Agile Project Management with Kanban
- 64Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
What are the main elements of the Kanban board described in the talk?
64 questions
- 1
What are the main elements of the Kanban board described in the talk?
Model answer
A prioritized backlog followed by workflow steps, with work items moving through the steps until they are done.
Explanation
The board is presented as the central tool for tracking work; the example workflow has breakdown, answering, and validation steps.
- 2
What does the backlog contain, and how is it usually organized?
Model answer
It contains work that needs to be done, usually ordered by priority.
Explanation
The backlog may be understood as a feature list, but in Kanban it is ordered work waiting to be taken on.
- 3
Why might a large backlog item be broken into smaller work items?
Model answer
Work items vary in size, so breaking a large item into smaller, more similarly sized pieces makes the work easier to manage and move through the workflow.
Explanation
The talk describes breaking down large features into smaller tasks, often ones that take a few days each.
- 4
What does it mean for each workflow step to have an active column and a done column?
Model answer
The active column shows items currently being worked on at that step, while the done column shows items that have finished that step.
Explanation
For example, the board distinguishes work being broken down from work whose breakdown is complete.
- 5
What are done rules, and why are they used?
Model answer
Done rules specify the conditions an item must meet before it can leave a workflow step. They help ensure that work is completed rather than merely moved along.
Explanation
The rules provide a check that the required work, such as reviews or tests in software development, has actually been performed.
- 6
In the talk’s example workflow, what condition makes a question ready to leave the breakdown step?
Model answer
It must be broken into questions that can each be answered in less than two minutes.
Explanation
The speaker uses this as a done rule for breaking down questions so the resulting items are roughly manageable in size.
- 7
In the example workflow, what must happen before an item is considered answered?
Model answer
The question must be repeated and then answered.
Explanation
Because the talk is being recorded and streamed, repeating the question is part of the example’s done rule for answering.
- 8
What is the done rule for validating an answer in the example workflow?
Model answer
The person who asked the question must be satisfied with the answer.
Explanation
Validation checks that the response addresses the question actually asked, rather than only the question the speaker thought was asked.
- 9
How does validation in product development relate to customer feedback?
Model answer
A completed implementation is not fully understood until customer feedback confirms how well it meets the customer’s needs.
Explanation
The speaker compares validating an answer with obtaining feedback on coded product work.
- 10
Are the workflow steps and their names fixed in Kanban?
Model answer
No. Teams can name steps as they choose and can use as many steps as their work requires.
Explanation
Breakdown, implementation, and validation are examples rather than mandatory steps; the board can be adapted.
- 11
What is a work-in-progress limit, and what does it control?
Model answer
A work-in-progress limit is a number assigned to a workflow step that caps how many items may be in that step.
Explanation
The limit applies to the total items in the step, including items being worked on and items already done at that step but not yet moved onward.
- 12
How does the example’s work-in-progress limit apply to both active and done items in a step?
Model answer
Both active and done items count toward the step’s total limit; for example, a limit of two allows only two items in that step altogether.
Explanation
The limit is not just a cap on items currently being worked on.
- 13
How does the speaker suggest setting an initial limit for the longest workflow step?
Model answer
Start with the number of people who can perform that step, then add a buffer; the example suggests a buffer of about 50%.
Explanation
For five people able to implement, the suggested initial limit would be roughly five plus a buffer, or about eight when rounded up.
- 14
How should limits for the other workflow steps be set in relation to the longest step?
Model answer
Set them to support a pace that matches the longest step, so work does not accumulate faster than it can be completed downstream.
Explanation
The speaker recommends matching the pace of breakdown and validation to implementation rather than overloading a step with excess work.
- 15
What is the minimum work-in-progress limit suggested in the talk?
Model answer
The minimum limit is one.
Explanation
The example uses a limit of one for steps that are quicker than the main work step.
- 16
How do work-in-progress limits help reveal problems in the workflow?
Model answer
They prevent people from continually adding more work when a step is blocked, making stalled work and unused capacity visible.
Explanation
When items stop moving and a step reaches its limit, the team can see that something needs attention instead of building up more unfinished work.
- 17
What can a team do when work is stalled and other members cannot take on more work because of the limits?
Model answer
The team can investigate the blockage and swarm to solve it, for example by helping with the task or coordinating with another team.
Explanation
The limits make the problem visible and encourage available team members to focus on resolving it rather than starting excess work.
- 18
How can a Kanban board help manage work without requiring every piece of work to be tracked on it?
Model answer
It can be used for substantial project work, while very quick tasks may be handled directly without being added to the board.
Explanation
The speaker says that short tasks taking minutes or about an hour do not necessarily need to go through the board.
- 19
How does the team typically prioritize its backlog?
Model answer
The team orders the work together according to its shared understanding of priorities and the needs of customers and stakeholders.
Explanation
Prioritization is described as a team conversation rather than an elaborate separate process.
- 20
How are new work items added to an existing backlog in the approach described?
Model answer
They are inserted into the backlog according to their priority relative to the existing work.
Explanation
The speaker describes adding new requests through an insertion sort rather than waiting for sprint planning.
- 21
When might a team need to reorder its backlog beyond inserting new work?
Model answer
It may need to reorder the backlog when circumstances or priorities change significantly.
Explanation
The team can discuss customer needs and expectations from executives or partners and then revise the ordering.
- 22
What meeting cadence does the speaker’s team use, and does Kanban prescribe it?
Model answer
The team uses a daily stand-up, but Kanban does not prescribe a fixed set of meetings.
Explanation
The speaker presents the stand-up as the team’s practice and emphasizes that Kanban is a flexible management tool, not a set of mandatory ceremonies.
- 23
What is the main focus of a daily stand-up on a large Kanban team?
Model answer
The team focuses on blockers and other issues affecting flow, rather than giving routine reports of what everyone did yesterday or will do tomorrow.
Explanation
Work status is already visible on the board, so the meeting can concentrate on items that need discussion.
- 24
How long might a daily stand-up take, according to the examples in the talk?
Model answer
Some teams finish in under five minutes; the speaker’s teams often take about half an hour, while a documented team of 70 people met in under 15 minutes.
Explanation
Meeting length varies with team practice, and the speaker notes that blocker-focused stand-ups can remain short even for large groups.
- 25
What is personal Kanban in the example given?
Model answer
It is an individual Kanban board with three columns: backlog, doing, and done.
Explanation
The speaker describes this as a simple way for an individual to manage personal work.
- 26
How does Kanban estimate a team’s completion rate from its board?
Model answer
Choose a measurement period, count how many work items reach done during that period, and use that count to determine the team’s rate of completion.
Explanation
The team can measure items completed over a period such as two weeks or a month to learn its actual pace.
- 27
Why should work items be broken into roughly similar sizes before using completion rate to estimate delivery?
Model answer
A completion count is more useful when the items being counted are comparable in size.
Explanation
The speaker recommends breaking software tasks down to roughly one to three days so differences in size are limited.
- 28
What does the speaker recommend estimating for a feature instead of estimating task hours or story points?
Model answer
Estimate how many similarly sized tasks the feature will break down into.
Explanation
The speaker describes this as an intuitive estimate of the number of tasks, each taking a few days, rather than an abstract point or hour total.
- 29
Can teams use their preferred estimation technique when estimating the number of tasks?
Model answer
Yes. Planning Poker or another preferred technique can be used; Kanban does not require a particular estimation method.
Explanation
The task-count approach is offered as one method that fits Kanban, not as a mandatory technique.
- 30
How can a team estimate how long a set of planned work will take?
Model answer
Estimate the number of tasks in the work, then compare that total with the team’s measured task completion rate.
Explanation
Combining the estimated task count with actual throughput provides an estimate of elapsed working time.
- 31
How can a team assess whether work is likely to meet a due date?
Model answer
Estimate the tasks required for the work, use the team’s completion rate to estimate duration, and compare that duration with the time remaining before the due date.
Explanation
If the estimate extends beyond the delivery date, the team can discuss simplifying the work, changing the plan, or making other adjustments.
- 32
Why can a completion rate based on actual work account for factors such as team size, weekends, bugs, and interruptions?
Model answer
Those effects are reflected in the number of tasks the team actually completes during the measured period.
Explanation
The method uses observed throughput rather than assuming a fixed rate based only on nominal work time.
- 33
How does breaking work into similarly sized tasks help with variation in task duration?
Model answer
It limits the size differences between tasks, and small variations tend to even out when many tasks are completed over time.
Explanation
The speaker acknowledges that individual tasks may take longer than expected but argues that the variation averages out across a stream of tasks.
- 34
Why might a highly predictable team eventually need fewer estimates?
Model answer
If the team reliably delivers quality work and stakeholders trust its flow, they may focus more on the work’s priority than on requesting a specific completion estimate.
Explanation
The speaker says some teams stopped being asked for frequent estimates after establishing a strong record of timely delivery.
- 35
How does the talk distinguish between handling a small bug and a substantial bug?
Model answer
A trivial bug can be fixed directly without adding it to the board; a substantial bug should be recorded as a work item, prioritized, and moved through the usual steps.
Explanation
The distinction is based on whether the fix is quick or requires significant design and implementation work.
- 36
What is the purpose of a track column for blocked dependencies?
Model answer
It makes a blocked dependency visible and gives someone responsibility for driving it toward resolution.
Explanation
A team can add a track column between workflow steps and assign an owner to each item placed there.
- 37
What actions might a team take to resolve or respond to a blocked dependency?
Model answer
It might find a workaround, take the missing work into its own backlog, change the feature or expectations, or lower the item’s priority.
Explanation
The appropriate response depends on the situation, but the team discusses and acts on the tracked blockage.
- 38
Do items in the track column count toward the ordinary work-in-progress limits?
Model answer
No. Track items do not add to the ordinary work-in-progress limit, so they do not by themselves prevent other work from continuing.
Explanation
If the team takes on the dependency work itself, that work then flows through the normal steps and limits.
- 39
What happens to a tracked dependency when it becomes unblocked?
Model answer
It moves into the implementation step as the highest-priority item to be worked on.
Explanation
The speaker says that the team pulls an unblocked tracked item into implementation before taking a lower-priority item from the backlog.
- 40
When is work considered ready to leave the end of the Kanban workflow?
Model answer
It is ready when it reaches the end after meeting the quality conditions for the preceding steps.
Explanation
The speaker describes items as ready for their intended destination once they pass through the workflow’s quality checks.
- 41
How can a team release work continuously while still coordinating a larger, coherent release?
Model answer
It can release some work as soon as it is ready, but for a coordinated release it waits until all associated work items are complete.
Explanation
The appropriate timing depends on whether the work is independent or part of a larger collection with a shared delivery date.
- 42
How can a Kanban board represent work that is complete but waiting for a coordinated release?
Model answer
The team can add a section for completed items that are waiting to ship, then move them to final done when the release occurs.
Explanation
This distinguishes completion of the team’s work from the later release of a larger coordinated set.
- 43
Does Kanban require teams to have specific formal roles?
Model answer
No. Kanban does not prescribe specific roles, although teams may assign responsibilities or develop informal roles that suit their work.
Explanation
The speaker gives examples of useful responsibilities but emphasizes that they are not mandatory Kanban roles.
- 44
What might the person facilitating a daily stand-up do?
Model answer
They help keep the discussion focused and prevent it from drifting too far off topic.
Explanation
The speaker describes this as a practical team responsibility, not a formal role required by Kanban.
- 45
How can a team keep an external work-item tracking system aligned with its physical Kanban board?
Model answer
A team member can spend a few minutes each day transferring updates about moved items into the tracking system.
Explanation
The speaker’s team uses a separate system for broader status sharing while continuing to manage work on its board.
- 46
How might responsibilities naturally align with workflow steps on a multidisciplinary team?
Model answer
Developers may focus mainly on implementation, program managers on breakdown, and testers on validation, although responsibilities can vary and overlap.
Explanation
The speaker presents these as common patterns rather than required assignments.
- 47
Who acts as a product owner in Kanban, according to the talk?
Model answer
It varies by feature: a program manager may represent partners, while a team member may take that role for an internally proposed feature or technical-debt work.
Explanation
The speaker says Kanban does not require a single fixed product-owner role.
- 48
How can a team represent a large item that has been broken into multiple smaller work items?
Model answer
It can keep the original item beneath the smaller items as a parent or bundle while the smaller items move through the workflow.
Explanation
The original item is counted as one bundle for the breakdown limit, and its component items are moved through the board individually.
- 49
What does swarming mean in the Kanban example?
Model answer
Swarming means having available team members join forces to address a blocked or unexpectedly difficult item.
Explanation
When limits reveal that work is stuck, the team can focus its available capacity on resolving the problem.
- 50
How should a team handle an open-ended task when it cannot identify all the work in advance?
Model answer
Break down what is currently understood, begin working, and add newly discovered tasks to the backlog as they emerge.
Explanation
The speaker says the approach can be used for research and other work where further tasks become clear over time.
- 51
How can a team handle an item that is too large or complex to break down directly?
Model answer
It can treat the design or analysis needed to understand the item as work in its own right, break that work down, complete and review it, and then break down the larger implementation.
Explanation
The example uses research, discussions, architecture, and a design document to prepare for later implementation planning.
- 52
How are ordinary work items assigned when a step has an available slot?
Model answer
The next item in priority order is pulled into the step and assigned to an available person, often with that person’s initials recorded on it.
Explanation
The approach prioritizes available capacity and the ordered backlog rather than assigning every item far in advance.
- 53
Why might a team assign a task to an available person who is not yet an expert in that area?
Model answer
Doing so reduces dependence on a single specialist; a more experienced teammate can provide guidance and reviews while the person learns.
Explanation
The speaker prefers avoiding single points of failure that could arise if one person is unavailable.
- 54
How can a Kanban team preserve continuity on a long-term project while still assigning work flexibly?
Model answer
The same person may keep pulling tasks from the project’s related stack, but the team can reassign work when needed to prevent a bottleneck.
Explanation
Continuity often develops naturally, but the team should not hold up customers or partners merely to keep work with one person.
- 55
What team size has been documented for Kanban, and what range does the speaker prefer for teams he has led?
Model answer
The talk cites a documented team of 70 people; the speaker’s own teams have typically had four to ten people.
Explanation
The speaker describes the larger example as workable with a large board and a focused stand-up, while preferring smaller teams for camaraderie and coverage.
- 56
Why does the speaker prefer multidisciplinary teams for Kanban?
Model answer
People with different disciplines can contribute across the workflow, making the arrangement work more smoothly than a team composed only of one discipline.
Explanation
The speaker says Kanban can be used within a single discipline, but that it works better in his experience when disciplines are combined.
- 57
How many different disciplines has the speaker seen using Kanban together, and how many are typical on his teams?
Model answer
He has seen five or six disciplines using it, while his own teams typically have about three.
Explanation
The talk mentions designers and testers among the disciplines that may participate.
- 58
How flexible is a Kanban board as a team’s work changes?
Model answer
Teams can change the board and its steps as needed; the board is not fixed permanently.
Explanation
The speaker emphasizes that teams can adapt the number and arrangement of steps to their workflow.
- 59
How are priorities established for work at the scale of a large organization?
Model answer
Senior groups identify major scenarios and strategic themes using market and organizational input, while teams contribute proposed work and technical opportunities; the work is then combined and refined for groups.
Explanation
The talk describes both top-down planning and bottom-up contributions from individual teams.
- 60
How can large organizations coordinate work across teams that depend on one another?
Model answer
Teams can place planned work on a shared timeline, discuss conflicts and dependencies, and adjust the ordering until the plan seems workable.
Explanation
The speaker describes a board with time on one dimension and teams on another as a way to coordinate approximate delivery periods.
- 61
How often does the large-scale organization revisit its broad plan and its team backlogs?
Model answer
The broad planning process may happen annually, with adjustments every few months; teams still revisit their specific backlog ordering daily as new work arrives.
Explanation
The speaker distinguishes large organizational planning from the more frequent ordering of individual team work.
- 62
How does the speaker recommend transitioning a waterfall team to Kanban?
Model answer
Put the work on a board, add work-in-progress limits, and continue the familiar specification, implementation, and testing activities while working in smaller batches.
Explanation
The transition changes how work is visualized and batched without requiring the team to replace every practice at once.
- 63
How can a Scrum team begin adapting to Kanban without immediately abandoning Scrum practices?
Model answer
It can put work on a board and follow work-in-progress limits while initially keeping its existing planning, review, retrospective, and demo practices.
Explanation
The team can later drop ceremonies it finds unnecessary, rather than needing to change everything at the beginning.
- 64
Does Kanban require teams to follow one rigid set of rules or ceremonies?
Model answer
No. It is a flexible tool for managing work, and teams can choose the steps, limits, and practices that suit their needs.
Explanation
The speaker emphasizes that there are no Kanban police and that teams need not track every task or adopt a prescribed meeting schedule.