Project Management Principles
- 80Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
- spaceFlip card
- KI knew it
- DI didn't know it
- ←Previous card
- →Next card
What is a project?
A temporary endeavor undertaken to create a unique product, service, or result.
Or swipe the card
80 cards
What is a project?
A temporary endeavor undertaken to create a unique product, service, or result.
How do projects differ from operations?
Operations are ongoing day-to-day activities; projects are finite endeavors that create change or innovation.
What are examples of projects?
Building a wastewater treatment plant, creating a mobile app, and running a public health campaign.
What makes a project temporary?
It has a definite beginning and end. It ends when its goals are achieved or when it becomes clear they will not be achieved.
Does temporary mean a project must be short?
No. A project can last weeks or years; it is temporary because it is finite, not because it is brief.
Does a project's result have to be temporary?
No. The project ends, but its result may last a long time, such as a monument intended to endure for centuries.
What does uniqueness mean in the context of projects?
Each project has a distinct combination of stakeholders, objectives, and circumstances, even if it uses familiar or repeatable elements.
What is project management?
Applying skills, tools, and structured techniques to guide project work and meet stakeholder needs and expectations.
Which major constraints must project managers balance?
Scope, time, cost, and quality, while also considering resources and stakeholder expectations.
Who may have expectations that project managers must manage?
Clients or customers, sponsors, team members, the public, and regulators.
How does project management connect strategy to outcomes?
It provides a structured framework for turning strategic business goals into real-world project outcomes.
What are the benefits of effective project management?
It aligns people around a goal, optimizes resources, surfaces risks early, improves communication, and supports repeatable methods that can increase success rates.
What are enterprise environmental factors (EEFs)?
Conditions in or around an organization that influence a project positively or negatively; many are outside the project team's control.
What external market conditions can affect a project?
Factors such as material prices and labor availability, including whether materials are expensive or there is a labor shortage.
How can legal and governmental conditions affect a project?
Regulations, building codes, labor laws, environmental standards, taxes, political stability, and permitting can constrain or shape project work.
How can culture and technology trends influence projects?
Cultural norms can affect time expectations, hierarchy, and communication; technology trends can change how a product is made or delivered.
What internal conditions can be enterprise environmental factors?
Organizational structure, available people and funding, tools and facilities, political climate, leadership support, departmental relationships, infrastructure, and IT systems.
Can project managers control all enterprise environmental factors?
No. They may not control these factors, but they can plan for them and adapt project strategies in response.
What are organizational process assets (OPAs)?
Internal organizational knowledge, processes, and resources that project teams can use, such as templates, procedures, and historical records.
What are examples of organizational process assets?
Contract templates, risk checklists, lessons learned, knowledge repositories, prior project files, procurement rules, quality procedures, and approval workflows.
How do organizational process assets help projects?
They increase consistency, reduce effort, help teams avoid reinventing solutions, and institutionalize best practices.
How does a functional organization affect project manager authority?
Projects sit within departments, and the project manager usually has limited authority and acts more like a coordinator.
How does a projectized organization affect project manager authority?
Projects are central to the organization, and the project manager generally has full authority and control over project resources.
What characterizes a matrix organization?
It is a hybrid structure in which team members report to both functional managers and project managers.
How do weak, balanced, and strong matrix structures differ?
Functional managers dominate in a weak matrix; authority is shared in a balanced matrix; the project manager leads in a strong matrix.
Why does organizational structure matter to project teams?
It affects authority, communication paths, decision speed, collaboration, and the availability of resources.
What does project governance establish?
How decisions are made, including roles and responsibilities, reporting relationships, and escalation paths.
Why should project managers understand the stakeholder ecosystem?
Sponsors, users, regulators, and other influential stakeholders can affect the outcome; a change in one stakeholder's priorities can redirect the project.
What is systems thinking in project management?
Viewing a project in relation to other projects, programs, portfolios, and the wider organization rather than treating it as isolated.
What project concerns does systems thinking help reveal?
Interdependencies, cross-functional risks, and shared resources that could be missed when teams work in silos.
What does tailoring a project management approach mean?
Customizing the approach to fit the project's complexity, stakeholder engagement, risk level, and industry norms.
Why should project managers balance standardization with flexibility?
A suitable balance preserves useful consistency while adapting the approach to the project's context, supporting better outcomes.
What is project integration management?
The processes and activities used to identify, define, combine, unify, and coordinate project elements into a coherent whole.
What is the central purpose of integration management?
To connect project components, align deliverables with organizational strategy, and coordinate work across the project life cycle.
What trade-offs does integration management help balance?
Competing objectives and constraints, including scope, schedule, cost, quality, and resources.
Why is integration management important when project conditions change?
A change in one area can affect the rest of the project, so decisions need to account for their wider effects.
What are examples of decisions requiring an integrated project view?
Choosing between faster delivery and maintaining the budget, adapting to changing stakeholder requirements, and balancing innovation with regulatory compliance.
How does integration management work across the project life cycle?
It supports strategic alignment and authorization during initiation, synchronizes goals and actions in planning, coordinates delivery in execution, takes a holistic performance view in monitoring, and supports handoff and reflection at closing.
What are common project integration challenges?
Conflicting stakeholder interests, uncontrolled scope changes, siloed teams, poor cross-functional communication, and incomplete knowledge transfer between phases.
How does effective integration management create value?
It turns strategic intent into coordinated action and measurable outcomes, helping keep the project coherent, efficient, and aligned with business value.
What is the purpose of developing a project charter?
To formally authorize the project, identify key people, establish high-level objectives and scope, align the project with business goals, and authorize the project manager to use organizational resources.
What are key inputs and the main output of developing a project charter?
The business case and benefits management plan are key inputs; the approved project charter is the output.
What is the purpose of developing the project management plan?
To create the guiding blueprint for execution, monitoring, and control by integrating subsidiary plans into one master document.
What are examples of subsidiary project management plans?
Scope, schedule, cost, risk, and communications management plans.
What does directing and managing project work involve?
Performing the work to produce deliverables; managing people, resources, and timelines; issuing work authorizations; resolving issues; coordinating teams; and managing change requests while maintaining quality.
What is the purpose of managing project knowledge?
To use knowledge from past projects and create new insights, transfer learning, document lessons, and avoid repeating mistakes.
How do explicit and tacit knowledge differ?
Explicit knowledge is recorded in documents and reports; tacit knowledge is held in people's experience and insight.
What does monitoring and controlling project work do?
It tracks, reviews, and reports performance against the plan to support proactive issue detection and decision-making.
What techniques can be used to monitor project work?
Variance analysis, forecasting, trend analysis, performance reviews, progress reporting, and risk reassessment.
What happens during integrated change control?
Change requests are evaluated for their effects on scope, time, cost, risk, and quality, and approval paths are determined before changes are implemented.
What is the role of a change control board (CCB)?
A CCB may formally evaluate project change requests.
What does closing a project or phase involve?
Finalizing activities, closing contracts, confirming deliverable acceptance, documenting lessons learned, transferring knowledge, and releasing resources.
What are possible outputs of project or phase closure?
A final report, archived documentation, and closure of procurement and legal matters.
What is project scope?
All the work required to deliver a product, service, or result that meets the project's objectives.
How do product scope and project scope differ?
Product scope describes the features and functions of the deliverable; project scope describes the work required to create and deliver it.
Why must product scope and project scope be managed together?
The product's required features and functions must be matched with the work needed to produce and deliver them.
How does clear scope management help a project?
It clarifies what is included and excluded, how completeness will be verified, and helps teams stay focused on approved objectives.
What can happen when project scope is vague or poorly controlled?
Teams may waste effort, stakeholders may be disappointed, and budgets and schedules may unravel.
What is gold plating?
Adding features or extras that were not requested or approved.
What is scope creep?
The gradual expansion of project scope, often through undocumented or uncontrolled requests, which can threaten budgets and timelines.
What is the goal of project scope management?
To deliver the approved work, no more and no less, while handling changes through appropriate awareness, approval, and alignment.
What is the purpose of planning scope management?
To define how scope will be developed, validated, and controlled, including how scope approvals and changes will be handled.
What is the main output of planning scope management?
The scope management plan, which establishes how scope will be developed and maintained.
What happens when requirements are collected?
Stakeholders are engaged to discover and document their functional needs, technical specifications, and compliance and usability expectations.
What techniques can be used to collect project requirements?
Interviews, surveys, questionnaires, focus groups, prototypes, wireframes, observation, and job shadowing.
What are the outputs of collecting requirements?
Requirements documentation and a requirements traceability matrix linking each requirement to project objectives.
What is the purpose of defining scope?
To translate requirements into an agreed boundary describing deliverables, included work, exclusions, assumptions, and constraints.
What does the project scope statement do?
It formally describes the project's scope and anchors stakeholder expectations by clarifying what is included and excluded.
What is a work breakdown structure (WBS)?
A hierarchical decomposition of the total project scope into smaller, manageable components.
What are the levels of a WBS?
Top levels represent major deliverables, middle levels represent subdeliverables, and the lowest levels contain work packages.
What is a work package?
A lowest-level WBS unit of work that can be estimated, assigned, and tracked.
What is included in the scope baseline?
The project scope statement, the WBS, and the WBS dictionary.
How does creating a WBS benefit project management?
It improves clarity and accountability, supports accurate scheduling and cost estimation, and provides a foundation for project control.
What happens during scope validation?
The customer or sponsor reviews completed deliverables against requirements and formally accepts them or requests changes or rework.
When does scope validation commonly occur, and why is it useful?
It commonly occurs at milestones or phase gates and reduces the risk of surprises at project close.
What does controlling scope involve?
Tracking scope status, ensuring only approved changes are implemented, and keeping the work aligned with the scope baseline or updating it through proper channels.
How are scope change requests evaluated?
They are evaluated through integrated change control, considering their effects before approval and implementation.
What tools can support scope control?
Variance analysis, change logs, and performance measurement such as earned value.
What are common scope management pitfalls?
Insufficient stakeholder involvement, vague deliverables without measurable acceptance criteria, undocumented requests, and skipping WBS creation.
Why are measurable acceptance criteria important for scope?
They make it possible to determine whether deliverables meet requirements and are complete.