Building Enclosure Design
Retrofitting a Historic Ocean Liner as a High-Performance Building
Project Concept and Design Challenge
The project examined how the SS United States, a historic ocean liner, could be adapted for a new use while responding to contemporary climate and energy goals. Rather than treating the ship as a conventional building, the design team studied it as a unique enclosure: a large, floating metal structure that had to remain dry, stable, and operational in a marine environment.
The central design challenge was to merge:
Naval architecture, including the ship’s structural frame, watertight compartments, double hull, and specialized systems.
Traditional building science, including insulation, air barriers, vapor control, compartmentalization, mechanical systems, and thermal-bridge reduction.
Adaptive reuse, preserving the ship’s historic identity while giving it a new function.
Climate-responsive design, including the possibility of reducing operational carbon emissions and approaching net-zero performance.
The ship was therefore treated as a large-scale retrofit project, even though it was not originally designed as a building. Its existing structure and enclosure had to be adapted without unnecessarily changing its iconic appearance.
The project asks whether an advanced object from the past—a ship—can become a climate-resilient, high-performance building for the future.
The SS United States as a Building Resource
The SS United States was described as:
A monument and national icon.
An ambassador of mid-century maritime design.
One of the world’s largest and fastest ocean liners when built.
A vessel with national-security significance because it could potentially be converted into a military or security vessel.
A carrier of historical stories involving travel, immigration, national identity, and technological achievement.
Its historical importance created a preservation challenge. The goal was not simply to cover the ship with a new exterior or replace its visual character. Instead, the design sought to work with the existing systems and structure.
The ship’s transformation raised broader questions about future building design:
Can an existing object be repurposed rather than demolished?
Can ships or other nontraditional structures become buildings?
Can a structure designed for an earlier technological era be upgraded to meet current energy standards?
Should future-proofing occur within the object itself, or should some systems be located externally and connected to it?
Could floating structures become increasingly relevant as flood levels and climate risks rise?
The project suggests that resilience may require looking beyond conventional land-based building types.
Understanding the Ship’s Existing Enclosure
The Superstructure Plate as Air and Vapor Control
A major discovery was that the ship’s superstructure plate could function simultaneously as:
An air barrier, limiting uncontrolled air movement.
A vapor barrier, limiting vapor diffusion through the metal enclosure.
A water-resistant exterior layer that helped keep the interior dry.
This differs from the usual organization of a high-performance wall, where separate layers are often assigned to:
Water control.
Air control.
Vapor control.
Thermal control.
Structural support.
In the ship, the metal superstructure already performed several of these control functions. Because the structure was made of metal and had to keep seawater out, it provided an inherently continuous protective surface.
However, this did not eliminate the need for careful enclosure design. The metal skin could still create difficult thermal and moisture conditions, especially after the ship was placed in a cold climate and converted into a conditioned building.
Convective Loops in the Double Hull
The ship included hollow spaces within its double-hull construction. These spaces were not simply empty voids; they could support unwanted air movement.
In a cold climate, warm interior air can rise while cooler air descends. If hollow cavities are connected vertically or horizontally, this movement can create convective loops. Convective loops can:
Increase heat loss.
Produce uneven temperatures.
Encourage condensation on cold metal surfaces.
Reduce the effectiveness of insulation.
Create localized moisture and durability problems.
The loops were not caused primarily by exterior wind. Instead, they occurred because the cavities were hollow and allowed air to circulate internally.
The retrofit therefore needed a strategy to:
Seal uncontrolled air pathways.
Divide the double-hull cavities into smaller zones.
Add insulation without blocking required ship systems.
Maintain access for electrical, mechanical, and plumbing infrastructure.
Compartmentalization as an Energy Strategy
The ship’s existing watertight divisions offered an important opportunity. In its original naval function, the bulkheads were designed to limit water movement between compartments. In the retrofit, those same divisions could also help limit:
Air movement.
Convective circulation.
Fire spread.
Thermal transfer.
The uncontrolled movement of mechanical systems between zones.
This demonstrates how a feature designed for one purpose can support another. The watertight compartment system could be adapted into a building-performance strategy.
Structural Organization: Bulkheads and Compartments
Watertight Compartments
The ship consisted of a series of bulkheads and approximately 20 watertight compartments. These compartments were intended to limit flooding: if water entered one part of the ship, the bulkheads would prevent it from spreading throughout the entire vessel.
The retrofit team viewed these compartments as usable infrastructure rather than obstacles. The hollow spaces could potentially accommodate:
Insulation.
Electrical distribution.
Mechanical systems.
Plumbing.
Ventilation pathways.
Service access.
Changing the Language of the Building
A ship does not use the same spatial vocabulary as a conventional building. Instead of referring simply to first, second, and third floors, the ship is organized through maritime terms such as:
Hold.
Decks.
Bulkheads.
Double hull.
Superstructure.
Understanding and preserving this organization was essential. The design strategy translated the ship’s existing spatial logic into building-performance zones.
Changing Thickness of the Double Hull
The double-hull frame changed thickness at different vertical levels:
It was approximately nine inches from the hold through the C deck.
It then became approximately six inches at higher levels.
It became smaller still in some upper portions.
These variations affected how the retrofit could be designed. The thicker lower portions offered more room for integrating:
Insulation.
Electrical infrastructure.
Mechanical distribution.
Plumbing systems.
Service cavities.
The double hull thus became more than a structural and maritime feature. It became a potential building-services zone.
Translating Naval Compartmentalization into Building Design
Naval vessels commonly divide their interiors into major vertical zones based on:
Thermal boundaries.
Structural boundaries.
Fire-risk categories.
Operational requirements.
Flood protection.
The retrofit adapted this logic into a building organization. Existing bulkheads were extended vertically to form several major compartments. These compartments could correspond to different building systems and program areas.
For example, each compartment could have its own:
Electrical systems.
Mechanical systems.
Plumbing distribution.
Conditioned zones.
Fire and smoke control strategies.
This arrangement would reduce the need for systems to cross continuously through the entire ship. It would also make the systems easier to organize and maintain.
Compartmentalization supports both safety and energy performance by dividing a large, complex structure into smaller controlled zones.
The approach also resembled a conventional building arrangement in which:
Unconditioned service areas contain ducts, pipes, and equipment.
Conditioned zones contain occupied spaces.
Fire and structural boundaries organize the building into protected sections.
Insulation and Fire Protection
Marine Insulation Practices
Newer ships commonly use a marine insulation product referred to in the presentation as a marine board. This material is installed around the structure to provide multiple functions, including:
Thermal insulation.
Fire protection.
Enclosure coverage.
Protection of structural elements.
The approach is broadly similar to wrapping the ship’s structure in a continuous protective layer. Mechanical and electrical systems can then be installed in or around this protected zone.
Limitations of Retrofitting an Older Ship
The SS United States was an older vessel, so it could not necessarily receive the same treatment as a newly constructed ship. Retrofitting introduced several constraints:
Existing materials and assemblies had to be retained or worked around.
Additional fireproofing could change available space.
The structure had to be analyzed before new systems could be installed.
New insulation and services had to fit within restricted dimensions.
The sequence of installation was more complicated than in new construction.
The design therefore had to work backward from the existing ship. Instead of selecting an ideal new assembly, the team had to determine what could be safely and practically integrated into the historic structure.
Applying Building-Science Principles to a Ship
Conventional High-Performance Wall Logic
In a typical high-performance wall, the enclosure is often organized so that:
The exterior finish protects against weather.
The thermal layer is placed toward the exterior of the structure when possible.
The air-control layer is continuous.
The vapor-control layer is positioned according to climate and condensation risk.
The structural layer is protected from excessive temperature and moisture variation.
This organization makes it easier to control heat, air, and moisture.
Why the Ship Requires a Different Arrangement
The ship’s existing metal plate already served as the exterior air-control and vapor-control layer. As a result, the normal wall sequence had to be reconsidered.
The proposed approach placed new insulation within the double-hull space while maintaining the ship’s outer metal skin as a critical control layer. This required:
A highly continuous exterior air barrier.
Sealing of laps and joints in the metal skin.
Careful treatment of penetrations.
Compartmentalization of the hollow spaces.
A secondary interior vapor-control strategy where needed.
Thermal-bridge analysis at structural connections and openings.
The project applied familiar building-science principles, but adapted them to the ship’s unusual geometry and construction.
The Importance of a Continuous Air Barrier
The air barrier had to be especially reliable because uncontrolled air movement through the double hull could produce convective loops. The ship’s exterior metal skin had to be made sufficiently airtight across:
Plate joints.
Laps.
Openings.
Connections.
Service penetrations.
Areas where new systems interfaced with the original structure.
The air barrier was therefore not just a moisture-control layer. It was also a strategy for reducing heat loss and stabilizing the enclosure.
Mechanical and Electrical Systems
Using the Double Hull as a Services Zone
One of the major design opportunities was to use the double hull to carry systems rather than placing ducts and equipment inside occupied spaces.
Potential uses included:
Electrical distribution.
Mechanical ventilation.
Plumbing.
Insulation.
Service access.
Heat-pump connections.
This strategy helped preserve interior volume and avoid reducing headroom. Since the ship had limited height for ductwork, locating systems in the double hull was particularly valuable.
Energy Recovery Ventilation
The design considered energy recovery ventilators, or ERVs, as part of the ventilation strategy. ERVs exchange stale interior air for outdoor air while transferring energy between the two air streams.
An ERV can:
Exhaust warm or cool indoor air.
Bring in fresh outdoor air.
Recover some of the energy from the outgoing air.
Reduce the load on heating and cooling equipment.
The proposed system would use the ship’s existing structural elements and service cavities to route ventilation efficiently.
Heat Pumps
The design also considered air-source heat pumps. These systems move heat rather than generating it directly through combustion.
Depending on operating mode:
In heating mode, a heat pump extracts heat from outdoor air and transfers it indoors.
In cooling mode, it reverses the process and removes heat from the building.
Air-source heat pumps were attractive because they could support lower-carbon operation and integrate with a building designed to minimize heat loss.
Hybrid Systems Strategy
The project eventually moved toward a hybrid strategy in which:
Many systems would be routed through or along the double-hull enclosure.
Air-source heat pumps and other major infrastructure could be supported from land.
A small mainland building could contain or support some equipment.
The ship would remain operationally independent in many respects while being connected to external utilities.
This approach avoided forcing every piece of equipment into the ship itself. It also allowed the project to preserve interior space and reduce the amount of mechanical infrastructure installed within the historic vessel.
Plugging the Ship into the Mainland
The ship could be connected to mainland systems for:
Electricity.
Plumbing.
Mechanical support.
Waste handling.
Other utilities.
A vacuum plumbing system was considered for toilets and related functions. Such systems can reduce water use and limit the size of waste and drainage infrastructure.
The overall strategy distinguished between:
Systems that should be integrated into the ship.
Systems that could be placed externally.
Systems that could be prefabricated and connected to the ship.
Systems that needed to remain within each compartment.
This is an example of distributed infrastructure planning, in which a building’s services are not necessarily contained entirely within the building envelope.
Enclosure Design Alternatives
The design team developed three broad enclosure strategies. Each responded differently to the ship’s curved geometry, existing structure, and need for improved thermal performance.
Baseline Marine Assembly
The first approach followed a more conventional marine construction method. It included some combination of:
Ballast or fill within the double hull to help stabilize the ship.
Spray-applied closed-cell foam.
An air gap.
A grid or support system.
Thermally broken clips.
Mineral-wool insulation.
Additional air space.
A final exterior finish.
This approach relied on familiar marine materials and assemblies. It could provide:
Thermal resistance.
Fire performance.
Structural protection.
A layered enclosure.
However, it could also introduce complexity and added material thickness. Spray foam would need to be evaluated carefully for fire, moisture, aging, repairability, and compatibility with the historic structure.
Continuous Marine-Grade Coating and Mineral Wool
The second approach proposed using a continuous marine-grade coating over the steel structure. This coating could serve several functions at once:
Fire protection.
Air control.
Protection of the steel.
Continuity across parts of the enclosure.
The strategy then relied primarily on mineral-wool insulation rather than spray foam. A separate vapor-control layer was also considered within the assembly.
Advantages of this approach included:
Avoiding extensive spray foam.
Using mineral wool, which offers strong fire resistance.
Creating a more continuous air-control layer.
Taking advantage of a coating already suited to marine conditions.
Simplifying the relationship between fire protection and air sealing.
The exact performance of the assembly would still depend on climate, vapor-permeability analysis, detailing, and the continuity of the coating.
Three-Dimensional Scanning and Prefabricated Panels
The third approach took advantage of the ship’s complex curved geometry. The idea was to:
Three-dimensionally scan the ship.
Use the digital model to document its exact surface.
Design enclosure panels or modules to match the scanned geometry.
Prefabricate those elements away from the ship.
Install them using a series of slots, clips, or attachment points.
This could produce a highly accurate enclosure system and reduce the need for extensive on-site adjustment.
However, the method would likely be more expensive because of:
Scanning and digital modeling.
Custom fabrication.
Nonstandard panel shapes.
Complex transportation and installation.
Specialized attachment systems.
Coordination with existing ship structure.
Despite the cost, the approach was considered promising because the ship’s curvature made standardized rectangular assemblies difficult to apply.
Upper Decks and Changing Enclosure Conditions
The Promenade and Sports Decks
At the lower portions of the ship, the double-hull system provided a major enclosure and service cavity. At the upper levels, including the promenade deck and sports deck, the geometry changed.
The ship was no longer organized in the same way as the lower double hull. The enclosure became more similar to a conventional building placed on top of a structure.
Treating the Upper Structure as a Building
From the promenade deck upward, the design had to address:
Continuous air sealing.
Conditioned interior volumes.
Floor and roof assemblies.
Thermal bridges.
Fire compartmentation.
Connections between new enclosure systems and historic steel.
The floor below the upper volume could act as a separate zone, while the upper floors could be treated as their own conditioned spaces.
This distinction was important because the upper part of the ship could not rely on exactly the same enclosure logic as the lower hull. The design had to change as the ship’s form changed.
Thermal Modeling and Performance Analysis
Modeling Existing Conditions
The team studied how the ship performed before and after insulation was added. Because the vessel was made largely of metal, the uninsulated structure would be highly conductive and vulnerable to temperature changes.
Thermal modeling helped identify:
Cold areas.
Hot areas.
Heat-flow paths.
Thermal bridges.
Potential condensation zones.
Locations where insulation would be most effective.
Areas requiring improved detailing.
Thermal Bridging
A thermal bridge is a part of an enclosure where heat flows more easily than through the surrounding insulated assembly. In a ship, thermal bridges can occur at:
Steel ribs.
Structural connections.
Window frames.
Deck connections.
Bulkhead intersections.
Exterior clips and fasteners.
Areas where insulation is interrupted.
Thermal bridges can cause:
Increased heat loss.
Interior surface cooling.
Condensation risk.
Uneven comfort.
Reduced energy performance.
The studies showed that simply adding insulation would not solve every problem. The connections between the existing steel structure and the new enclosure had to be analyzed and detailed carefully.
Relocating Mechanical Systems
The thermal studies also helped determine where mechanical and electrical systems should be placed. Areas that appeared vulnerable to heat loss or condensation could not necessarily be used as service zones without additional protection.
The design therefore used analysis to decide:
Where systems could safely run.
Where insulation needed to remain continuous.
Where thermal bridges required special treatment.
Which spaces could remain unconditioned.
How the enclosure and MEP systems could coexist.
Preserving the Ship’s Structural Expression
The ship’s ribs were visually important. They communicated the vessel’s identity and expressed its maritime construction.
The design team wanted to preserve these ribs rather than conceal them behind a generic building envelope. This created a tension between:
Architectural expression, which favored exposing the ribs.
Energy performance, which required continuous insulation and air control.
Historic preservation, which favored retaining original structural character.
Constructability, which required practical attachment and fabrication systems.
The solution required the enclosure, structure, and building systems to be designed together. The ribs were not merely decorative elements; they were part of the thermal and structural problem.
This is a central lesson of adaptive reuse: historic features often need to serve multiple roles simultaneously.
Air Sealing and Fireproofing at Structural Laps
The ship’s metal enclosure was composed of plates and laps. Each lap had to be treated carefully to prevent uncontrolled air movement.
A likely sequence included:
Sealing the laps and joints with an appropriate sealant or air-control treatment.
Establishing a continuous air barrier across the ship’s exterior skin.
Applying fireproofing to protect the steel and meet building requirements.
Installing spray foam, mineral wool, or another insulation system where appropriate.
Detailing windows, penetrations, and transitions.
Installing interior finishes and service systems.
The presentation emphasized the need for airtightness because the ship’s hollow cavities could otherwise support convective circulation.
Reusing King Posts
Structural and Historical Significance
The ship’s king posts were prominent structural elements. They contributed to the vessel’s identity and could support cable or other structural systems.
Rather than treating them as obsolete features, the project explored using them as active parts of the new building systems.
Integrating Ventilation
The proposed concept routed ERV ductwork through the king posts:
One post or pathway could serve as a supply route.
Another could serve as a return route.
The existing structural elements could remain visible.
Mechanical infrastructure could be integrated into the ship’s historical form.
This approach transformed the king posts into functional architectural infrastructure.
Heat Pumps in the Roof
A specialized roof design was also considered so that small air-source heat pumps could be located at the roof level. The systems could then:
Remain integrated with the building design.
Vent directly to the exterior.
Avoid being treated as completely separate rooftop objects.
Reduce the need for long mechanical runs.
Preserve interior space.
The challenge was to find equipment small enough to fit the available spaces while maintaining:
Proper airflow.
Service access.
Acoustic control.
Visual compatibility.
Efficient operation.
Prefabrication and Modular Installation
The king-post and roof systems were envisioned as potentially prefabricated components. Prefabrication could allow systems to be:
Fabricated accurately off-site.
Coordinated with the ship’s complex geometry.
Installed more quickly.
Integrated with structural and enclosure elements.
Repeated where appropriate.
However, the design still needed to account for the highly individualized geometry of the historic vessel.
Reusing Lifeboats as Programmed Spaces
From Emergency Equipment to Architectural Space
The ship’s lifeboats were iconic but no longer usable for their original emergency function. Rather than removing them, the project proposed reimagining them as occupied spaces or “cabana”-like rooms.
The lifeboats would retain:
Their approximate existing floor area.
Their recognizable external form.
Their relationship to the ship’s history.
Their connection to the promenade deck.
They would gain a new function while remaining visually associated with their original purpose.
High-Performance Lifeboat Enclosures
The proposed conversion applied the same principles used in high-performance buildings:
A continuous insulated shell.
A reliable air barrier.
Carefully detailed enclosure connections.
Integrated plumbing and mechanical systems.
Ventilation equipment connected through the upper portion of the structure.
The lifeboat’s shiny metal exterior could remain part of its visual identity while new insulation and control layers were added behind or within it.
Experience of Old and New
The transformed lifeboats would offer occupants a hybrid experience:
The original structural and historical form would remain visible.
The interior would function as a modern conditioned space.
New building systems would be integrated without erasing the maritime character.
The space would allow occupants to experience the ship’s history in a new way.
This illustrates the broader adaptive-reuse principle of preserving recognizable character while changing performance and function.
Resilience, Adaptive Reuse, and Future Building Types
The project raised broader questions about what qualifies as a building and how society should respond to changing climate conditions.
Resilience Through Reuse
Resilience is not limited to strengthening new buildings. It can also involve:
Reusing existing structures.
Avoiding demolition and replacement.
Extending the life of durable objects.
Adapting infrastructure to new environmental conditions.
Integrating new technologies into historic forms.
A ship can be resilient because it was originally designed to remain dry, resist water, and function in a demanding environment. Those characteristics may become increasingly valuable as flooding and sea-level rise affect land-based construction.
Floating Structures and Flood Risk
As flood levels rise, floating or water-adapted structures may become more relevant. This does not mean ships automatically solve climate problems. They still require:
Efficient energy systems.
Safe utility connections.
Reliable wastewater management.
Fire protection.
Structural evaluation.
Moisture control.
Long-term maintenance.
Protection from corrosion.
However, their original relationship to water gives them a different starting point than conventional buildings.
Future-Proofing Beyond Conventional Buildings
The project challenges the assumption that future buildings must be newly constructed on land. Future-proofing could involve:
Transforming ships into occupied buildings.
Reusing industrial structures.
Converting transportation infrastructure.
Designing buildings that can move, float, or adapt.
Combining on-site and off-site energy systems.
Using existing structural cavities for new technology.
The SS United States served as a case study in how an existing object can be reinterpreted as a high-performance building without abandoning its original identity.
Key Design Principles
1. Treat Existing Structure as Infrastructure
Bulkheads, double-hull spaces, king posts, and lifeboats were not merely constraints. They could support:
Air control.
Thermal protection.
Mechanical distribution.
Program organization.
Historical expression.
2. Use Compartmentalization to Control Air and Heat
The ship’s watertight compartments could also limit convective loops, separate conditioned zones, and organize mechanical systems.
3. Preserve Continuous Control Layers
A high-performance retrofit requires continuous:
Air barriers.
Vapor-control strategies.
Insulation.
Fire protection.
Water-shedding surfaces.
Breaks at laps, penetrations, windows, and structural connections can undermine the whole enclosure.
4. Adapt the Enclosure to Changing Geometry
The lower hull, promenade deck, sports deck, and upper structures required different enclosure strategies. One assembly could not be applied uniformly across the entire ship.
5. Protect Interior Space
Routing systems through the double hull or connecting them to mainland infrastructure helped preserve:
Headroom.
Occupied floor area.
Historic interior volume.
Architectural character.
6. Combine Preservation with Performance
Historic elements such as ribs, king posts, and lifeboats could remain visible and meaningful while also supporting modern building systems.
7. Use Digital Fabrication for Complex Forms
Three-dimensional scanning and prefabrication can help create accurate enclosure components for curved and irregular structures, although the approach may increase cost and coordination requirements.
8. Analyze Before Adding Insulation
Thermal modeling is necessary to identify:
Thermal bridges.
Cold surfaces.
Hotspots.
Condensation risks.
Locations where insulation must remain continuous.
Appropriate routes for mechanical and electrical systems.
Overall Significance
The SS United States retrofit study demonstrates how building science can be applied to a structure that was not originally intended to function as a land-based building. Its metal enclosure, double hull, bulkheads, and maritime systems provided both challenges and opportunities.
The project’s most important insight is that adaptive reuse and high-performance design can reinforce each other. Existing elements can be retained not only for historical reasons but also because they can become part of the new building’s environmental and mechanical systems.
The ship could potentially function as a future-oriented building by combining:
Its original watertight construction.
Airtight enclosure detailing.
New insulation.
Compartmentalized service zones.
Energy recovery ventilation.
Air-source heat pumps.
External utility support.
Digital fabrication.
Reuse of historic structural elements.
The resulting design approach treats the ship as both a historic artifact and an experimental building system: a structure capable of carrying its past into a lower-carbon, climate-adaptive future.