Project Management Principles
- 96Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
96 questions
- 1A project is a temporary effort created to deliver something_____such as a product, service, or result.
Hint
Consider what distinguishes a project’s output from routine operations.
Answer
unique
Explanation
A project is defined as a temporary effort created to deliver a unique product, service, or result.
- 2Unlike projects,_____are the day-to-day activities of a business.
Hint
Think of ongoing work that keeps an organization functioning.
Answer
operations
Explanation
Operations are day-to-day business activities, while projects are special efforts that drive change or innovation.
- 3Projects are special missions that drive_____or innovation.
Hint
Projects create something different from routine business activity.
Answer
change
Explanation
Projects are distinct from ongoing operations because they are undertaken to drive change or innovation.
- 4Projects have a clear start and end, specific objectives and outputs, and distinct_____.
Hint
Think about the results a project produces.
Answer
outcomes
Explanation
Projects are characterized by defined beginnings and endings, objectives, outputs, and distinct outcomes.
- 5A project is_____because it ends when its goals are achieved or when it becomes clear they will not be met.
Hint
Temporary does not necessarily mean brief; focus on whether the effort has an endpoint.
Answer
finite
Explanation
Projects are finite endeavors. They conclude when their goals are achieved or when it is clear those goals cannot be met.
- 6The temporary nature of a project does not mean that its_____must also be temporary.
Hint
A project can end while the thing it created continues to exist.
Answer
result
Explanation
Although a project is temporary, its result may endure; for example, a monument may last for centuries.
- 7Projects can include repeatable elements, but each combination of stakeholders, objectives, and_____is different.
Hint
Consider the setting in which a project is carried out.
Answer
environments
Explanation
A project can reuse practices and structures while remaining unique because its stakeholders, objectives, and environments differ.
- 8Project management applies skills, tools, and structured techniques to meet stakeholder needs and_____.
Hint
Think of what stakeholders anticipate in addition to what they need.
Answer
expectations
Explanation
Project management uses skills, tools, and structured techniques to meet the needs and expectations of stakeholders.
- 9Project managers balance scope, time, cost, and_____.
Hint
This constraint concerns how well the work or deliverable meets requirements.
Answer
quality
Explanation
Scope, time, cost, and quality are competing considerations that project managers must balance.
- 10Project management connects strategic business goals with real-world_____.
Hint
Think of what strategic goals become when project work is delivered.
Answer
outcomes
Explanation
Project management provides a framework that links organizational strategy to concrete results.
- 11Disciplines such as time management, scope management, and risk management are project management_____.
Hint
These are the organized subject areas that structure project work.
Answer
knowledge areas
Explanation
Knowledge areas organize project management disciplines, including time, scope, and risk management.
- 12By making problems visible early, project management helps_____.
Hint
Early visibility makes it possible to respond before problems grow.
Answer
reduce risk
Explanation
Project management reduces risk by helping teams identify and address problems early.
- 13Enterprise environmental factors are abbreviated as_____.
Hint
This abbreviation names conditions in the project’s surrounding environment.
Answer
EEFs
Explanation
Enterprise environmental factors, or EEFs, are environmental conditions that can influence a project.
- 14Organizational process assets are abbreviated as_____.
Hint
This abbreviation refers to internal organizational knowledge, processes, and assets.
Answer
OPAs
Explanation
Organizational process assets, or OPAs, are internal resources and guidelines that project teams can use.
- 15EEFs are conditions that can affect a project positively or negatively and are often outside the project manager’s direct_____.
Hint
These influences may need to be planned for rather than changed directly.
Answer
control
Explanation
Many EEFs are outside the project manager’s direct control, but they still affect project work.
- 16Market conditions such as material prices and labor shortages are examples of_____EEFs.
Hint
These conditions originate in the broader world outside the organization.
Answer
external
Explanation
Market conditions are external enterprise environmental factors that may affect project cost and staffing.
- 17Building codes, labor laws, and environmental standards are examples of external_____affecting projects.
Hint
These are formal rules that projects must comply with.
Answer
legal regulations
Explanation
Legal regulations, including building codes, labor laws, and environmental standards, are external EEFs.
- 18Norms around time, hierarchy, and communication in international projects are_____influences.
Hint
These influences reflect shared norms and practices in different societies.
Answer
cultural
Explanation
Cultural influences can shape communication and working expectations, particularly in international projects.
- 19Taxation, political stability, and permits are examples of_____factors affecting projects.
Hint
These influences are associated with public authorities and political conditions.
Answer
governmental
Explanation
Governmental factors include taxation, political stability, and permits.
- 20Innovations that affect how a product is made or delivered are examples of_____trends.
Hint
These trends concern new tools and technical methods.
Answer
technology
Explanation
Technology trends are external EEFs that can influence how project products are made or delivered.
- 21Organizational structure, available resources, internal politics, and IT systems are examples of_____EEFs.
Hint
These influences arise within the organization.
Answer
internal
Explanation
Internal EEFs include organizational structure, resources, political climate, and infrastructure such as IT systems.
- 22People, funding, tools, and facilities are examples of available organizational_____.
Hint
These are inputs the organization can make available to the project.
Answer
resources
Explanation
Available resources—such as people, funding, tools, and facilities—are internal EEFs.
- 23OPAs include templates, procedures, historical data, lessons learned, and knowledge_____.
Hint
These are places or systems where organizational knowledge is collected and stored.
Answer
repositories
Explanation
Knowledge repositories, databases, document management systems, and prior project files are examples of OPAs.
- 24Standard contract formats, risk checklists, procurement rules, and approval workflows are examples of OPA_____.
Hint
These organizational resources prescribe or guide how work should be carried out.
Answer
guidelines and policies
Explanation
OPAs include templates, procedures, guidelines, and policies such as contract formats, risk checklists, and approval workflows.
- 25By reusing organizational knowledge and procedures, OPAs increase consistency and reduce_____.
Hint
Reusable playbooks help teams avoid reinventing the wheel.
Answer
effort
Explanation
OPAs help teams work consistently, reduce effort, and institutionalize best practices.
- 26In a functional organization, projects live within departments and the project manager has_____authority.
Hint
The project manager acts more like a coordinator in this structure.
Answer
limited
Explanation
In a functional organization, projects are housed in departments and the project manager has limited authority.
- 27In a projectized organization, the project manager has full authority and control over_____.
Hint
This structure gives the project manager strong control over what the project needs to do its work.
Answer
resources
Explanation
Projectized organizations give the project manager full authority and control over resources.
- 28A matrix organization is a_____model between functional and projectized structures.
Hint
It combines characteristics of more than one organizational structure.
Answer
hybrid
Explanation
A matrix organization is a hybrid structure in which team members report to both functional and project managers.
- 29In a weak matrix,_____managers dominate.
Hint
This matrix type gives more influence to the managers responsible for departments.
Answer
functional
Explanation
In a weak matrix, functional managers dominate decision-making and authority.
- 30In a balanced matrix, authority is_____.
Hint
Neither the functional manager nor the project manager has all the authority.
Answer
shared
Explanation
A balanced matrix distributes authority between functional and project managers.
- 31In a strong matrix, the_____leads.
Hint
This matrix type gives greater authority to the person leading the project.
Answer
project manager
Explanation
In a strong matrix, the project manager leads and has comparatively greater authority.
- 32An organization’s structure affects project communication paths, decision speed, and resource_____.
Hint
Structure influences whether the people and tools needed by the project can be accessed.
Answer
availability
Explanation
How a project team is organized affects communication, the speed of decisions, and the availability of resources.
- 33Project governance defines how_____get made.
Hint
Governance establishes how choices and approvals occur.
Answer
decisions
Explanation
Governance is not only about compliance; it defines how decisions are made.
- 34Clear roles, responsibilities, reporting relationships, and escalation paths are features of well-defined project_____.
Hint
This system establishes accountability and decision routes.
Answer
governance
Explanation
Well-governed projects have clear roles and responsibilities, reporting relationships, and escalation paths.
- 35Sponsors, users, regulators, and others able to influence a project’s outcome make up its stakeholder_____.
Hint
This term describes the network of people and groups surrounding a project.
Answer
ecosystem
Explanation
Project managers need to understand the stakeholder ecosystem because stakeholders can influence the outcome.
- 36Systems thinking encourages project managers to examine interdependencies, cross-functional risks, and shared_____.
Hint
Projects may rely on the same people or assets as other organizational work.
Answer
resources
Explanation
Systems thinking looks at connections among projects, including interdependencies, cross-functional risks, and shared resources.
- 37Projects interact with portfolios, programs, and other projects, so they do not happen in_____.
Hint
Consider whether projects are independent from the broader organization.
Answer
isolation
Explanation
Projects are connected to broader organizational work, including portfolios, programs, and other projects.
- 38The project management approach should be customized to complexity, stakeholder engagement, risk level, and industry norms through_____.
Hint
This practice adapts a standard approach to the needs of a particular project.
Answer
tailoring
Explanation
Tailoring means customizing the project management approach to the characteristics and context of the project.
- 39A good balance between standardization and flexibility can lead to better project_____.
Hint
The balance should improve the results produced by the project.
Answer
outcomes
Explanation
Tailoring seeks an appropriate balance between standardization and flexibility to improve outcomes.
- 40Project integration management identifies, defines, combines, unifies, and_____project elements.
Hint
Integration brings separate parts into a coherent whole.
Answer
coordinates
Explanation
Integration management coordinates the various elements of a project so they work together.
- 41Integration management aligns project deliverables with organizational_____.
Hint
The project’s outputs should support the organization’s broader direction.
Answer
strategy
Explanation
One purpose of integration management is to align deliverables with organizational strategy.
- 42Integration management balances competing objectives and_____.
Hint
Projects must reconcile their goals with limits such as time and cost.
Answer
constraints
Explanation
Integration management helps balance competing project objectives and constraints.
- 43Integration management coordinates trade-offs among scope, schedule, cost, quality, and_____.
Hint
This is another major project consideration that may be affected by trade-offs.
Answer
resources
Explanation
Project integration involves managing trade-offs among scope, schedule, cost, quality, and resources.
- 44Integration management is critical because a change in one project area can_____through the rest of the project.
Hint
Think of the spreading effect of a change on connected areas.
Answer
ripple
Explanation
Integration helps decision-makers understand how changes in one area affect other parts of the project.
- 45Choosing between fast-tracking and maintaining the budget is an example of a project_____.
Hint
The situation requires balancing competing priorities.
Answer
trade-off
Explanation
Project managers often face trade-offs, such as accelerating work while trying to maintain the budget.
- 46Integration management helps balance innovation with regulatory_____.
Hint
Projects must sometimes reconcile new ideas with applicable rules and standards.
Answer
compliance
Explanation
Integration requires considering the full set of project effects, including balancing innovation with regulatory compliance.
- 47Integration management operates across the full project life cycle, from initiation through_____.
Hint
This is the final phase in the project life cycle.
Answer
closing
Explanation
Integration processes span the project life cycle, from initiation to closing.
- 48During initiation, integration emphasizes strategic alignment and_____.
Hint
The project must be formally permitted to begin.
Answer
authorization
Explanation
Integration during initiation establishes strategic alignment and authorizes the project.
- 49During planning, integration focuses on synchronizing project goals and_____.
Hint
Plans connect what the project intends to achieve with what people will do.
Answer
actions
Explanation
Planning integrates project goals with the actions needed to achieve them.
- 50During execution, integration supports coordinated delivery across_____.
Hint
Different areas of project work need to operate in concert.
Answer
disciplines
Explanation
Execution requires coordinated delivery across the project’s disciplines.
- 51The process that formally authorizes a project and gives the project manager authority to use organizational resources is developing the project_____.
Hint
This official document establishes the project’s existence.
Answer
charter
Explanation
The project charter formally authorizes the project, identifies key roles and alignment, and grants the project manager authority to use organizational resources.
- 52The project charter identifies the project manager, sponsor, and key_____.
Hint
These people or groups have an interest in or influence on the project.
Answer
stakeholders
Explanation
Identifying the project manager, sponsor, and key stakeholders is part of developing the project charter.
- 53A business case and benefits management plan are key inputs to developing the project_____.
Hint
These inputs help establish the project’s justification and expected benefits.
Answer
charter
Explanation
The business case and benefits management plan are key inputs used to develop the project charter.
- 54The approved project charter is the key output of the process to develop the project_____.
Hint
The output is the formally approved authorization document.
Answer
charter
Explanation
Developing the project charter produces an approved project charter.
- 55The document that consolidates subsidiary plans for scope, schedule, cost, and quality into a guiding blueprint is the project management_____.
Hint
This master document guides execution, monitoring, and control.
Answer
plan
Explanation
The project management plan consolidates subsidiary plans into a blueprint for executing, monitoring, and controlling the project.
- 56The project management plan should be tailored to the project’s complexity and_____.
Hint
The plan needs to fit what the particular project calls for.
Answer
requirements
Explanation
The project management plan must be tailored to the project’s complexity and requirements.
- 57Directing and managing project work performs the actual work needed to produce project_____.
Hint
These are the outputs created by carrying out the project work.
Answer
deliverables
Explanation
Direct and manage project work turns plans into action by performing work to produce deliverables.
- 58Issuing work authorizations, updating plans, resolving issues, and coordinating deliverables occur when teams direct and manage project_____.
Hint
This integration process turns the plan into action.
Answer
work
Explanation
Direct and manage project work includes authorizing work, updating plans, resolving issues, and coordinating delivery across teams.
- 59Managing project knowledge balances explicit knowledge, such as documents and reports, with_____knowledge, such as experience and insight.
Hint
This type of knowledge is often gained through personal experience.
Answer
tacit
Explanation
Manage project knowledge uses both explicit knowledge and tacit knowledge, including experience and insight.
- 60A goal of managing project knowledge is to avoid repeating mistakes and maximize organizational_____.
Hint
This improves as knowledge and lessons are transferred and retained.
Answer
learning
Explanation
Knowledge management promotes continuous learning and lessons learned so organizations can avoid repeating mistakes.
- 61Monitoring and controlling project work tracks, reviews, and reports performance against the_____.
Hint
Performance is compared with the agreed guide for project work.
Answer
plan
Explanation
Monitor and control project work compares actual performance with the project plan to support decisions.
- 62Variance analysis, forecasting, and trend analysis are tools used in monitoring and controlling project_____.
Hint
These tools help assess whether project performance is on track.
Answer
work
Explanation
Monitoring and controlling project work uses tools such as variance analysis, forecasting, and trend analysis.
- 63Integrated change control evaluates change requests and assesses effects on scope, time, cost, risk, and_____.
Hint
This project consideration can be affected when changes are proposed.
Answer
quality
Explanation
Integrated change control assesses the impact of changes on multiple areas, including quality.
- 64A Change Control Board, abbreviated_____, may be used for formal evaluation of changes.
Hint
The abbreviation names the board that reviews change requests.
Answer
CCB
Explanation
A Change Control Board (CCB) may formally evaluate project change requests.
- 65Closing a project or phase includes confirming that deliverables have been formally_____.
Hint
The customer or other authorized party agrees that the deliverables meet expectations.
Answer
accepted
Explanation
Closing includes confirming acceptance of deliverables, finalizing activities, documenting lessons, and releasing resources.
- 66Final reports, archived documentation, and closure of procurement and legal matters are outputs of project_____.
Hint
These outputs are produced when project activities are formally completed.
Answer
closure
Explanation
Project closure finalizes activities and produces outputs such as a final report, archived documentation, and closure of procurement and legal matters.
- 67The discipline that defines all work required to deliver a product, service, or result meeting project objectives is project_____.
Hint
This concept defines what work and deliverables belong to the project.
Answer
scope
Explanation
Project scope refers to all the work required to deliver a product, service, or result that meets the project’s objectives.
- 68The features and functions of a product or deliverable are its_____scope.
Hint
This type of scope describes the thing being created rather than the work to create it.
Answer
product
Explanation
Product scope describes the features and functions of the product or deliverable itself.
- 69The work needed to create, test, and install a product is the_____scope.
Hint
This type of scope concerns the work performed to deliver the product.
Answer
project
Explanation
Project scope is the work needed to deliver the product, such as engineering, coding, testing, or installation.
- 70Clear scope management specifies what work is included and what is_____.
Hint
Defining boundaries means identifying work that does not belong in the project.
Answer
excluded
Explanation
Scope management aligns stakeholders on what is included in the project and what is excluded.
- 71Adding unrequested extras to a project is called_____.
Hint
This practice adds features beyond what was asked for.
Answer
goldplating
Explanation
Goldplating means adding extras that stakeholders did not request.
- 72The gradual, uncontrolled expansion of project work is called scope_____.
Hint
This is the “silent killer” of budgets and timelines described in the material.
Answer
creep
Explanation
Scope creep occurs when the project expands beyond its defined scope without proper control, threatening budgets and timelines.
- 73Project scope management helps prevent wasted effort, disappointed stakeholders, and unraveling budgets and_____.
Hint
This is the project constraint that can slip when scope is vague or uncontrolled.
Answer
schedules
Explanation
Poorly defined or controlled scope can cause wasted effort, stakeholder disappointment, and problems with budgets and schedules.
- 74The requirements traceability matrix links each requirement to project_____.
Hint
Traceability shows how an individual need supports what the project aims to accomplish.
Answer
objectives
Explanation
The requirements traceability matrix links requirements to project objectives.
- 75A scope statement defines in-scope work, deliverables, out-of-scope items, assumptions, and_____.
Hint
These are limits or conditions that affect what the project can do.
Answer
constraints
Explanation
The project scope statement defines boundaries and includes assumptions and constraints.
- 76The scope baseline consists of the scope statement, the WBS, and the WBS_____.
Hint
This component provides supporting detail about the work breakdown structure.
Answer
dictionary
Explanation
The scope baseline is made up of the scope statement, WBS, and WBS dictionary.
- 77The process that establishes how scope will be defined, validated, and controlled is plan scope_____.
Hint
This process sets the rules for handling project scope.
Answer
management
Explanation
Plan scope management defines how the scope will be defined, validated, and controlled, and produces the scope management plan.
- 78The scope management plan describes who approves scope statements and how scope_____will be handled.
Hint
The plan establishes rules for responding when project boundaries need revision.
Answer
changes
Explanation
The scope management plan specifies approval responsibilities and how scope changes will be handled.
- 79Interviews, surveys, focus groups, prototypes, and observation are techniques used to collect_____.
Hint
These techniques help uncover what stakeholders need and expect.
Answer
requirements
Explanation
Collect requirements engages stakeholders and uses techniques such as interviews, surveys, focus groups, prototypes, and observation.
- 80Functional needs, technical specifications, compliance, and usability expectations are collected during the process of collecting_____.
Hint
These describe what stakeholders expect the project or product to satisfy.
Answer
requirements
Explanation
Requirements gathering identifies functional, technical, compliance, and usability needs and expectations.
- 81The process of defining scope turns stakeholder needs into a clear, agreed-upon project scope_____.
Hint
This formal description establishes the project’s boundaries.
Answer
statement
Explanation
Define scope translates requirements into a project scope statement that describes the work, deliverables, exclusions, assumptions, and constraints.
- 82The hierarchical decomposition of the total project scope into smaller pieces is the work breakdown structure, or_____.
Hint
This three-letter structure breaks deliverables down into manageable work.
Answer
WBS
Explanation
The WBS hierarchically decomposes the total scope into deliverables, subdeliverables, and work packages.
- 83The lowest levels of the WBS are called work_____.
Hint
These are units of work that can be estimated, assigned, and tracked.
Answer
packages
Explanation
Work packages are the lowest WBS levels and can be estimated, assigned, and tracked.
- 84Breaking project scope into WBS work packages improves clarity and accountability and supports accurate scheduling and cost_____.
Hint
This activity predicts the time and money needed for the work.
Answer
estimation
Explanation
The WBS improves clarity and accountability and provides a basis for accurate schedule and cost estimation.
- 85The process of obtaining formal approval for completed deliverables is validate_____.
Hint
This process confirms that completed work meets requirements and is accepted.
Answer
scope
Explanation
Validate scope involves customer or sponsor review and formal acceptance of completed deliverables.
- 86Scope validation usually occurs at key milestones or phase_____.
Hint
These are formal checkpoints in the project life cycle.
Answer
gates
Explanation
Customers or sponsors typically review deliverables for scope validation at key milestones or phase gates.
- 87Scope validation can result in formal acceptance, requests for changes, or rework_____.
Hint
This response directs the team to correct or redo work.
Answer
orders
Explanation
A scope review may produce formal acceptance, change requests, or rework orders.
- 88The process that tracks scope status and ensures only approved changes are implemented is control_____.
Hint
This process keeps project work within approved boundaries.
Answer
scope
Explanation
Control scope manages changes, tracks scope status, and ensures only approved changes are implemented.
- 89Scope change requests are evaluated using integrated change_____.
Hint
This formal process assesses proposed changes and their impacts.
Answer
control
Explanation
Control scope uses integrated change control to evaluate scope change requests and ensure proper approval.
- 90Variance analysis, change logs, and earned value performance measurement can support control_____.
Hint
These tools help track whether work remains aligned with the approved boundary.
Answer
scope
Explanation
Tools for controlling scope include variance analysis, change logs, and performance measurement such as earned value.
- 91The approved reference used to keep project work aligned, or updated through proper channels, is the scope_____.
Hint
This is the formal benchmark for the project’s approved scope.
Answer
baseline
Explanation
Control scope aims to keep work aligned with the original scope baseline or to update it through approved processes.
- 92A common scope management pitfall is gathering requirements without adequate stakeholder_____.
Hint
Stakeholders need to participate so their needs are understood.
Answer
involvement
Explanation
Insufficient stakeholder involvement during requirements gathering can lead to a poorly defined scope.
- 93Deliverables without measurable acceptance criteria are often too_____.
Hint
The team cannot clearly determine whether this kind of deliverable is complete.
Answer
vague
Explanation
Vague deliverables make it difficult to verify completion and can create disagreements about acceptance.
- 94Undocumented requests such as “just one more feature” can cause scope_____.
Hint
Uncontrolled additions gradually expand project work beyond the agreed scope.
Answer
creep
Explanation
Undocumented requests can expand scope without proper evaluation or approval, causing scope creep.
- 95Skipping creation of the WBS can lead to confusion and_____work.
Hint
Without a clear breakdown, different people may unknowingly do the same task.
Answer
duplicate
Explanation
A WBS clarifies and organizes work; skipping it can create confusion and duplicate effort.
- 96Scope management is not about rejecting all change; it is about approving change with awareness, approval, and_____.
Hint
Changes should remain consistent with project objectives and stakeholder needs.
Answer
alignment
Explanation
Effective scope management allows appropriate change through awareness, approval, and alignment rather than accepting uncontrolled additions.