Dam Construction Process
- 27Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
27 questions
- 1The concrete poured before formwork assembly is called_____because it does not require structural strength.
Hint
This concrete is used to improve work efficiency for formwork creation.
Answer
throwaway concrete
- 2During formwork assembly, the formwork is fixed with nails to_____that are fixed in place with concrete.
Hint
These are horizontal strips used to attach formwork panels.
Answer
battens
- 3To keep formwork vertical during assembly,_____are used.
Hint
These are driven into the ground to support the formwork.
Answer
reinforcing stakes
- 4After connecting formwork, holes are drilled and_____are installed for reinforcement.
Hint
These are inserted into the holes to provide a point for form ties.
Answer
plastic cones
- 5Form ties are attached to bolts on the_____protruding from the underside of the formwork.
Hint
These protrusions come from the cones installed in the formwork.
Answer
plastic cones
- 6A_____is used to tighten the form tie and steel pipe, preventing formwork warping.
Hint
This device uses a wedge mechanism to apply tension.
Answer
wedge-type backing plate
- 7A separator is a metal fitting that maintains a constant_____between opposing formwork pieces.
Hint
It ensures the formwork walls are parallel and evenly spaced.
Answer
distance
- 8The process of_____rounds off the edges of concrete to prevent chipping.
Hint
This is done to the concrete surface after formwork is in place.
Answer
facing
- 9To reinforce formwork against concrete pressure,_____is welded to the separator.
Hint
This steel bar is inserted into the concrete.
Answer
rebar
- 10After pouring concrete,_____is used to distribute it evenly and fill all parts of the formwork.
Hint
This technique uses mechanical shaking to settle the concrete.
Answer
vibration
- 11_____is placed between concrete pours to prevent cracks.
Hint
This material is inserted at joints in concrete structures.
Answer
Elastite
- 12Weed-proof concrete is used to cover soil, preventing weed growth and erosion; its surface is_____to prevent slipping.
Hint
The texture is intentionally made uneven.
Answer
roughened
- 13Once concrete has hardened to a certain extent, the surface is_____.
Hint
This step smoothens or textures the concrete top.
Answer
finished
- 14After formwork is dismantled, plastic cones are removed and the resulting holes are_____.
Hint
The voids left by the cones need to be filled.
Answer
repaired
- 15After the dam-type structure is completed, the excavated riverbed is_____.
Hint
The soil that was removed is replaced.
Answer
backfilled
- 16During construction, drainage pipes are installed to prevent flooding; after work, they are_____.
Hint
These pipes are temporary.
Answer
removed
- 17The dam-type structure prevents erosion of the riverbed, creating a_____environment.
Hint
It makes the area more resilient to natural disasters.
Answer
disaster-resistant
- 18For effective dirt removal, a high pressure water stream should be held at a_____to the surface.
Hint
The angle is 90 degrees.
Answer
right angle
- 19At the edge of the river, a path for water is created to prevent_____.
Hint
Without flow, water becomes still.
Answer
stagnation
- 20Sediment is removed from rivers to prevent_____because accumulated sediment impedes water flow.
Hint
During heavy rain, blocked flow can lead to overflow.
Answer
flooding
- 21Local residents have been mowing grass almost free of charge, but the financial and physical burden has become greater, so improvements are being_____.
Hint
The changes are put into action.
Answer
implemented
- 22Long arm parts are attachments that allow a hydraulic excavator to work_____and deeper.
Hint
It extends the reach from the machine.
Answer
farther
- 23During crane operation, the heavy machinery is lifted using a_____.
Hint
This is a strong cable made of twisted metal wires.
Answer
wire rope
- 24Before installing long arm parts, each part is_____.
Hint
The components are taken apart first.
Answer
disassembled
- 25After installing long arm parts, the bucket is_____.
Hint
The bucket is put back in place.
Answer
refitted
- 26Heavy machinery is transported to a designated_____for use.
Hint
It is moved to a specific place where it will be operated.
Answer
location
- 27Grass cutting on river bank slopes is done to improve_____.
Hint
It makes it easier to see the area.
Answer
visibility

Ask anything
We've read this whole study set, so questions about it get the best answers.