Project Management Principles

  • 96Unfamiliar
  • 0Learning
  • 0Familiar
  • 0Mastered
Topic: Project Foundations
A project is a temporary effort created to deliver something
such as a product, service, or result.

96 questions

  1. 1
    A project is a temporary effort created to deliver something
    _____
    such as a product, service, or result.
    Hint

    Consider what distinguishes a project’s output from routine operations.

    Answer

    unique

    Explanation

    A project is defined as a temporary effort created to deliver a unique product, service, or result.

  2. 2
    Unlike projects,
    _____
    are the day-to-day activities of a business.
    Hint

    Think of ongoing work that keeps an organization functioning.

    Answer

    operations

    Explanation

    Operations are day-to-day business activities, while projects are special efforts that drive change or innovation.

  3. 3
    Projects are special missions that drive
    _____
    or innovation.
    Hint

    Projects create something different from routine business activity.

    Answer

    change

    Explanation

    Projects are distinct from ongoing operations because they are undertaken to drive change or innovation.

  4. 4
    Projects have a clear start and end, specific objectives and outputs, and distinct
    _____
    .
    Hint

    Think about the results a project produces.

    Answer

    outcomes

    Explanation

    Projects are characterized by defined beginnings and endings, objectives, outputs, and distinct outcomes.

  5. 5
    A project is
    _____
    because it ends when its goals are achieved or when it becomes clear they will not be met.
    Hint

    Temporary does not necessarily mean brief; focus on whether the effort has an endpoint.

    Answer

    finite

    Explanation

    Projects are finite endeavors. They conclude when their goals are achieved or when it is clear those goals cannot be met.

  6. 6
    The temporary nature of a project does not mean that its
    _____
    must also be temporary.
    Hint

    A project can end while the thing it created continues to exist.

    Answer

    result

    Explanation

    Although a project is temporary, its result may endure; for example, a monument may last for centuries.

  7. 7
    Projects can include repeatable elements, but each combination of stakeholders, objectives, and
    _____
    is different.
    Hint

    Consider the setting in which a project is carried out.

    Answer

    environments

    Explanation

    A project can reuse practices and structures while remaining unique because its stakeholders, objectives, and environments differ.

  8. 8
    Project management applies skills, tools, and structured techniques to meet stakeholder needs and
    _____
    .
    Hint

    Think of what stakeholders anticipate in addition to what they need.

    Answer

    expectations

    Explanation

    Project management uses skills, tools, and structured techniques to meet the needs and expectations of stakeholders.

  9. 9
    Project managers balance scope, time, cost, and
    _____
    .
    Hint

    This constraint concerns how well the work or deliverable meets requirements.

    Answer

    quality

    Explanation

    Scope, time, cost, and quality are competing considerations that project managers must balance.

  10. 10
    Project management connects strategic business goals with real-world
    _____
    .
    Hint

    Think of what strategic goals become when project work is delivered.

    Answer

    outcomes

    Explanation

    Project management provides a framework that links organizational strategy to concrete results.

  11. 11
    Disciplines such as time management, scope management, and risk management are project management
    _____
    .
    Hint

    These are the organized subject areas that structure project work.

    Answer

    knowledge areas

    Explanation

    Knowledge areas organize project management disciplines, including time, scope, and risk management.

  12. 12
    By making problems visible early, project management helps
    _____
    .
    Hint

    Early visibility makes it possible to respond before problems grow.

    Answer

    reduce risk

    Explanation

    Project management reduces risk by helping teams identify and address problems early.

  13. 13
    Enterprise environmental factors are abbreviated as
    _____
    .
    Hint

    This abbreviation names conditions in the project’s surrounding environment.

    Answer

    EEFs

    Explanation

    Enterprise environmental factors, or EEFs, are environmental conditions that can influence a project.

  14. 14
    Organizational process assets are abbreviated as
    _____
    .
    Hint

    This abbreviation refers to internal organizational knowledge, processes, and assets.

    Answer

    OPAs

    Explanation

    Organizational process assets, or OPAs, are internal resources and guidelines that project teams can use.

  15. 15
    EEFs are conditions that can affect a project positively or negatively and are often outside the project manager’s direct
    _____
    .
    Hint

    These influences may need to be planned for rather than changed directly.

    Answer

    control

    Explanation

    Many EEFs are outside the project manager’s direct control, but they still affect project work.

  16. 16
    Market conditions such as material prices and labor shortages are examples of
    _____
    EEFs.
    Hint

    These conditions originate in the broader world outside the organization.

    Answer

    external

    Explanation

    Market conditions are external enterprise environmental factors that may affect project cost and staffing.

  17. 17
    Building codes, labor laws, and environmental standards are examples of external
    _____
    affecting projects.
    Hint

    These are formal rules that projects must comply with.

    Answer

    legal regulations

    Explanation

    Legal regulations, including building codes, labor laws, and environmental standards, are external EEFs.

  18. 18
    Norms around time, hierarchy, and communication in international projects are
    _____
    influences.
    Hint

    These influences reflect shared norms and practices in different societies.

    Answer

    cultural

    Explanation

    Cultural influences can shape communication and working expectations, particularly in international projects.

  19. 19
    Taxation, political stability, and permits are examples of
    _____
    factors affecting projects.
    Hint

    These influences are associated with public authorities and political conditions.

    Answer

    governmental

    Explanation

    Governmental factors include taxation, political stability, and permits.

  20. 20
    Innovations that affect how a product is made or delivered are examples of
    _____
    trends.
    Hint

    These trends concern new tools and technical methods.

    Answer

    technology

    Explanation

    Technology trends are external EEFs that can influence how project products are made or delivered.

  21. 21
    Organizational structure, available resources, internal politics, and IT systems are examples of
    _____
    EEFs.
    Hint

    These influences arise within the organization.

    Answer

    internal

    Explanation

    Internal EEFs include organizational structure, resources, political climate, and infrastructure such as IT systems.

  22. 22
    People, funding, tools, and facilities are examples of available organizational
    _____
    .
    Hint

    These are inputs the organization can make available to the project.

    Answer

    resources

    Explanation

    Available resources—such as people, funding, tools, and facilities—are internal EEFs.

  23. 23
    OPAs include templates, procedures, historical data, lessons learned, and knowledge
    _____
    .
    Hint

    These are places or systems where organizational knowledge is collected and stored.

    Answer

    repositories

    Explanation

    Knowledge repositories, databases, document management systems, and prior project files are examples of OPAs.

  24. 24
    Standard contract formats, risk checklists, procurement rules, and approval workflows are examples of OPA
    _____
    .
    Hint

    These organizational resources prescribe or guide how work should be carried out.

    Answer

    guidelines and policies

    Explanation

    OPAs include templates, procedures, guidelines, and policies such as contract formats, risk checklists, and approval workflows.

  25. 25
    By reusing organizational knowledge and procedures, OPAs increase consistency and reduce
    _____
    .
    Hint

    Reusable playbooks help teams avoid reinventing the wheel.

    Answer

    effort

    Explanation

    OPAs help teams work consistently, reduce effort, and institutionalize best practices.

  26. 26
    In a functional organization, projects live within departments and the project manager has
    _____
    authority.
    Hint

    The project manager acts more like a coordinator in this structure.

    Answer

    limited

    Explanation

    In a functional organization, projects are housed in departments and the project manager has limited authority.

  27. 27
    In a projectized organization, the project manager has full authority and control over
    _____
    .
    Hint

    This structure gives the project manager strong control over what the project needs to do its work.

    Answer

    resources

    Explanation

    Projectized organizations give the project manager full authority and control over resources.

  28. 28
    A matrix organization is a
    _____
    model between functional and projectized structures.
    Hint

    It combines characteristics of more than one organizational structure.

    Answer

    hybrid

    Explanation

    A matrix organization is a hybrid structure in which team members report to both functional and project managers.

  29. 29
    In a weak matrix,
    _____
    managers dominate.
    Hint

    This matrix type gives more influence to the managers responsible for departments.

    Answer

    functional

    Explanation

    In a weak matrix, functional managers dominate decision-making and authority.

  30. 30
    In a balanced matrix, authority is
    _____
    .
    Hint

    Neither the functional manager nor the project manager has all the authority.

    Answer

    shared

    Explanation

    A balanced matrix distributes authority between functional and project managers.

  31. 31
    In a strong matrix, the
    _____
    leads.
    Hint

    This matrix type gives greater authority to the person leading the project.

    Answer

    project manager

    Explanation

    In a strong matrix, the project manager leads and has comparatively greater authority.

  32. 32
    An organization’s structure affects project communication paths, decision speed, and resource
    _____
    .
    Hint

    Structure influences whether the people and tools needed by the project can be accessed.

    Answer

    availability

    Explanation

    How a project team is organized affects communication, the speed of decisions, and the availability of resources.

  33. 33
    Project governance defines how
    _____
    get made.
    Hint

    Governance establishes how choices and approvals occur.

    Answer

    decisions

    Explanation

    Governance is not only about compliance; it defines how decisions are made.

  34. 34
    Clear roles, responsibilities, reporting relationships, and escalation paths are features of well-defined project
    _____
    .
    Hint

    This system establishes accountability and decision routes.

    Answer

    governance

    Explanation

    Well-governed projects have clear roles and responsibilities, reporting relationships, and escalation paths.

  35. 35
    Sponsors, users, regulators, and others able to influence a project’s outcome make up its stakeholder
    _____
    .
    Hint

    This term describes the network of people and groups surrounding a project.

    Answer

    ecosystem

    Explanation

    Project managers need to understand the stakeholder ecosystem because stakeholders can influence the outcome.

  36. 36
    Systems thinking encourages project managers to examine interdependencies, cross-functional risks, and shared
    _____
    .
    Hint

    Projects may rely on the same people or assets as other organizational work.

    Answer

    resources

    Explanation

    Systems thinking looks at connections among projects, including interdependencies, cross-functional risks, and shared resources.

  37. 37
    Projects interact with portfolios, programs, and other projects, so they do not happen in
    _____
    .
    Hint

    Consider whether projects are independent from the broader organization.

    Answer

    isolation

    Explanation

    Projects are connected to broader organizational work, including portfolios, programs, and other projects.

  38. 38
    The project management approach should be customized to complexity, stakeholder engagement, risk level, and industry norms through
    _____
    .
    Hint

    This practice adapts a standard approach to the needs of a particular project.

    Answer

    tailoring

    Explanation

    Tailoring means customizing the project management approach to the characteristics and context of the project.

  39. 39
    A good balance between standardization and flexibility can lead to better project
    _____
    .
    Hint

    The balance should improve the results produced by the project.

    Answer

    outcomes

    Explanation

    Tailoring seeks an appropriate balance between standardization and flexibility to improve outcomes.

  40. 40
    Project integration management identifies, defines, combines, unifies, and
    _____
    project elements.
    Hint

    Integration brings separate parts into a coherent whole.

    Answer

    coordinates

    Explanation

    Integration management coordinates the various elements of a project so they work together.

  41. 41
    Integration management aligns project deliverables with organizational
    _____
    .
    Hint

    The project’s outputs should support the organization’s broader direction.

    Answer

    strategy

    Explanation

    One purpose of integration management is to align deliverables with organizational strategy.

  42. 42
    Integration management balances competing objectives and
    _____
    .
    Hint

    Projects must reconcile their goals with limits such as time and cost.

    Answer

    constraints

    Explanation

    Integration management helps balance competing project objectives and constraints.

  43. 43
    Integration management coordinates trade-offs among scope, schedule, cost, quality, and
    _____
    .
    Hint

    This is another major project consideration that may be affected by trade-offs.

    Answer

    resources

    Explanation

    Project integration involves managing trade-offs among scope, schedule, cost, quality, and resources.

  44. 44
    Integration management is critical because a change in one project area can
    _____
    through the rest of the project.
    Hint

    Think of the spreading effect of a change on connected areas.

    Answer

    ripple

    Explanation

    Integration helps decision-makers understand how changes in one area affect other parts of the project.

  45. 45
    Choosing between fast-tracking and maintaining the budget is an example of a project
    _____
    .
    Hint

    The situation requires balancing competing priorities.

    Answer

    trade-off

    Explanation

    Project managers often face trade-offs, such as accelerating work while trying to maintain the budget.

  46. 46
    Integration management helps balance innovation with regulatory
    _____
    .
    Hint

    Projects must sometimes reconcile new ideas with applicable rules and standards.

    Answer

    compliance

    Explanation

    Integration requires considering the full set of project effects, including balancing innovation with regulatory compliance.

  47. 47
    Integration management operates across the full project life cycle, from initiation through
    _____
    .
    Hint

    This is the final phase in the project life cycle.

    Answer

    closing

    Explanation

    Integration processes span the project life cycle, from initiation to closing.

  48. 48
    During initiation, integration emphasizes strategic alignment and
    _____
    .
    Hint

    The project must be formally permitted to begin.

    Answer

    authorization

    Explanation

    Integration during initiation establishes strategic alignment and authorizes the project.

  49. 49
    During planning, integration focuses on synchronizing project goals and
    _____
    .
    Hint

    Plans connect what the project intends to achieve with what people will do.

    Answer

    actions

    Explanation

    Planning integrates project goals with the actions needed to achieve them.

  50. 50
    During execution, integration supports coordinated delivery across
    _____
    .
    Hint

    Different areas of project work need to operate in concert.

    Answer

    disciplines

    Explanation

    Execution requires coordinated delivery across the project’s disciplines.

  51. 51
    The process that formally authorizes a project and gives the project manager authority to use organizational resources is developing the project
    _____
    .
    Hint

    This official document establishes the project’s existence.

    Answer

    charter

    Explanation

    The project charter formally authorizes the project, identifies key roles and alignment, and grants the project manager authority to use organizational resources.

  52. 52
    The project charter identifies the project manager, sponsor, and key
    _____
    .
    Hint

    These people or groups have an interest in or influence on the project.

    Answer

    stakeholders

    Explanation

    Identifying the project manager, sponsor, and key stakeholders is part of developing the project charter.

  53. 53
    A business case and benefits management plan are key inputs to developing the project
    _____
    .
    Hint

    These inputs help establish the project’s justification and expected benefits.

    Answer

    charter

    Explanation

    The business case and benefits management plan are key inputs used to develop the project charter.

  54. 54
    The approved project charter is the key output of the process to develop the project
    _____
    .
    Hint

    The output is the formally approved authorization document.

    Answer

    charter

    Explanation

    Developing the project charter produces an approved project charter.

  55. 55
    The document that consolidates subsidiary plans for scope, schedule, cost, and quality into a guiding blueprint is the project management
    _____
    .
    Hint

    This master document guides execution, monitoring, and control.

    Answer

    plan

    Explanation

    The project management plan consolidates subsidiary plans into a blueprint for executing, monitoring, and controlling the project.

  56. 56
    The project management plan should be tailored to the project’s complexity and
    _____
    .
    Hint

    The plan needs to fit what the particular project calls for.

    Answer

    requirements

    Explanation

    The project management plan must be tailored to the project’s complexity and requirements.

  57. 57
    Directing and managing project work performs the actual work needed to produce project
    _____
    .
    Hint

    These are the outputs created by carrying out the project work.

    Answer

    deliverables

    Explanation

    Direct and manage project work turns plans into action by performing work to produce deliverables.

  58. 58
    Issuing work authorizations, updating plans, resolving issues, and coordinating deliverables occur when teams direct and manage project
    _____
    .
    Hint

    This integration process turns the plan into action.

    Answer

    work

    Explanation

    Direct and manage project work includes authorizing work, updating plans, resolving issues, and coordinating delivery across teams.

  59. 59
    Managing project knowledge balances explicit knowledge, such as documents and reports, with
    _____
    knowledge, such as experience and insight.
    Hint

    This type of knowledge is often gained through personal experience.

    Answer

    tacit

    Explanation

    Manage project knowledge uses both explicit knowledge and tacit knowledge, including experience and insight.

  60. 60
    A goal of managing project knowledge is to avoid repeating mistakes and maximize organizational
    _____
    .
    Hint

    This improves as knowledge and lessons are transferred and retained.

    Answer

    learning

    Explanation

    Knowledge management promotes continuous learning and lessons learned so organizations can avoid repeating mistakes.

  61. 61
    Monitoring and controlling project work tracks, reviews, and reports performance against the
    _____
    .
    Hint

    Performance is compared with the agreed guide for project work.

    Answer

    plan

    Explanation

    Monitor and control project work compares actual performance with the project plan to support decisions.

  62. 62
    Variance analysis, forecasting, and trend analysis are tools used in monitoring and controlling project
    _____
    .
    Hint

    These tools help assess whether project performance is on track.

    Answer

    work

    Explanation

    Monitoring and controlling project work uses tools such as variance analysis, forecasting, and trend analysis.

  63. 63
    Integrated change control evaluates change requests and assesses effects on scope, time, cost, risk, and
    _____
    .
    Hint

    This project consideration can be affected when changes are proposed.

    Answer

    quality

    Explanation

    Integrated change control assesses the impact of changes on multiple areas, including quality.

  64. 64
    A Change Control Board, abbreviated
    _____
    , may be used for formal evaluation of changes.
    Hint

    The abbreviation names the board that reviews change requests.

    Answer

    CCB

    Explanation

    A Change Control Board (CCB) may formally evaluate project change requests.

  65. 65
    Closing a project or phase includes confirming that deliverables have been formally
    _____
    .
    Hint

    The customer or other authorized party agrees that the deliverables meet expectations.

    Answer

    accepted

    Explanation

    Closing includes confirming acceptance of deliverables, finalizing activities, documenting lessons, and releasing resources.

  66. 66
    Final reports, archived documentation, and closure of procurement and legal matters are outputs of project
    _____
    .
    Hint

    These outputs are produced when project activities are formally completed.

    Answer

    closure

    Explanation

    Project closure finalizes activities and produces outputs such as a final report, archived documentation, and closure of procurement and legal matters.

  67. 67
    The discipline that defines all work required to deliver a product, service, or result meeting project objectives is project
    _____
    .
    Hint

    This concept defines what work and deliverables belong to the project.

    Answer

    scope

    Explanation

    Project scope refers to all the work required to deliver a product, service, or result that meets the project’s objectives.

  68. 68
    The features and functions of a product or deliverable are its
    _____
    scope.
    Hint

    This type of scope describes the thing being created rather than the work to create it.

    Answer

    product

    Explanation

    Product scope describes the features and functions of the product or deliverable itself.

  69. 69
    The work needed to create, test, and install a product is the
    _____
    scope.
    Hint

    This type of scope concerns the work performed to deliver the product.

    Answer

    project

    Explanation

    Project scope is the work needed to deliver the product, such as engineering, coding, testing, or installation.

  70. 70
    Clear scope management specifies what work is included and what is
    _____
    .
    Hint

    Defining boundaries means identifying work that does not belong in the project.

    Answer

    excluded

    Explanation

    Scope management aligns stakeholders on what is included in the project and what is excluded.

  71. 71
    Adding unrequested extras to a project is called
    _____
    .
    Hint

    This practice adds features beyond what was asked for.

    Answer

    goldplating

    Explanation

    Goldplating means adding extras that stakeholders did not request.

  72. 72
    The gradual, uncontrolled expansion of project work is called scope
    _____
    .
    Hint

    This is the “silent killer” of budgets and timelines described in the material.

    Answer

    creep

    Explanation

    Scope creep occurs when the project expands beyond its defined scope without proper control, threatening budgets and timelines.

  73. 73
    Project scope management helps prevent wasted effort, disappointed stakeholders, and unraveling budgets and
    _____
    .
    Hint

    This is the project constraint that can slip when scope is vague or uncontrolled.

    Answer

    schedules

    Explanation

    Poorly defined or controlled scope can cause wasted effort, stakeholder disappointment, and problems with budgets and schedules.

  74. 74
    The requirements traceability matrix links each requirement to project
    _____
    .
    Hint

    Traceability shows how an individual need supports what the project aims to accomplish.

    Answer

    objectives

    Explanation

    The requirements traceability matrix links requirements to project objectives.

  75. 75
    A scope statement defines in-scope work, deliverables, out-of-scope items, assumptions, and
    _____
    .
    Hint

    These are limits or conditions that affect what the project can do.

    Answer

    constraints

    Explanation

    The project scope statement defines boundaries and includes assumptions and constraints.

  76. 76
    The scope baseline consists of the scope statement, the WBS, and the WBS
    _____
    .
    Hint

    This component provides supporting detail about the work breakdown structure.

    Answer

    dictionary

    Explanation

    The scope baseline is made up of the scope statement, WBS, and WBS dictionary.

  77. 77
    The process that establishes how scope will be defined, validated, and controlled is plan scope
    _____
    .
    Hint

    This process sets the rules for handling project scope.

    Answer

    management

    Explanation

    Plan scope management defines how the scope will be defined, validated, and controlled, and produces the scope management plan.

  78. 78
    The scope management plan describes who approves scope statements and how scope
    _____
    will be handled.
    Hint

    The plan establishes rules for responding when project boundaries need revision.

    Answer

    changes

    Explanation

    The scope management plan specifies approval responsibilities and how scope changes will be handled.

  79. 79
    Interviews, surveys, focus groups, prototypes, and observation are techniques used to collect
    _____
    .
    Hint

    These techniques help uncover what stakeholders need and expect.

    Answer

    requirements

    Explanation

    Collect requirements engages stakeholders and uses techniques such as interviews, surveys, focus groups, prototypes, and observation.

  80. 80
    Functional needs, technical specifications, compliance, and usability expectations are collected during the process of collecting
    _____
    .
    Hint

    These describe what stakeholders expect the project or product to satisfy.

    Answer

    requirements

    Explanation

    Requirements gathering identifies functional, technical, compliance, and usability needs and expectations.

  81. 81
    The process of defining scope turns stakeholder needs into a clear, agreed-upon project scope
    _____
    .
    Hint

    This formal description establishes the project’s boundaries.

    Answer

    statement

    Explanation

    Define scope translates requirements into a project scope statement that describes the work, deliverables, exclusions, assumptions, and constraints.

  82. 82
    The hierarchical decomposition of the total project scope into smaller pieces is the work breakdown structure, or
    _____
    .
    Hint

    This three-letter structure breaks deliverables down into manageable work.

    Answer

    WBS

    Explanation

    The WBS hierarchically decomposes the total scope into deliverables, subdeliverables, and work packages.

  83. 83
    The lowest levels of the WBS are called work
    _____
    .
    Hint

    These are units of work that can be estimated, assigned, and tracked.

    Answer

    packages

    Explanation

    Work packages are the lowest WBS levels and can be estimated, assigned, and tracked.

  84. 84
    Breaking project scope into WBS work packages improves clarity and accountability and supports accurate scheduling and cost
    _____
    .
    Hint

    This activity predicts the time and money needed for the work.

    Answer

    estimation

    Explanation

    The WBS improves clarity and accountability and provides a basis for accurate schedule and cost estimation.

  85. 85
    The process of obtaining formal approval for completed deliverables is validate
    _____
    .
    Hint

    This process confirms that completed work meets requirements and is accepted.

    Answer

    scope

    Explanation

    Validate scope involves customer or sponsor review and formal acceptance of completed deliverables.

  86. 86
    Scope validation usually occurs at key milestones or phase
    _____
    .
    Hint

    These are formal checkpoints in the project life cycle.

    Answer

    gates

    Explanation

    Customers or sponsors typically review deliverables for scope validation at key milestones or phase gates.

  87. 87
    Scope validation can result in formal acceptance, requests for changes, or rework
    _____
    .
    Hint

    This response directs the team to correct or redo work.

    Answer

    orders

    Explanation

    A scope review may produce formal acceptance, change requests, or rework orders.

  88. 88
    The process that tracks scope status and ensures only approved changes are implemented is control
    _____
    .
    Hint

    This process keeps project work within approved boundaries.

    Answer

    scope

    Explanation

    Control scope manages changes, tracks scope status, and ensures only approved changes are implemented.

  89. 89
    Scope change requests are evaluated using integrated change
    _____
    .
    Hint

    This formal process assesses proposed changes and their impacts.

    Answer

    control

    Explanation

    Control scope uses integrated change control to evaluate scope change requests and ensure proper approval.

  90. 90
    Variance analysis, change logs, and earned value performance measurement can support control
    _____
    .
    Hint

    These tools help track whether work remains aligned with the approved boundary.

    Answer

    scope

    Explanation

    Tools for controlling scope include variance analysis, change logs, and performance measurement such as earned value.

  91. 91
    The approved reference used to keep project work aligned, or updated through proper channels, is the scope
    _____
    .
    Hint

    This is the formal benchmark for the project’s approved scope.

    Answer

    baseline

    Explanation

    Control scope aims to keep work aligned with the original scope baseline or to update it through approved processes.

  92. 92
    A common scope management pitfall is gathering requirements without adequate stakeholder
    _____
    .
    Hint

    Stakeholders need to participate so their needs are understood.

    Answer

    involvement

    Explanation

    Insufficient stakeholder involvement during requirements gathering can lead to a poorly defined scope.

  93. 93
    Deliverables without measurable acceptance criteria are often too
    _____
    .
    Hint

    The team cannot clearly determine whether this kind of deliverable is complete.

    Answer

    vague

    Explanation

    Vague deliverables make it difficult to verify completion and can create disagreements about acceptance.

  94. 94
    Undocumented requests such as “just one more feature” can cause scope
    _____
    .
    Hint

    Uncontrolled additions gradually expand project work beyond the agreed scope.

    Answer

    creep

    Explanation

    Undocumented requests can expand scope without proper evaluation or approval, causing scope creep.

  95. 95
    Skipping creation of the WBS can lead to confusion and
    _____
    work.
    Hint

    Without a clear breakdown, different people may unknowingly do the same task.

    Answer

    duplicate

    Explanation

    A WBS clarifies and organizes work; skipping it can create confusion and duplicate effort.

  96. 96
    Scope management is not about rejecting all change; it is about approving change with awareness, approval, and
    _____
    .
    Hint

    Changes should remain consistent with project objectives and stakeholder needs.

    Answer

    alignment

    Explanation

    Effective scope management allows appropriate change through awareness, approval, and alignment rather than accepting uncontrolled additions.

1 of 96
Question 1 of 96