project manager executes the project management plan and tracks more than just task completion.
- 74
When should a project manager negotiate a change to project baselines?
Model answer
When a deviation is too large to correct within the existing plan, the manager should negotiate a change to scope, schedule, or budget and confirm the revised plan is feasible.
Explanation
The revised baselines should address the problem sufficiently to avoid needing another change request for the same issue shortly afterward.
- 75
Why does completing the project plan not eliminate the project manager's work during execution?
Model answer
The plan outlines work but does not solve technical problems, resolve conflicts, motivate people, or provide every detailed instruction needed during execution.
Explanation
The project manager must still facilitate people and support delivery of the planned work.
- 76
What people-focused responsibilities does a project manager have during execution?
Model answer
The manager facilitates interaction, encourages problem-solving, resolves conflicts, removes impediments, tracks progress, and supports the team through activities such as meetings, reviews, and training.
Explanation
These activities help people carry out the project work according to the plan.
- 77
Why is communication a substantial part of project management work?
Model answer
Facilitating collaboration, handling issues, and coordinating project activity involve communication through meetings, email, calls, and documentation; the content estimates it may take about 80% of the workday.
Explanation
Communication is embedded in many routine project management responsibilities.
- 78
What should a project manager prioritize in daily team coordination and short-term lookahead?
Model answer
Ensure the team is working on the right tasks today and look a few days ahead to identify blockers.
Explanation
Daily coordination combines attention to current work with preparation for near-future obstacles.
- 79
What is the purpose of a daily project information maintenance routine?
Model answer
It keeps project software current with team progress, time, expenses, risks, and other performance data.
Explanation
Updating information daily is easier than trying to gather it all immediately before a progress report.
- 80
What should a daily team sync-up meeting accomplish?
Model answer
Team members report their progress and problems, giving the project manager an opportunity to correct the team's work if needed.
Explanation
The meeting provides a regular check on daily activity and obstacles.
- 81
Why might a project manager hold daily sync-ups with clients or project owners?
Model answer
Frequent updates help keep project owners informed and engaged.
Explanation
Regular client or owner communication supports ongoing stakeholder involvement.
- 82
What is the purpose of a daily motivational routine?
Model answer
The project manager can spend time connecting meaningfully with one or two team members each day rather than waiting for a special occasion.
Explanation
Small, regular interactions can have a positive effect on motivation.
- 83
How can scheduled communication periods and batched meetings support a project manager's work?
Model answer
Replying to email at chosen times and grouping meetings can help manage communications and create free time for focused work.
Explanation
Intentional scheduling helps prevent communication tasks from consuming the entire day in an unstructured way.
- 84
Why should rolling wave planning continue during project execution?
Model answer
The team needs to keep collecting requirements, identifying vacant roles, estimating future tasks, and adding detail to the schedule and budget as more information becomes available.
Explanation
Near-term planning continues to evolve the project plan as work proceeds.
- 85
How does the character of project planning differ from execution?
Model answer
Planning is an intensive but relatively short period, while execution is a longer daily process that requires routines to maintain control and consistency.
Explanation
The project manager's responsibilities continue well beyond the planning stage.