- 1A project is an endeavor that has a definite_____and end.
Hint
Think about the two boundaries that distinguish a project from ongoing work.
Answer
beginning
- 2A project creates a unique result, product, service, or_____.
Hint
This is the fourth example of a unique project output mentioned in the definition.
Answer
document
- 3Building a house can qualify as a project because every house is somewhat_____.
Hint
The defining project characteristic is not that the activity is never repeated, but that its outcome varies.
Answer
different
- 4A project may involve a single individual or_____individuals.
Hint
Think of projects that require a team rather than only one person.
Answer
multiple
- 5Project participants may come from different organizational_____.
Hint
Examples include departments, divisions, or other parts of an organization.
Answer
units
- 6Planning a holiday meal, cleaning a garage, and building a room are all examples of_____.
Hint
Each activity has a desired result and a completion point.
Answer
projects
- 7A project should have a target date or_____by which its result is intended to be completed.
Hint
This is a significant planned point in the project schedule.
Answer
milestone
- 8The basic project phases described are starting, planning, performing the work, and_____it.
Hint
This phase occurs after the work has been performed.
Answer
finishing
- 9Project management can be applied as a professional competency and as an everyday_____skill.
Hint
The presentation connects project management to activities outside formal employment.
Answer
life
- 10Project management involves more than creating a schedule because it also requires individual and_____competencies.
Hint
These competencies concern working with people and guiding an effort.
Answer
leadership
- 11The PMBOK Guide is a guide to the Project Management Body of_____.
Hint
This is the final word in the guide's full title.
Answer
Knowledge
- 12The PMBOK Guide identifies project management best practices, skills, tools, and_____.
Hint
Tools are commonly paired with this word when describing methods.
Answer
techniques
- 13The PMBOK Guide is continually updated as new ideas and_____practices emerge.
Hint
The guide records recommended ways of working.
Answer
best
- 14One purpose of the PMBOK Guide is to provide a common_____among project managers.
Hint
This allows professionals to understand terms such as risk register and project charter.
Answer
terminology
- 15The practices in the PMBOK Guide are recommendations, so the team must decide what is_____for its particular project.
Hint
The amount of documentation and process should fit the task.
Answer
appropriate
- 16Project documentation should be proportional to the project's duration and_____.
Hint
A short, simple effort should not require months of planning.
Answer
complexity
- 17Before detailed planning begins, the team should identify why the project is being done, who requested it, and what it is expected to_____.
Hint
This concerns the project's intended outcome.
Answer
achieve
- 18A project charter formally_____the project.
Hint
The charter gives official permission for the project to proceed.
Answer
authorizes
- 19The project charter authorizes the project manager to spend project_____.
Hint
In this context, resources especially include money, people, and equipment.
Answer
resources
- 20A project charter should generally be written within the first_____of the project.
Hint
The presentation recommends completing it very early.
Answer
week
- 21For executive audiences, the project charter should usually be concise, ideally about_____page.
Hint
The recommendation is to summarize only the most important information.
Answer
one
- 22A stakeholder is anyone who cares about the project or may be_____by its work.
Hint
Stakeholders can be affected by the project or affect it themselves.
Answer
impacted
- 23Stakeholders can affect a project or be_____by it.
Hint
This describes the two-way relationship between a project and its interested parties.
Answer
affected
- 24Stakeholder analysis should consider people's concerns, interests, influence, interdependencies, and potential_____.
Hint
This refers to the possible effect a stakeholder can have on the project.
Answer
impact
- 25Stakeholders whose influence is not immediately visible, such as lobbyists operating in the background, may be called_____stakeholders.
Hint
They exist and can influence the project even when the team does not clearly see them.
Answer
blind
- 26The project team consists of the people who help perform the project_____.
Hint
They may include experts, sellers, partners, and customer representatives.
Answer
work
- 27Organizations or individuals contracted to provide services to a project are called_____.
Hint
They sell their services to the project.
Answer
sellers
- 28A team that works directly on the effort is the_____team.
Hint
It is contrasted with an extended team that joins when needed.
Answer
core
- 29A team that brings people in when their expertise is needed is an_____team.
Hint
It extends beyond the people working continuously on the project.
Answer
extended
- 30A team whose members work in different locations and communicate primarily through technology is a_____team.
Hint
Its members may be separated by cities, countries, or time zones.
Answer
virtual
- 31Virtual teams allow organizations to access expertise from many locations rather than being limited to the local_____.
Hint
This is the geographic region near the project site.
Answer
area
- 32A major challenge of virtual teams is that members may feel_____because they lack regular face-to-face contact.
Hint
This describes feeling separated from other people.
Answer
isolated
- 33Ongoing day-to-day work in an organization is called an_____rather than a project.
Hint
Registering students and presenting recurring courses are examples.
Answer
operation
- 34Both projects and operations are performed by people, constrained by limited resources, and planned, executed, and_____.
Hint
This activity involves monitoring work to keep it aligned with expectations.
Answer
controlled
- 35The three commonly discussed project constraints are cost, time, and_____.
Hint
This constraint concerns the required level or standard of the result.
Answer
quality
- 36A project manager must determine which constraint is the most important because constraints require_____.
Hint
Improving one constraint may require sacrificing another.
Answer
trade-offs
- 37In some casino projects, the dominant constraint was the_____rather than the budget.
Hint
The project had to be completed by a fixed opening date.
Answer
schedule
- 38A project to create a brand-new course would be initiated because creating the course is temporary and produces a_____result.
Hint
This distinguishes the course-development effort from repeatedly presenting an existing course.
Answer
unique
- 39An assumption is something the plan believes will be_____so the work can proceed.
Hint
For example, the plan may assume that key individuals will be ready to work.
Answer
available
- 40A constraint identifies something known that could go_____and create a project problem.
Hint
It limits the team's ability to execute the plan.
Answer
wrong
- 41For every planning assumption, there may be a corresponding_____if that assumed condition fails.
Hint
The unavailable resource becomes a limitation on the project.
Answer
constraint
- 42Requirements should be specific and detailed enough to allow_____and validation.
Hint
This process checks whether the work was done correctly.
Answer
verification
- 43Verification checks whether the work was done_____.
Hint
It focuses on conformity to the requirement.
Answer
correctly
- 44Validation determines whether the completed work is approved and can move_____.
Hint
Approval allows the project to proceed to the next step.
Answer
on
- 45A facilitated session brings relevant people together to discuss and capture project_____.
Hint
Participants clarify what the project must produce.
Answer
requirements
- 46Facilitation keeps the discussion on track while ensuring that information is_____.
Hint
The facilitator does not make every decision but records the group's input.
Answer
captured
- 47Requirements should be discussed so all participants develop the same understanding of the project_____.
Hint
Without discussion, different people may imagine different outputs.
Answer
result
- 48A work breakdown structure organizes_____that must be done for the project.
Hint
It decomposes the project into grouped areas of work.
Answer
everything
- 49In the Post-it exercise, tasks are grouped visually into branches of a_____.
Hint
The structure resembles a central trunk with branches for related work.
Answer
tree
- 50The work breakdown structure can reveal tasks that the team had_____out.
Hint
It exposes omissions in the original list of work.
Answer
left
- 51A schedule represents the order in which project tasks need to be_____.
Hint
It answers the question of what must happen before something else.
Answer
done
- 52A task that must occur before another task establishes a dependency or_____relationship.
Hint
Planting follows activities such as preparing the ground.
Answer
precedence
- 53The critical path is the_____path through the project.
Hint
A delay anywhere on this path delays the overall project.
Answer
longest
- 54A delay in a critical-path activity can delay the_____project.
Hint
Critical-path tasks have no usable schedule flexibility.
Answer
whole
- 55Critical chain focuses on the availability of critical_____rather than only task sequence.
Hint
A specialized person or piece of equipment may control progress.
Answer
resources
- 56Buffers provide schedule_____that can absorb unexpected delays.
Hint
They are described informally as wiggle room.
Answer
flexibility
- 57When a project is behind schedule, adding more people to accelerate the work is called_____.
Hint
This schedule-compression technique adds resources.
Answer
crashing
- 58Starting some work before all preceding work is complete creates an_____relationship.
Hint
This approach can shorten the schedule but requires some information to remain unfinished.
Answer
overlapping
- 59In a sequential phase-to-phase relationship, the current phase must be completed before the_____phase begins.
Hint
Approved blueprints are needed before construction begins.
Answer
next
- 60An adaptive life cycle is commonly associated with_____project approaches.
Hint
This approach emphasizes short cycles and responding to change.
Answer
Agile
- 61Agile approaches divide work into small groups called_____.
Hint
Each cycle produces an opportunity to learn and adjust.
Answer
iterations
- 62An iteration usually operates within a fixed amount of time or_____.
Hint
The team determines what can be completed within this limit.
Answer
money
- 63After an iteration, the team can reprioritize what should be done in the_____iteration.
Hint
Adaptive planning postpones some decisions until more is known.
Answer
next
- 64A retrospective review asks what the team did right and what it could do_____.
Hint
The purpose is continuous improvement.
Answer
better
- 65Rolling wave planning gives the greatest detail to work being done_____.
Hint
Future work remains less defined until it approaches.
Answer
now
- 66Progressive elaboration adds increasing detail as the project moves_____into future work.
Hint
The plan becomes more specific when the work is nearer to execution.
Answer
closer
- 67Adaptive planning is useful when the environment changes rapidly, such as in_____efforts.
Hint
Customer preferences and market conditions can shift quickly.
Answer
marketing
- 68During performing, the project manager compares planned accomplishments with what has actually been_____.
Hint
This comparison identifies variance from the plan.
Answer
accomplished
- 69Changing project work in the middle of execution without approval may constitute a change_____.
Hint
This formal term is used when proposed work differs from the approved plan.
Answer
request
- 70A corrective action fixes something that is currently being done_____.
Hint
It addresses an existing deviation or problem.
Answer
incorrectly
- 71A preventative action is taken to stop a problem from_____or getting worse.
Hint
It addresses potential future deterioration.
Answer
continuing
- 72A defect is a problem that must be_____using appropriate time, resources, or money.
Hint
The response addresses something that is not acceptable.
Answer
fixed
- 73A project manager should be both preventative and_____.
Hint
The second quality involves anticipating issues instead of waiting for them to be reported.
Answer
proactive
- 74Effective project communication should be concise, timely, clear, and appropriate to the_____.
Hint
The same message may need different wording for different audiences.
Answer
context
- 75If a communicator repeatedly exaggerates problems, recipients may stop_____to future warnings.
Hint
The presentation compares this behavior to repeatedly crying wolf.
Answer
listening
- 76A communication plan identifies who receives information, what is delivered, how it is delivered, and how much_____is appropriate.
Hint
Different audiences may need different levels of explanation.
Answer
detail
- 77A communication plan should specify how often information is_____.
Hint
This concerns the frequency of status reports or other messages.
Answer
delivered
- 78Before sending an approved document, the project manager should understand the approval_____and its required steps.
Hint
Several people may need to review or sign off before release.
Answer
workflow
- 79Communication should include feedback to verify that the recipient_____the message.
Hint
What the sender intended may differ from what the listener heard.
Answer
understood
- 80The project manager must communicate with the team, sponsor, and_____when managing change.
Hint
These are all people who may be affected by or influence the project.
Answer
stakeholders
- 81Administrative closure includes documenting what worked, what did not, and preserving_____for future projects.
Hint
These are learned insights that can improve later work.
Answer
lessons
- 82A project is not fully closed until its deliverables have been completed and_____.
Hint
The result must be accepted by the appropriate authority.
Answer
approved
- 83The final comparison of promised work with completed work is part of project_____.
Hint
This confirms that the result meets the agreed expectations.
Answer
validation
- 84Unapproved deliverables should be recorded so the team can understand why they were rejected and avoid repeating the_____.
Hint
The record supports future improvement.
Answer
problem
- 85Providing feedback to a team member's management is a form of performance_____.
Hint
It evaluates the person's contribution and involvement.
Answer
assessment
- 86Project completion should include recognition and celebration of the team's_____.
Hint
Celebration provides positive reinforcement after difficult work.
Answer
success
- 87Project closure is important because stored project information can help other people_____from the experience.
Hint
The knowledge becomes useful beyond the original project.
Answer
learn
- 88A project manager needs technical knowledge as well as strong_____skills.
Hint
These skills involve communication, motivation, and teamwork.
Answer
people
- 89Interpersonal skills are also known as_____skills.
Hint
They contrast with technical or hard skills.
Answer
soft
- 90Emotional intelligence helps a leader understand and apply_____when working with a group.
Hint
It concerns awareness of one's own and others' feelings.
Answer
emotions
- 91Group facilitation helps people interact, communicate, and combine their_____.
Hint
A facilitator enables productive collective discussion.
Answer
ideas
- 92A project manager must balance ethical, interpersonal, and_____skills.
Hint
This third category involves seeing the broader situation and relationships among its parts.
Answer
conceptual
- 93Leadership includes motivating team members and communicating clearly what needs to be_____.
Hint
Team members need a shared understanding of the expected work.
Answer
done
- 94Project managers may use coaching and_____to develop other people.
Hint
Both activities support another person's growth and learning.
Answer
mentoring
- 95Negotiation seeks a give-and-take outcome that can be described as_____-win.
Hint
The preferred result benefits all sides rather than producing one winner and one loser.
Answer
win
- 96Building trust, managing conflict, influencing people, and making decisions are examples of project_____skills.
Hint
These abilities help a manager guide people toward a shared result.
Answer
leadership
- 97A project manager should understand political and_____awareness when working across organizations or cultures.
Hint
This concerns differences in values, practices, and social expectations.
Answer
cultural
- 98The PMI Code of Ethics applies to project managers, including those who are certified or who_____with PMI.
Hint
It covers people who contribute to the professional association without necessarily being employees.
Answer
volunteer
- 99The four aspects of the PMI Code of Ethics are responsibility, respect, fairness, and_____.
Hint
This final principle requires telling the truth and avoiding concealment.
Answer
honesty
- 100Taking responsibility means doing what you say you are going to_____.
Hint
This principle connects commitments with actions.
Answer
do
- 101Respect must be shown to team members, stakeholders, and_____people involved.
Hint
The principle is not limited to the immediate project team.
Answer
all
- 102Fairness requires avoiding preferential treatment and applying standards consistently to_____people.
Hint
The code rejects giving some individuals unfair advantages.
Answer
different
- 103Mandatory ethical standards require project managers not to cheat or_____.
Hint
This is the opposite of honest communication.
Answer
lie
- 104A project manager must disclose and avoid a conflict of_____.
Hint
This occurs when personal interests could improperly influence professional judgment.
Answer
interest
- 105A contractual obligation requires the project manager to meet the needs of the_____.
Hint
This is the formal agreement defining required obligations.
Answer
contract
- 106PMI distinguishes between mandatory standards and_____standards.
Hint
These standards describe ideals people should strive toward rather than minimum requirements.
Answer
aspirational
- 107Knowing one's values makes ethical_____easier.
Hint
Clear principles help guide choices in difficult situations.
Answer
decisions