Project Management Lecture

  • 91Unfamiliar
  • 0Learning
  • 0Familiar
  • 0Mastered
Topic: Project Foundations
  • spaceFlip card
  • KI knew it
  • DI didn't know it
  • ←Previous card
  • →Next card

What defines a project?

Tap to flipClick to flipspace

A project has a definite beginning and end and creates a unique product, service, result, or document.

Or swipe the card

91 cards

  1. What defines a project?

    A project has a definite beginning and end and creates a unique product, service, result, or document.

  2. Why is building a house considered a unique project even when many houses are built?

    Each house differs in its people, tools, location, requirements, and circumstances.

  3. Can a project involve only one person?

    Yes, although projects usually involve multiple individuals with different roles and levels of involvement.

  4. What kinds of organizational structures can project participants come from?

    They may come from one organization, multiple units, different organizations, families, or communities.

  5. What are examples of everyday projects?

    Planning a party or meal, cleaning a garage, adding a room, or redesigning landscaping.

  6. What is project management?

    Project management addresses stakeholder needs, concerns, and expectations while organizing work to achieve a project result.

  7. What is the difference between a project and an operation?

    A project is temporary and unique; an operation is ongoing, repetitive, day-to-day work.

  8. What characteristics do projects and operations share?

    Both are performed by people, use limited resources, and are planned, executed, and controlled.

  9. What are the four broad phases of a project?

    Starting, planning, performing the work, and finishing or closing the project.

  10. Why must a project have a target date or milestone?

    It establishes when the project or a major result is intended to be completed.

  11. What is the PMBOK Guide?

    A PMI guide describing generally accepted project management best practices, skills, tools, techniques, and terminology.

  12. What is the purpose of common project management terminology?

    It gives project managers a shared language for discussing tools, techniques, documents, and work.

  13. Are all practices in the PMBOK Guide required for every project?

    No. They are recommended practices that must be tailored to the project's needs.

  14. How should project documentation be scaled?

    Documentation should be proportional to the task; a small project may need one page rather than extensive binders.

  15. What is a stakeholder?

    Anyone who can affect the project, is affected by it, or cares about its outcome.

  16. Why must project managers identify stakeholder concerns?

    Stakeholder concerns can impose requirements, create risks, influence decisions, or affect acceptance of the result.

  17. What should a project manager assess about stakeholders?

    Their interests, reasons for involvement, influence, potential impact, interdependencies, and preferred involvement timing.

  18. What are common project constraints?

    Time, cost, quality, resources, regulations, and other limits that restrict how the work can be performed.

  19. Why must project managers prioritize constraints?

    When constraints conflict, the manager must know which is most important to guide trade-offs.

  20. What is an assumption in project planning?

    A condition believed to be true and used as the basis for requirements or planning.

  21. What is a constraint related to an assumption?

    It is the limitation or potential problem that arises if the assumed condition is not true.

  22. What is the main purpose of the starting phase?

    To determine why the project is being undertaken, who requested it, and what outcome is expected.

  23. What is a project charter?

    A document that formally authorizes the project and gives the project manager authority to use organizational resources.

  24. When should a project charter generally be created?

    As soon as possible, ideally within the first week or first few days of the project.

  25. What high-level information should a project charter contain?

    The purpose, success criteria, major requirements, constraints, schedule targets, budget information, approval requirements, project manager, authority, and sponsor.

  26. Why should a project charter identify final approval requirements?

    It defines who will approve the result and what criteria they will use to determine whether the project is complete.

  27. What is the role of the project sponsor?

    The sponsor is the individual or group that supports and funds the project and is accountable for its authorization.

  28. Why should a project manager identify the project team early?

    The project manager needs the appropriate expertise, people, equipment, money, and approvals to perform the work.

  29. What is a business case?

    A justification for undertaking a project that may describe return on investment, objectives, and strategic alignment.

  30. What is the main purpose of the planning phase?

    To determine in greater detail what must be done, who will do it, when it will occur, and how it will be accomplished.

  31. How should planning detail change over the course of a project?

    Planning should become more detailed as the team gains information and approaches the work.

  32. What is a requirement?

    A specific need or condition that the project result must satisfy.

  33. What is a facilitated session?

    A structured meeting in which participants collaboratively discuss and develop requirements or other project information.

  34. Why must requirements be discussed and agreed upon?

    Without shared discussion, stakeholders may hold different expectations about the product or result.

  35. What is verification?

    Checking that the work or result was produced correctly according to the requirements.

  36. What is validation?

    Confirming that the completed result meets the request and is approved for acceptance.

  37. What is a work breakdown structure?

    A structured breakdown of the total work needed to complete a project.

  38. How can Post-it notes help create a work breakdown structure?

    Participants write tasks on notes, group related tasks, and organize the groups into a hierarchical structure.

  39. Why should planning effort be proportional to the project?

    A short or simple project should not require months of planning or excessive documentation.

  40. What is a project schedule?

    An ordered representation of project activities showing when work should occur and how activities depend on one another.

  41. What is a dependency?

    A relationship in which one activity relies on another activity being completed or started.

  42. What is the critical path?

    The longest sequence of dependent activities that determines the project's minimum completion time.

  43. What is the critical chain?

    A scheduling approach that considers resource limitations and the effect of critical resources on project completion.

  44. Why are buffers or schedule reserves used?

    They provide flexibility for delays, uncertainty, and variation in the work.

  45. What is a sequential phase-to-phase relationship?

    A relationship in which one phase must be sufficiently completed before the next phase begins.

  46. What is an overlapping phase relationship?

    A relationship in which parts of different phases proceed at the same time to shorten the schedule.

  47. What is an adaptive life cycle?

    An approach that divides work into short iterations and adjusts priorities and plans as learning occurs.

  48. What is an iteration?

    A fixed period or work cycle in which the team completes a selected portion of the project and then reassesses priorities.

  49. What is a retrospective review?

    A review at the end of an iteration in which the team identifies what went well and what should improve.

  50. What are rolling-wave planning and progressive elaboration?

    They are approaches that develop near-term work in detail while leaving later work at a higher level until more is known.

  51. What is the purpose of monitoring during project performance?

    To compare planned work with actual progress and determine whether adjustments are needed.

  52. Why should a project manager control changes to the plan?

    Unapproved changes can affect scope, time, cost, resources, quality, and the original objectives.

  53. What is a change request?

    A formal request to modify an approved aspect of the project.

  54. What is corrective action?

    An action that fixes a current deviation or problem in project performance.

  55. What is preventive action?

    An action taken to reduce the likelihood or impact of a future problem.

  56. Why should project managers be proactive?

    They should identify developing problems early and act before those problems cause major disruption.

  57. What is the difference between corrective and preventive action?

    Corrective action fixes an existing problem; preventive action reduces the chance of a future problem.

  58. Why is communication essential during project execution?

    It keeps the team, sponsor, stakeholders, and other affected parties informed about progress, decisions, risks, and changes.

  59. What qualities make project communication effective?

    It should be concise, clear, timely, appropriately formatted, properly targeted, and suitable for its context.

  60. What should a communications management plan identify?

    Who needs information, what information they need, how and when it will be delivered, its level of detail, and who supplies it.

  61. Why must project communication account for approval workflows?

    Approvals may require several people and can delay the release of documents or information.

  62. What is a virtual team?

    A team whose members work together through technology with little or no face-to-face contact.

  63. What is a major advantage of virtual teams?

    They provide access to expertise from many locations and can enable work across different time zones.

  64. What are common challenges of virtual teams?

    Misunderstandings, isolation, time-zone differences, cultural and language barriers, technology costs, and hidden conflict.

  65. Why is feedback important in virtual and global teams?

    Feedback confirms whether the message was understood as intended and helps prevent communication errors.

  66. What is the purpose of project closure?

    To confirm completion and acceptance, archive information, assess performance, provide feedback, and formally close the project.

  67. What is administrative closure?

    The formal completion of project records, documentation, approvals, evaluations, and other closing activities.

  68. Why should project documents and lessons be archived?

    They help the organization learn from the project and reuse useful information on future efforts.

  69. What should a project manager assess during closure?

    What was completed, what worked, what did not work, what was accepted or rejected, and what should change in the future.

  70. Why should project team members receive performance feedback?

    Feedback recognizes contributions, supports development, informs management, and provides useful recommendations for future opportunities.

  71. Why is celebrating project completion valuable?

    It recognizes effort, reinforces accomplishment, and provides positive feedback after difficult work.

  72. What three broad competency areas does a project manager need?

    Knowledge, performance, and personal or behavioral competencies.

  73. Why are technical project management skills alone insufficient?

    A person may create a schedule yet fail to lead, communicate with, motivate, or coordinate the people needed to complete the project.

  74. What are interpersonal or soft skills?

    Competencies that help people communicate, lead, motivate, influence, negotiate, build trust, and work together.

  75. Why is emotional intelligence important for project managers?

    It helps managers understand emotions, relationships, reactions, and motivations when working with individuals and teams.

  76. What is group facilitation?

    Helping a group interact, communicate, organize ideas, and reach useful results.

  77. What leadership skills are important in project management?

    Team building, motivation, communication, influence, decision-making, conflict management, coaching, mentoring, and trust building.

  78. Why must project managers understand cultural and political awareness?

    Culture and organizational politics influence communication, decision-making, relationships, expectations, and stakeholder behavior.

  79. What is the difference between a win-win and a win-lose outcome?

    A win-win outcome benefits the parties involved, while a win-lose outcome benefits one party at another's expense.

  80. How should a project manager motivate team members?

    By understanding individual needs, recognizing contributions, encouraging people, and avoiding rewards that conflict with their preferences.

  81. What are the four values in PMI's code of ethics?

    Responsibility, respect, fairness, and honesty.

  82. What does responsibility mean in project management ethics?

    Taking ownership of commitments and doing what one has agreed to do.

  83. What does respect mean in project management ethics?

    Treating team members, stakeholders, and others with consideration and dignity.

  84. What does fairness mean in project management ethics?

    Making decisions impartially and avoiding favoritism or unequal treatment without justification.

  85. What does honesty mean in project management ethics?

    Telling the truth and avoiding lies, concealment, or misleading information.

  86. What is the difference between mandatory and aspirational ethical standards?

    Mandatory standards are required behaviors; aspirational standards describe ideals professionals should strive to achieve.

  87. Why are conflicts of interest ethically important?

    They can compromise impartial judgment or create the appearance that personal interests influence project decisions.

  88. What combination of expertise is useful for a project manager?

    Project management knowledge combined with knowledge of the relevant industry or technical field.

  89. Why might a technical specialist become a project manager?

    They may want to coordinate people and teamwork, lead efforts, and move beyond performing technical tasks alone.

  90. What is schedule compression?

    A set of techniques used to shorten a project schedule without changing the project scope.

  91. What is crashing?

    A schedule-compression technique that adds resources to shorten the duration of an activity or project.

Card 1 of 91
Card 1 of 91