Agile Project Management with Kanban
- 76Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
76 questions
- 1Kanban supports a workflow in which completed work can be delivered continuously rather than waiting for fixed release cycles; it was built for_____delivery.
Hint
Think of delivery that can happen as work is completed, rather than only at the end of a sprint.
Answer
continuous
Explanation
The speaker describes Kanban as built for continuous delivery, allowing work to be shipped frequently.
- 2In the speaker’s description, Kanban avoids milestones, sprints, and_____as sources of overhead.
Hint
The missing term refers to extra effort that does not directly contribute to product work.
Answer
overhead
Explanation
The talk says that with Kanban there are no milestones, sprints, or overhead.
- 3The speaker says quality happens at_____step of the workflow, rather than being checked only at the end.
Hint
Think about whether quality is handled throughout the process or only in a final phase.
Answer
every
Explanation
The speaker emphasizes that quality happens at every step.
- 4The speaker values Kanban because it helps the team spend its working time on actual_____going into the product.
Hint
This is what customers ultimately receive from useful product work.
Answer
value
Explanation
The speaker contrasts work that contributes indirectly with actual value going into the product.
- 5The visual centerpiece of the approach described is the_____board.
Hint
It is the board used to make the flow of work visible.
Answer
Kanban
Explanation
The speaker describes the Kanban board as the center of the approach.
- 6Kanban is presented as a tool to help a team_____its project, not as a rigid set of rules enforced by authorities.
Hint
The verb describes what the board helps a team do with its work.
Answer
manage
Explanation
The speaker says Kanban is a tool to help manage a project and that there are no Kanban police enforcing a single way to use it.
- 7The speaker recommends using Kanban primarily to manage work that takes a few_____rather than every brief interruption.
Hint
The talk distinguishes project-type work from tasks that take only minutes or an hour.
Answer
days
Explanation
Kanban is described as helpful for managing work that takes a few days, while short pieces of work can be handled as they come in.
- 8A personal Kanban board can be reduced to backlog, doing, and_____.
Hint
The last column contains work that has been completed.
Answer
done
Explanation
The speaker describes personal Kanban as a simple board with three columns: backlog, doing, and done.
- 9Kanban’s simplicity does not prevent teams from changing their process; the speaker says there are no hard and fast_____.
Hint
These are strict requirements that would dictate exactly how every team must work.
Answer
rules
Explanation
The speaker stresses that Kanban is flexible and does not impose hard and fast rules.
- 10The speaker characterizes Kanban as a way to improve work through_____improvement.
Hint
The term describes improvement that happens repeatedly over time.
Answer
continuous
Explanation
The speaker jokingly refers to continuous improvement while describing Kanban as an approach that teams can keep adjusting.
- 11Unlike a process that requires a single completion day for all work, Kanban lets teams finish items_____as they move through the workflow.
Hint
Think about work completing throughout the process rather than all at once.
Answer
continuously
Explanation
The speaker contrasts Kanban with approaches that have one specific day when a batch is finished; Kanban work completes continuously.
- 12In the example board, the initial collection of work waiting to be done is called the_____.
Hint
This is the ordered list of work items awaiting action.
Answer
backlog
Explanation
The speaker defines the backlog as the list of things the team has to do, typically prioritized in some way.
- 13A backlog may be compared with a feature list in a traditional_____approach.
Hint
This is the traditional development approach contrasted with Scrum and Kanban in the talk.
Answer
waterfall
Explanation
The speaker says that in a traditional waterfall approach, the backlog would be a feature list.
- 14Because backlog items can vary greatly in size, the team uses a_____step to split large items into manageable pieces.
Hint
This step turns a complicated item into smaller work items.
Answer
breakdown
Explanation
The speaker explains that items of different sizes should be broken down into more equally sized pieces.
- 15Some teams call the breakdown step_____because it includes a small amount of specification.
Hint
The alternate name refers to defining just enough detail before work is carried out.
Answer
specify
Explanation
The speaker says some people call breakdown specify because a little specification is done while dividing work into pieces.
- 16After work has been broken down, the next example step is to_____the question or implement the work.
Hint
In the talk’s question-answering demonstration, this is the step after breakdown.
Answer
answer
Explanation
The example workflow moves from breakdown to answering; in product development, this corresponds to implementation.
- 17The final example step checks that the answer or completed work meets the intended need; it is called_____.
Hint
This step confirms that the result is correct from the customer’s or questioner’s perspective.
Answer
validate
Explanation
The speaker adds a validate step to ensure the answer addresses the question that was actually asked.
- 18Kanban stages can be named according to the team’s needs, and teams can have as_____steps as they want.
Hint
The number of stages is flexible, not fixed by the example board.
Answer
many
Explanation
The speaker says teams can name steps anything they want and have as many steps as they want.
- 19Each workflow step is divided into an active column and a_____column.
Hint
The second column records that work in the step has been completed.
Answer
done
Explanation
The speaker says every step has an active and a done column, distinguishing work in progress from completed work at that stage.
- 20The active and done columns help a team specify what it means for work to be_____.
Hint
The team needs a clear criterion for moving an item out of active work.
Answer
done
Explanation
The speaker explains that the columns support explicit definitions of when something is finished.
- 21The criteria specifying when work in a step is finished are called_____rules.
Hint
The term names the rules that define completion for each stage.
Answer
done
Explanation
The speaker calls the criteria for completing a step done rules.
- 22In the example, a question is considered broken down only when each resulting question can be answered in less than_____minutes.
Hint
The example uses a short maximum duration to keep the pieces small.
Answer
two
Explanation
The speaker’s done rule for breakdown is that each question should take less than two minutes to answer.
- 23In the example answering step, the speaker’s done rule requires the question to be repeated and then_____.
Hint
Both restating the prompt and providing a response are required.
Answer
answered
Explanation
Because the talk is being recorded, the speaker says he should repeat the question and answer it before marking the step done.
- 24For the example validate step, work is done when the_____is satisfied.
Hint
This is the person who asked the question and judges whether the response was useful.
Answer
questioner
Explanation
The speaker’s validation criterion is that the questioner is satisfied with the answer.
- 25In software development, an implementation done rule might require code review and unit_____.
Hint
This practice checks small units of code as part of verifying implementation quality.
Answer
testing
Explanation
The speaker gives code review and unit testing as examples of checks that can be included in implementation done rules.
- 26A work in progress limit, abbreviated WIP limit, restricts how many_____may be in a workflow step.
Hint
These are the board markers representing work items.
Answer
stickies
Explanation
The speaker defines WIP limits as numbers that limit the stickies allowed in each step.
- 27WIP limits apply to the total items in a step, including items being worked on and items already marked_____.
Hint
The limit counts both active work and completed work within that step.
Answer
done
Explanation
The speaker clarifies that the limit includes stickies on either side of a step’s active/done division.
- 28Along with done rules, WIP limits help turn a board from a visualization tool into a project_____technique.
Hint
This is the broader activity of controlling and guiding project work.
Answer
management
Explanation
The speaker says that done rules and WIP limits are what make the approach project management rather than merely work visualization.
- 29To set an initial WIP limit for the longest step, the speaker starts with the number of people who can work on that_____.
Hint
The initial limit is based on the people available to perform the stage’s work.
Answer
step
Explanation
The recommended starting limit for the longest step is the number of people involved in working on that step.
- 30For an implementation step with five developers able to do the work, the initial WIP limit is five plus a buffer of about_____percent.
Hint
The speaker suggests adding half of the base number to allow for variation and delays.
Answer
50
Explanation
The example recommends setting the limit to the number of people who can do the work, plus a buffer of about 50 percent.
- 31After setting the WIP limit for the longest step, the limits for other steps are chosen to match its_____.
Hint
The goal is to avoid sending work into a stage faster than it can process it.
Answer
pace
Explanation
The speaker says the other steps’ WIP limits should match the pace of the longest step, preventing upstream overload.
- 32The minimum WIP limit described in the talk is_____.
Hint
Even a small workflow step needs capacity for at least one item.
Answer
one
Explanation
The speaker says the minimum WIP limit is one.
- 33If a team produces too many specifications before implementation can catch up, the WIP limit helps prevent work from_____.
Hint
Think of unfinished work accumulating ahead of a slower stage.
Answer
piling up
Explanation
WIP limits prevent a team from overloading a step with more work than the next step can process, reducing piles of potentially premature work.
- 34When a blocked step causes other people to have no work available within their limits, the board makes the problem_____.
Hint
The visible accumulation or stoppage makes the issue easy to notice.
Answer
evident
Explanation
The speaker says WIP limits make a stalled workflow visible, often on the same day or at the next stand-up.
- 35To measure how fast work moves through the system, count the stickies that reach done during a chosen_____period.
Hint
The measurement might cover two weeks or a month.
Answer
time
Explanation
The speaker recommends choosing a period, counting completed items during it, and using that count to calculate the completion rate.
- 36Dividing the number of completed stickies by the measurement period gives a completion rate in stickies per_____.
Hint
This is the unit used in the speaker’s example of work rate.
Answer
day
Explanation
The speaker describes dividing completed work by the chosen period to calculate stickies per day.
- 37For estimation, the speaker separates how fast the team works from how many_____a piece of work contains.
Hint
The second part estimates the number of similarly sized units required for an item.
Answer
tasks
Explanation
The speaker divides estimation into the team’s speed and the number of tasks in the work.
- 38The speaker recommends breaking work into tasks that take roughly one to_____days each.
Hint
The suggested task size spans a small range of a few days.
Answer
three
Explanation
The speaker says the preferred breakdown is into tasks that take one to three days, approximately.
- 39Instead of estimating abstract story points, the described approach estimates how many_____an item will break down into.
Hint
These are the similarly sized pieces created during breakdown.
Answer
tasks
Explanation
The speaker recommends estimating the number of tasks in an item, which he describes as more intuitive than abstract story points.
- 40Planning Poker and other estimation methods can still be used with Kanban because no special estimation technique is_____.
Hint
The method is compatible with teams’ preferred approaches rather than mandating one.
Answer
required
Explanation
The speaker says teams can use Planning Poker or any favorite estimation method; Kanban does not require a special one.
- 41To estimate a project’s duration, estimate the number of tasks in its items and compare that total with the team’s task_____rate.
Hint
This is the measured rate at which tasks pass through the workflow.
Answer
completion
Explanation
The speaker combines the estimated task count with the observed task completion rate to calculate how long work may take.
- 42A due-date estimate is checked by comparing the calculated completion time with the calendar date when the team is supposed to_____.
Hint
This is the committed outcome associated with the date.
Answer
deliver
Explanation
The speaker says to compare the estimated duration with the planned delivery date to see whether the work will finish in time.
- 43Because completion rates are based on actual tasks finished, they account for factors such as team size, weekends, bugs, and_____.
Hint
This everyday interruption is one of the factors mentioned as affecting actual work time.
Answer
e-mail
Explanation
The speaker notes that counting completed tasks over time reflects real conditions, including bugs and e-mail, rather than assuming uninterrupted effort.
- 44When task sizes vary somewhat, breaking work down into similarly sized tasks helps the variation average out over_____.
Hint
The benefit appears across repeated tasks rather than from a single task.
Answer
time
Explanation
The speaker argues that smaller size variation evens out over time, making the overall estimate more reliable.
- 45When a task proves larger than expected, the breakdown step should split it into smaller tasks instead of leaving a single oversized_____.
Hint
The goal is to return the work to pieces of roughly comparable size.
Answer
task
Explanation
The speaker says the breakdown step handles differing item sizes by dividing work into tasks of roughly one to three days.
- 46A team may reduce the need for repeated estimates when its flow becomes sufficiently predictable and stakeholders trust its_____.
Hint
This is the confidence earned by consistently delivering reliably.
Answer
reputation
Explanation
The speaker says his team’s reliable quality and speed created a reputation that meant others often focused on priority rather than requesting estimates.
- 47When new work arrives, the team can add it to the backlog through an_____sort rather than waiting for a sprint-planning meeting.
Hint
This sorting method places each new item into an existing ordered list.
Answer
insertion
Explanation
The speaker says the team fills the backlog as it goes using an insertion sort, without sprint-planning meetings.
- 48When a dependency is blocked, the team can add a separate_____column to make the issue visible and actively managed.
Hint
The column name in the talk signals that someone is following up on the blocked item.
Answer
Track
Explanation
The speaker describes adding a Track column for dependencies that are not ready or are not working as expected.
- 49An item placed in the Track column is assigned to someone responsible for driving it to the correct_____.
Hint
This is the condition the blocked dependency must reach before the team can proceed appropriately.
Answer
state
Explanation
The person assigned to a tracked dependency is responsible for driving it to the correct state.
- 50The correct response to a tracked dependency might be to work around it, change expectations, lower priority, or add the missing work to the_____.
Hint
This is where the team records work it intends to do.
Answer
backlog
Explanation
The speaker lists several possible ways to resolve a tracked dependency, including adding the unfinished task to the team’s backlog.
- 51Track items do not count toward the step’s_____limit, so they do not automatically stop other work from proceeding.
Hint
This limit restricts how many active work items occupy a workflow step.
Answer
WIP
Explanation
The speaker says track tasks do not add to the WIP limit, allowing other work to continue while the dependency is managed.
- 52At each daily stand-up, the team discusses items in the Track column so that blocked dependencies receive ongoing_____.
Hint
The team must revisit these unresolved items regularly rather than ignore them.
Answer
attention
Explanation
The speaker says tracked dependencies are discussed at every stand-up and worked on persistently until they are unblocked.
- 53Once an item in Track is unblocked, it moves into implementation because it is treated as the highest_____item.
Hint
The team gives the newly unblocked work precedence based on its position in the workflow.
Answer
priority
Explanation
The speaker says an unblocked tracked item moves into implementation because it is the top-priority item.
- 54A team can release individual work continuously, but when several items belong to one launch, it waits until all associated_____are complete.
Hint
These board items represent the work included in the planned release.
Answer
stickies
Explanation
The speaker says that for a larger coordinated launch, the team ships when all stickies associated with that launch are complete.
- 55If completed work must wait for other groups before a coordinated release, the team can place it in a special section for items waiting to go out the_____.
Hint
This expression refers to work that is complete but not yet released.
Answer
door
Explanation
The speaker describes a section for completed items that must wait until the wider organization is ready to release them.
- 56Kanban has no required formal_____; people may naturally take on responsibilities such as running stand-up or maintaining status records.
Hint
These are predefined team positions that Kanban does not mandate.
Answer
roles
Explanation
The speaker says Kanban specifies no particular roles, although people on teams often take on practical responsibilities.
- 57A person who runs the daily stand-up may help keep the conversation focused, but this responsibility is not a mandated Kanban_____.
Hint
The term refers to a formally required position in a process.
Answer
role
Explanation
The speaker describes someone facilitating stand-up as a practical team responsibility, not a required Kanban role.
- 58A team may transfer board updates into a work item tracking system so that people outside the team can see the same_____.
Hint
This is information about where work items are in the process.
Answer
status
Explanation
The speaker describes recording which stickies have moved so others can see the board’s status in the tracking system.
- 59Team members may naturally focus on particular workflow steps, but the speaker says any team member can perform the work in a_____.
Hint
This is one stage of the board’s workflow, such as validation or implementation.
Answer
step
Explanation
The speaker says members often focus on certain steps, while also noting that any member can do the work.
- 60A person acting as a product owner may be a program manager for partner-driven features or a team member for other features; the assignment_____.
Hint
The responsibility depends on the feature rather than being fixed to one person in all cases.
Answer
varies
Explanation
The speaker says the product-owner-like responsibility varies with the feature and is not a static role.
- 61When one task is too large and other team members are idle, Kanban’s visible limits can prompt the team to_____on the problem.
Hint
This means several people join efforts to address a blocked or unusually large item.
Answer
swarm
Explanation
The speaker says that when work is stuck, available people can swarm to the problem and help resolve it.
- 62For an open-ended task, the team breaks down what it can, starts working, and adds newly discovered work back to the_____.
Hint
Newly identified work is recorded in the place where future tasks are prioritized.
Answer
backlog
Explanation
The speaker says open-ended work can proceed incrementally, with emerging tasks added back to the backlog.
- 63For a task too complex to break down immediately, the team can make the initial work a design document task, including research and_____.
Hint
This activity establishes the system’s structure before detailed implementation work begins.
Answer
architecture
Explanation
The speaker describes researching, talking to people, developing an architecture, and writing a design document before breaking down a very large feature.
- 64When a task requires expertise held by one person, the speaker prefers assigning it to the next available person and having the expert_____with them.
Hint
The expert provides advice and review while the assignee learns the work.
Answer
buddy up
Explanation
The speaker prefers avoiding a single-person bottleneck by assigning available staff and having a qualified person buddy up with them.
- 65Having another person learn a specialized task reduces the risk of a single point of_____.
Hint
This risk arises when the team’s success depends on one individual being available.
Answer
failure
Explanation
The speaker wants to avoid a single point of failure by spreading knowledge and supporting less-experienced assignees.
- 66For long-term projects, people may keep pulling items from the same stack of related work, which naturally supports project_____.
Hint
This describes maintaining a consistent connection to the same project over time.
Answer
continuity
Explanation
The speaker says that the sequence of related stickies often means the same person continues working on a project, while the team remains flexible when flow is blocked.
- 67The speaker describes teams using Kanban that commonly range from four to_____people, while noting that larger teams are possible.
Hint
The upper end of the preferred team-size range is a two-digit number.
Answer
10
Explanation
The speaker says teams he has run are typically in the range of four to 10 people, although documented examples include much larger teams.
- 68A large Kanban stand-up focuses on blocking_____rather than asking every person to report what they did yesterday and will do tomorrow.
Hint
These are the work entries that cannot proceed normally.
Answer
items
Explanation
The speaker says stand-ups need not repeat information already visible on the board; they focus on issues such as blocked items.
- 69Kanban can work across several disciplines, and the speaker says he has seen teams with five or six different_____.
Hint
Examples include designers, testers, and developers.
Answer
disciplines
Explanation
The speaker describes cross-disciplinary teams and says he has seen Kanban teams involving five or six disciplines.
- 70At very large scale, organizational leaders first determine high-level scenarios and priorities, while individual teams contribute technical_____.
Hint
This term describes improvement or technical work proposed from within teams.
Answer
opportunity
Explanation
The speaker says teams contribute technical opportunity, including desired work and technical debt, which is combined with high-level plans.
- 71In large-scale planning, team plans can be placed on a board arranged by time and by different team_____.
Hint
Each group is shown separately in a horizontal position on the planning board.
Answer
rows
Explanation
The speaker describes a large board laid out in time sequence, with different teams on different rows.
- 72Large-scale plans are revisited every few months, while the detailed ordering of a team’s backlog is reviewed as new work arrives, often every_____.
Hint
This is the frequent interval used for the team’s ongoing prioritization.
Answer
day
Explanation
The speaker distinguishes periodic large-scale planning from daily updates to the backlog ordering as new items come in.
- 73A waterfall team can transition by putting its work on a board, retaining familiar stages, and processing a small_____at a time.
Hint
This is a limited group of work items, as opposed to a large volume processed all at once.
Answer
batch
Explanation
The speaker describes adapting waterfall by tracking work on a board and doing a small batch at a time rather than a large batch.
- 74A Scrum team adopting Kanban can initially keep practices such as sprint planning and retrospectives while adding WIP_____.
Hint
These are the numerical constraints on work occupying each step.
Answer
limits
Explanation
The speaker recommends that Scrum teams can keep their familiar practices at first while beginning to follow WIP limits.
- 75As teams become comfortable with Kanban, they may stop meetings and practices they find unnecessary because those activities use time without adding enough_____.
Hint
This is the useful contribution to the product or team that the speaker wants work time to produce.
Answer
value
Explanation
The speaker says Scrum teams gradually dropped practices they no longer needed, freeing time to focus on delivering value.
- 76Adapting from Scrum or waterfall is presented as a gradual change rather than a dramatic replacement, because teams can begin by adding a_____to track work.
Hint
This visual tool is the first simple change in the transition described.
Answer
board
Explanation
The speaker describes introducing a board and WIP limits while initially allowing teams to retain familiar practices.