1. Home
  2. Explore
  3. Business
  4. Agile Project Management with Kanban

Study methods

Flashcards
Quiz
Fill in the blanks
Written test
Lesson
Notes
Podcast
Content

Agile Project Management with Kanban

  • 76Unfamiliar
  • 0Learning
  • 0Familiar
  • 0Mastered
Topic: Kanban Fundamentals
Kanban supports a workflow in which completed work can be delivered continuously rather than waiting for fixed release cycles; it was built for
delivery.

76 questions

  1. 1
    Kanban supports a workflow in which completed work can be delivered continuously rather than waiting for fixed release cycles; it was built for
    _____
    delivery.
    Hint

    Think of delivery that can happen as work is completed, rather than only at the end of a sprint.

    Answer

    continuous

    Explanation

    The speaker describes Kanban as built for continuous delivery, allowing work to be shipped frequently.

  2. 2
    In the speaker’s description, Kanban avoids milestones, sprints, and
    _____
    as sources of overhead.
    Hint

    The missing term refers to extra effort that does not directly contribute to product work.

    Answer

    overhead

    Explanation

    The talk says that with Kanban there are no milestones, sprints, or overhead.

  3. 3
    The speaker says quality happens at
    _____
    step of the workflow, rather than being checked only at the end.
    Hint

    Think about whether quality is handled throughout the process or only in a final phase.

    Answer

    every

    Explanation

    The speaker emphasizes that quality happens at every step.

  4. 4
    The speaker values Kanban because it helps the team spend its working time on actual
    _____
    going into the product.
    Hint

    This is what customers ultimately receive from useful product work.

    Answer

    value

    Explanation

    The speaker contrasts work that contributes indirectly with actual value going into the product.

  5. 5
    The visual centerpiece of the approach described is the
    _____
    board.
    Hint

    It is the board used to make the flow of work visible.

    Answer

    Kanban

    Explanation

    The speaker describes the Kanban board as the center of the approach.

  6. 6
    Kanban is presented as a tool to help a team
    _____
    its project, not as a rigid set of rules enforced by authorities.
    Hint

    The verb describes what the board helps a team do with its work.

    Answer

    manage

    Explanation

    The speaker says Kanban is a tool to help manage a project and that there are no Kanban police enforcing a single way to use it.

  7. 7
    The speaker recommends using Kanban primarily to manage work that takes a few
    _____
    rather than every brief interruption.
    Hint

    The talk distinguishes project-type work from tasks that take only minutes or an hour.

    Answer

    days

    Explanation

    Kanban is described as helpful for managing work that takes a few days, while short pieces of work can be handled as they come in.

  8. 8
    A personal Kanban board can be reduced to backlog, doing, and
    _____
    .
    Hint

    The last column contains work that has been completed.

    Answer

    done

    Explanation

    The speaker describes personal Kanban as a simple board with three columns: backlog, doing, and done.

  9. 9
    Kanban’s simplicity does not prevent teams from changing their process; the speaker says there are no hard and fast
    _____
    .
    Hint

    These are strict requirements that would dictate exactly how every team must work.

    Answer

    rules

    Explanation

    The speaker stresses that Kanban is flexible and does not impose hard and fast rules.

  10. 10
    The speaker characterizes Kanban as a way to improve work through
    _____
    improvement.
    Hint

    The term describes improvement that happens repeatedly over time.

    Answer

    continuous

    Explanation

    The speaker jokingly refers to continuous improvement while describing Kanban as an approach that teams can keep adjusting.

  11. 11
    Unlike a process that requires a single completion day for all work, Kanban lets teams finish items
    _____
    as they move through the workflow.
    Hint

    Think about work completing throughout the process rather than all at once.

    Answer

    continuously

    Explanation

    The speaker contrasts Kanban with approaches that have one specific day when a batch is finished; Kanban work completes continuously.

  12. 12
    In the example board, the initial collection of work waiting to be done is called the
    _____
    .
    Hint

    This is the ordered list of work items awaiting action.

    Answer

    backlog

    Explanation

    The speaker defines the backlog as the list of things the team has to do, typically prioritized in some way.

  13. 13
    A backlog may be compared with a feature list in a traditional
    _____
    approach.
    Hint

    This is the traditional development approach contrasted with Scrum and Kanban in the talk.

    Answer

    waterfall

    Explanation

    The speaker says that in a traditional waterfall approach, the backlog would be a feature list.

  14. 14
    Because backlog items can vary greatly in size, the team uses a
    _____
    step to split large items into manageable pieces.
    Hint

    This step turns a complicated item into smaller work items.

    Answer

    breakdown

    Explanation

    The speaker explains that items of different sizes should be broken down into more equally sized pieces.

  15. 15
    Some teams call the breakdown step
    _____
    because it includes a small amount of specification.
    Hint

    The alternate name refers to defining just enough detail before work is carried out.

    Answer

    specify

    Explanation

    The speaker says some people call breakdown specify because a little specification is done while dividing work into pieces.

  16. 16
    After work has been broken down, the next example step is to
    _____
    the question or implement the work.
    Hint

    In the talk’s question-answering demonstration, this is the step after breakdown.

    Answer

    answer

    Explanation

    The example workflow moves from breakdown to answering; in product development, this corresponds to implementation.

  17. 17
    The final example step checks that the answer or completed work meets the intended need; it is called
    _____
    .
    Hint

    This step confirms that the result is correct from the customer’s or questioner’s perspective.

    Answer

    validate

    Explanation

    The speaker adds a validate step to ensure the answer addresses the question that was actually asked.

  18. 18
    Kanban stages can be named according to the team’s needs, and teams can have as
    _____
    steps as they want.
    Hint

    The number of stages is flexible, not fixed by the example board.

    Answer

    many

    Explanation

    The speaker says teams can name steps anything they want and have as many steps as they want.

  19. 19
    Each workflow step is divided into an active column and a
    _____
    column.
    Hint

    The second column records that work in the step has been completed.

    Answer

    done

    Explanation

    The speaker says every step has an active and a done column, distinguishing work in progress from completed work at that stage.

  20. 20
    The active and done columns help a team specify what it means for work to be
    _____
    .
    Hint

    The team needs a clear criterion for moving an item out of active work.

    Answer

    done

    Explanation

    The speaker explains that the columns support explicit definitions of when something is finished.

  21. 21
    The criteria specifying when work in a step is finished are called
    _____
    rules.
    Hint

    The term names the rules that define completion for each stage.

    Answer

    done

    Explanation

    The speaker calls the criteria for completing a step done rules.

  22. 22
    In the example, a question is considered broken down only when each resulting question can be answered in less than
    _____
    minutes.
    Hint

    The example uses a short maximum duration to keep the pieces small.

    Answer

    two

    Explanation

    The speaker’s done rule for breakdown is that each question should take less than two minutes to answer.

  23. 23
    In the example answering step, the speaker’s done rule requires the question to be repeated and then
    _____
    .
    Hint

    Both restating the prompt and providing a response are required.

    Answer

    answered

    Explanation

    Because the talk is being recorded, the speaker says he should repeat the question and answer it before marking the step done.

  24. 24
    For the example validate step, work is done when the
    _____
    is satisfied.
    Hint

    This is the person who asked the question and judges whether the response was useful.

    Answer

    questioner

    Explanation

    The speaker’s validation criterion is that the questioner is satisfied with the answer.

  25. 25
    In software development, an implementation done rule might require code review and unit
    _____
    .
    Hint

    This practice checks small units of code as part of verifying implementation quality.

    Answer

    testing

    Explanation

    The speaker gives code review and unit testing as examples of checks that can be included in implementation done rules.

  26. 26
    A work in progress limit, abbreviated WIP limit, restricts how many
    _____
    may be in a workflow step.
    Hint

    These are the board markers representing work items.

    Answer

    stickies

    Explanation

    The speaker defines WIP limits as numbers that limit the stickies allowed in each step.

  27. 27
    WIP limits apply to the total items in a step, including items being worked on and items already marked
    _____
    .
    Hint

    The limit counts both active work and completed work within that step.

    Answer

    done

    Explanation

    The speaker clarifies that the limit includes stickies on either side of a step’s active/done division.

  28. 28
    Along with done rules, WIP limits help turn a board from a visualization tool into a project
    _____
    technique.
    Hint

    This is the broader activity of controlling and guiding project work.

    Answer

    management

    Explanation

    The speaker says that done rules and WIP limits are what make the approach project management rather than merely work visualization.

  29. 29
    To set an initial WIP limit for the longest step, the speaker starts with the number of people who can work on that
    _____
    .
    Hint

    The initial limit is based on the people available to perform the stage’s work.

    Answer

    step

    Explanation

    The recommended starting limit for the longest step is the number of people involved in working on that step.

  30. 30
    For an implementation step with five developers able to do the work, the initial WIP limit is five plus a buffer of about
    _____
    percent.
    Hint

    The speaker suggests adding half of the base number to allow for variation and delays.

    Answer

    50

    Explanation

    The example recommends setting the limit to the number of people who can do the work, plus a buffer of about 50 percent.

  31. 31
    After setting the WIP limit for the longest step, the limits for other steps are chosen to match its
    _____
    .
    Hint

    The goal is to avoid sending work into a stage faster than it can process it.

    Answer

    pace

    Explanation

    The speaker says the other steps’ WIP limits should match the pace of the longest step, preventing upstream overload.

  32. 32
    The minimum WIP limit described in the talk is
    _____
    .
    Hint

    Even a small workflow step needs capacity for at least one item.

    Answer

    one

    Explanation

    The speaker says the minimum WIP limit is one.

  33. 33
    If a team produces too many specifications before implementation can catch up, the WIP limit helps prevent work from
    _____
    .
    Hint

    Think of unfinished work accumulating ahead of a slower stage.

    Answer

    piling up

    Explanation

    WIP limits prevent a team from overloading a step with more work than the next step can process, reducing piles of potentially premature work.

  34. 34
    When a blocked step causes other people to have no work available within their limits, the board makes the problem
    _____
    .
    Hint

    The visible accumulation or stoppage makes the issue easy to notice.

    Answer

    evident

    Explanation

    The speaker says WIP limits make a stalled workflow visible, often on the same day or at the next stand-up.

  35. 35
    To measure how fast work moves through the system, count the stickies that reach done during a chosen
    _____
    period.
    Hint

    The measurement might cover two weeks or a month.

    Answer

    time

    Explanation

    The speaker recommends choosing a period, counting completed items during it, and using that count to calculate the completion rate.

  36. 36
    Dividing the number of completed stickies by the measurement period gives a completion rate in stickies per
    _____
    .
    Hint

    This is the unit used in the speaker’s example of work rate.

    Answer

    day

    Explanation

    The speaker describes dividing completed work by the chosen period to calculate stickies per day.

  37. 37
    For estimation, the speaker separates how fast the team works from how many
    _____
    a piece of work contains.
    Hint

    The second part estimates the number of similarly sized units required for an item.

    Answer

    tasks

    Explanation

    The speaker divides estimation into the team’s speed and the number of tasks in the work.

  38. 38
    The speaker recommends breaking work into tasks that take roughly one to
    _____
    days each.
    Hint

    The suggested task size spans a small range of a few days.

    Answer

    three

    Explanation

    The speaker says the preferred breakdown is into tasks that take one to three days, approximately.

  39. 39
    Instead of estimating abstract story points, the described approach estimates how many
    _____
    an item will break down into.
    Hint

    These are the similarly sized pieces created during breakdown.

    Answer

    tasks

    Explanation

    The speaker recommends estimating the number of tasks in an item, which he describes as more intuitive than abstract story points.

  40. 40
    Planning Poker and other estimation methods can still be used with Kanban because no special estimation technique is
    _____
    .
    Hint

    The method is compatible with teams’ preferred approaches rather than mandating one.

    Answer

    required

    Explanation

    The speaker says teams can use Planning Poker or any favorite estimation method; Kanban does not require a special one.

  41. 41
    To estimate a project’s duration, estimate the number of tasks in its items and compare that total with the team’s task
    _____
    rate.
    Hint

    This is the measured rate at which tasks pass through the workflow.

    Answer

    completion

    Explanation

    The speaker combines the estimated task count with the observed task completion rate to calculate how long work may take.

  42. 42
    A due-date estimate is checked by comparing the calculated completion time with the calendar date when the team is supposed to
    _____
    .
    Hint

    This is the committed outcome associated with the date.

    Answer

    deliver

    Explanation

    The speaker says to compare the estimated duration with the planned delivery date to see whether the work will finish in time.

  43. 43
    Because completion rates are based on actual tasks finished, they account for factors such as team size, weekends, bugs, and
    _____
    .
    Hint

    This everyday interruption is one of the factors mentioned as affecting actual work time.

    Answer

    e-mail

    Explanation

    The speaker notes that counting completed tasks over time reflects real conditions, including bugs and e-mail, rather than assuming uninterrupted effort.

  44. 44
    When task sizes vary somewhat, breaking work down into similarly sized tasks helps the variation average out over
    _____
    .
    Hint

    The benefit appears across repeated tasks rather than from a single task.

    Answer

    time

    Explanation

    The speaker argues that smaller size variation evens out over time, making the overall estimate more reliable.

  45. 45
    When a task proves larger than expected, the breakdown step should split it into smaller tasks instead of leaving a single oversized
    _____
    .
    Hint

    The goal is to return the work to pieces of roughly comparable size.

    Answer

    task

    Explanation

    The speaker says the breakdown step handles differing item sizes by dividing work into tasks of roughly one to three days.

  46. 46
    A team may reduce the need for repeated estimates when its flow becomes sufficiently predictable and stakeholders trust its
    _____
    .
    Hint

    This is the confidence earned by consistently delivering reliably.

    Answer

    reputation

    Explanation

    The speaker says his team’s reliable quality and speed created a reputation that meant others often focused on priority rather than requesting estimates.

  47. 47
    When new work arrives, the team can add it to the backlog through an
    _____
    sort rather than waiting for a sprint-planning meeting.
    Hint

    This sorting method places each new item into an existing ordered list.

    Answer

    insertion

    Explanation

    The speaker says the team fills the backlog as it goes using an insertion sort, without sprint-planning meetings.

  48. 48
    When a dependency is blocked, the team can add a separate
    _____
    column to make the issue visible and actively managed.
    Hint

    The column name in the talk signals that someone is following up on the blocked item.

    Answer

    Track

    Explanation

    The speaker describes adding a Track column for dependencies that are not ready or are not working as expected.

  49. 49
    An item placed in the Track column is assigned to someone responsible for driving it to the correct
    _____
    .
    Hint

    This is the condition the blocked dependency must reach before the team can proceed appropriately.

    Answer

    state

    Explanation

    The person assigned to a tracked dependency is responsible for driving it to the correct state.

  50. 50
    The correct response to a tracked dependency might be to work around it, change expectations, lower priority, or add the missing work to the
    _____
    .
    Hint

    This is where the team records work it intends to do.

    Answer

    backlog

    Explanation

    The speaker lists several possible ways to resolve a tracked dependency, including adding the unfinished task to the team’s backlog.

  51. 51
    Track items do not count toward the step’s
    _____
    limit, so they do not automatically stop other work from proceeding.
    Hint

    This limit restricts how many active work items occupy a workflow step.

    Answer

    WIP

    Explanation

    The speaker says track tasks do not add to the WIP limit, allowing other work to continue while the dependency is managed.

  52. 52
    At each daily stand-up, the team discusses items in the Track column so that blocked dependencies receive ongoing
    _____
    .
    Hint

    The team must revisit these unresolved items regularly rather than ignore them.

    Answer

    attention

    Explanation

    The speaker says tracked dependencies are discussed at every stand-up and worked on persistently until they are unblocked.

  53. 53
    Once an item in Track is unblocked, it moves into implementation because it is treated as the highest
    _____
    item.
    Hint

    The team gives the newly unblocked work precedence based on its position in the workflow.

    Answer

    priority

    Explanation

    The speaker says an unblocked tracked item moves into implementation because it is the top-priority item.

  54. 54
    A team can release individual work continuously, but when several items belong to one launch, it waits until all associated
    _____
    are complete.
    Hint

    These board items represent the work included in the planned release.

    Answer

    stickies

    Explanation

    The speaker says that for a larger coordinated launch, the team ships when all stickies associated with that launch are complete.

  55. 55
    If completed work must wait for other groups before a coordinated release, the team can place it in a special section for items waiting to go out the
    _____
    .
    Hint

    This expression refers to work that is complete but not yet released.

    Answer

    door

    Explanation

    The speaker describes a section for completed items that must wait until the wider organization is ready to release them.

  56. 56
    Kanban has no required formal
    _____
    ; people may naturally take on responsibilities such as running stand-up or maintaining status records.
    Hint

    These are predefined team positions that Kanban does not mandate.

    Answer

    roles

    Explanation

    The speaker says Kanban specifies no particular roles, although people on teams often take on practical responsibilities.

  57. 57
    A person who runs the daily stand-up may help keep the conversation focused, but this responsibility is not a mandated Kanban
    _____
    .
    Hint

    The term refers to a formally required position in a process.

    Answer

    role

    Explanation

    The speaker describes someone facilitating stand-up as a practical team responsibility, not a required Kanban role.

  58. 58
    A team may transfer board updates into a work item tracking system so that people outside the team can see the same
    _____
    .
    Hint

    This is information about where work items are in the process.

    Answer

    status

    Explanation

    The speaker describes recording which stickies have moved so others can see the board’s status in the tracking system.

  59. 59
    Team members may naturally focus on particular workflow steps, but the speaker says any team member can perform the work in a
    _____
    .
    Hint

    This is one stage of the board’s workflow, such as validation or implementation.

    Answer

    step

    Explanation

    The speaker says members often focus on certain steps, while also noting that any member can do the work.

  60. 60
    A person acting as a product owner may be a program manager for partner-driven features or a team member for other features; the assignment
    _____
    .
    Hint

    The responsibility depends on the feature rather than being fixed to one person in all cases.

    Answer

    varies

    Explanation

    The speaker says the product-owner-like responsibility varies with the feature and is not a static role.

  61. 61
    When one task is too large and other team members are idle, Kanban’s visible limits can prompt the team to
    _____
    on the problem.
    Hint

    This means several people join efforts to address a blocked or unusually large item.

    Answer

    swarm

    Explanation

    The speaker says that when work is stuck, available people can swarm to the problem and help resolve it.

  62. 62
    For an open-ended task, the team breaks down what it can, starts working, and adds newly discovered work back to the
    _____
    .
    Hint

    Newly identified work is recorded in the place where future tasks are prioritized.

    Answer

    backlog

    Explanation

    The speaker says open-ended work can proceed incrementally, with emerging tasks added back to the backlog.

  63. 63
    For a task too complex to break down immediately, the team can make the initial work a design document task, including research and
    _____
    .
    Hint

    This activity establishes the system’s structure before detailed implementation work begins.

    Answer

    architecture

    Explanation

    The speaker describes researching, talking to people, developing an architecture, and writing a design document before breaking down a very large feature.

  64. 64
    When a task requires expertise held by one person, the speaker prefers assigning it to the next available person and having the expert
    _____
    with them.
    Hint

    The expert provides advice and review while the assignee learns the work.

    Answer

    buddy up

    Explanation

    The speaker prefers avoiding a single-person bottleneck by assigning available staff and having a qualified person buddy up with them.

  65. 65
    Having another person learn a specialized task reduces the risk of a single point of
    _____
    .
    Hint

    This risk arises when the team’s success depends on one individual being available.

    Answer

    failure

    Explanation

    The speaker wants to avoid a single point of failure by spreading knowledge and supporting less-experienced assignees.

  66. 66
    For long-term projects, people may keep pulling items from the same stack of related work, which naturally supports project
    _____
    .
    Hint

    This describes maintaining a consistent connection to the same project over time.

    Answer

    continuity

    Explanation

    The speaker says that the sequence of related stickies often means the same person continues working on a project, while the team remains flexible when flow is blocked.

  67. 67
    The speaker describes teams using Kanban that commonly range from four to
    _____
    people, while noting that larger teams are possible.
    Hint

    The upper end of the preferred team-size range is a two-digit number.

    Answer

    10

    Explanation

    The speaker says teams he has run are typically in the range of four to 10 people, although documented examples include much larger teams.

  68. 68
    A large Kanban stand-up focuses on blocking
    _____
    rather than asking every person to report what they did yesterday and will do tomorrow.
    Hint

    These are the work entries that cannot proceed normally.

    Answer

    items

    Explanation

    The speaker says stand-ups need not repeat information already visible on the board; they focus on issues such as blocked items.

  69. 69
    Kanban can work across several disciplines, and the speaker says he has seen teams with five or six different
    _____
    .
    Hint

    Examples include designers, testers, and developers.

    Answer

    disciplines

    Explanation

    The speaker describes cross-disciplinary teams and says he has seen Kanban teams involving five or six disciplines.

  70. 70
    At very large scale, organizational leaders first determine high-level scenarios and priorities, while individual teams contribute technical
    _____
    .
    Hint

    This term describes improvement or technical work proposed from within teams.

    Answer

    opportunity

    Explanation

    The speaker says teams contribute technical opportunity, including desired work and technical debt, which is combined with high-level plans.

  71. 71
    In large-scale planning, team plans can be placed on a board arranged by time and by different team
    _____
    .
    Hint

    Each group is shown separately in a horizontal position on the planning board.

    Answer

    rows

    Explanation

    The speaker describes a large board laid out in time sequence, with different teams on different rows.

  72. 72
    Large-scale plans are revisited every few months, while the detailed ordering of a team’s backlog is reviewed as new work arrives, often every
    _____
    .
    Hint

    This is the frequent interval used for the team’s ongoing prioritization.

    Answer

    day

    Explanation

    The speaker distinguishes periodic large-scale planning from daily updates to the backlog ordering as new items come in.

  73. 73
    A waterfall team can transition by putting its work on a board, retaining familiar stages, and processing a small
    _____
    at a time.
    Hint

    This is a limited group of work items, as opposed to a large volume processed all at once.

    Answer

    batch

    Explanation

    The speaker describes adapting waterfall by tracking work on a board and doing a small batch at a time rather than a large batch.

  74. 74
    A Scrum team adopting Kanban can initially keep practices such as sprint planning and retrospectives while adding WIP
    _____
    .
    Hint

    These are the numerical constraints on work occupying each step.

    Answer

    limits

    Explanation

    The speaker recommends that Scrum teams can keep their familiar practices at first while beginning to follow WIP limits.

  75. 75
    As teams become comfortable with Kanban, they may stop meetings and practices they find unnecessary because those activities use time without adding enough
    _____
    .
    Hint

    This is the useful contribution to the product or team that the speaker wants work time to produce.

    Answer

    value

    Explanation

    The speaker says Scrum teams gradually dropped practices they no longer needed, freeing time to focus on delivering value.

  76. 76
    Adapting from Scrum or waterfall is presented as a gradual change rather than a dramatic replacement, because teams can begin by adding a
    _____
    to track work.
    Hint

    This visual tool is the first simple change in the transition described.

    Answer

    board

    Explanation

    The speaker describes introducing a board and WIP limits while initially allowing teams to retain familiar practices.

1 of 76
Question 1 of 76

Ask anything

We've read this whole study set, so questions about it get the best answers.

FlashcardsQuizFill in the blanksWritten testLessonNotesPodcastContent