One of the oldest concepts in project management is the concept of the critical path. And I truly doubt that many project managers do they really know what it means and do they really know how to calculate it. Most of the PMP candidates, most of the CAPM candidates, of other credentials are struggling because most of the time, they think: how do you find a critical path? They open the software and click on the critical path. Let's now try to understand what is behind that button.
The critical path is one of really one of the most relevant concepts around project management. And I know that many times people say, okay, we don't need to think in the schedule because we have such a dynamic environment. But many times, finding this path will give you some reasoning on the relevance of everything you need to do from the start of a project up to the end of the project. And this is an example. So I took twelve tasks, each of them one-day duration,
four-day duration, four-day duration, and three days. And I organize this in the network chart, ok? Any software can do this; you just need to link. And I did just basic: finish to start. It means for K to start, F and I, need to finish. This is why we have these two arrows combined to generate K. But when I'm doing this, I need to understand wWhat, is more important? Let's suppose I need to prioritize resources. Should I prioritize G or H or F? What is the most relevant one,
in terms of time for my project? And this is the root of the concept of the critical path. And the critical path method has four components. Did you see this ES, EF, LS, LF? First, let's try to understand this. What is the concept of ES? This means "Early Start". It means: what is the best possible date that that task can start? This means: if everything happens perfectly. What is the best dream date for that task to start? If early start is this, "Early Finish" is what?
Is the early finish of that task. And basically, it's very simple. The early finish is equal to the early start, plus the duration. If early start is 1000 and the duration is eight days, early finish is 1008. It's simple like that. These are all extremely positive, right? This is exactly what I want to that my project happens, everything is perfect, everything happening at the early moment. But then I go to the bottom, and there is there are two concepts LS and LF. LS means "Late Start".
What is the late start? It's the latest possible date that you can start that task. Without delaying your project. This is your late start. It means if you start after that date. You are in trouble. And the late finish, the same concept. The late finish is the latest day. You can finish that task without damaging it. This is our target, this star. This is what I don't want to mess up because I want to know exactly which of these 12 tasks they affect directly this finish date. And this is the concept of the Critical Path Method. So with this four, of course, you may say that a late finish is equal to a late start plus the duration. Okay, this is obvious and it's the same analogy. So these are the initial ones. I will not talk yet about
the free float and the total float. I will talk a little bit later. So what do I need to do to identify which tasks that belong to this critical path? And the critical path the name critical plus path, the path is a path of tasks between start and finish. And it's critical because that group of tasks cannot delay, because if you delay them and if you do not recover, if the other tasks, are executed at the same time as you expected, this project will become late. Okay? So now what do I do?
I will start by doing what is what we call Forward Pass. And what is the forward pass? In the forward pass, I go from this start to the finish. I don't even look at the bottom part of the network. I will only and only concentrate on these fields at the top. I don't care about this at this moment. And what do I do? I will combine this and try to understand what will be the two dates that will come here or the duration that will come here. So let's start. Of course, the first point or the starting point. It's zero, right?
This means as soon as I'm allowed to start, I am starting. Then what do I need? If zero is here. So the end of this start is zero. The beginning of A and B is zero. It means I can do them on zero. I can do them on zero. Then what happens? After bringing the zero to here and the zero to here, I need to calculate the early finish of A and B. EF = ES + Duration. So very easy. Zero plus one is one. Zero plus three is three. Easy! Now, what happens? Let's do this first part.
The early finish of this means the best day for A to finish is after one day. It means, C can start because C only depends on A. C can start immediately on day one. So this number here goes to this number here. Why? Because C can start as soon as A finishes. And if we are talking about early, one day, one day. Of course, I'm not here calculating that you need to start the next day and this. I'm calculating a continuous flow, ok? So one plus four, that is five.
Okay, let's go here. Three comes here on D. Three plus seven is ten. Ten come here. Ten plus two, twelve. Then twelve come here, twelve plus one, thirteen. Let's stop. Ok! We did this and we did the two initial ones. What happens after C? C goes to E and C goes to F. It means this number five here goes here and also to here. So five comes here, and five comes here.
Five plus four, nine. Nine come here. Nine plus three, twelve. Twelve come here. Twelve plus four, sixteen. Sixteen come here. Sixteen plus three nineteen. We did this. We did this. We still need to do this three. Okay! Five plus two, that is seven. Okay. But now on K and M, we need to think a little bit more. Because what happens with K? K depends on F and, it's not or, and I.
F until F is ready, It takes you seven days. But until "I" is ready, it takes you 13 days. So if K depends on F and I. Which number will come to this box here? You have just two options, seven or thirteen. Which one goes? The largest one. Why? Because it takes, for example, it doesn't matter if you start this at seven days.
"I" is not ready. G is not ready. D is not even ready. So you need to wait for thirteen. So every time that you have this, junction. The largest number goes. So on the forward path, always think about that. If you want to memorize for an exam, the largest number goes, the longest. So between seven and thirteen, thirteen. Thirteen plus eight means 21. Ok. But now on M. I have the same, the same challenge. K was F and I, M is L and K.
L takes nineteen days. K takes twenty-one days. M needs to be nineteen or twenty-one. Which one? The largest. Twenty-one goes here. This means this number goes here. Twenty-one plus four, twenty-five. Finish twenty-five Let's stop here. What do we know so far? This project, from A to M takes twenty-five days. This is for sure. If you need just to calculate the duration. It's very simple. If you are using, for example, Microsoft Project, this is exactly what Project does.
And you may ask me. So if Microsoft Project does, why you were teaching this? It's the same reason why you cannot use Excel, if you do not know mathematics, you will be extremely dangerous. And I want you to know what is behind it because then you can use the tool, the IT tool, the software you want. But you know what is behind it. And of course, this is a super simple example. Usually, when you are in an industrial capital project, we are talking about thousands, truly thousands of boxes like this one. So you need to use a computer because it makes more sense. You will not spend, you know, a week calculating that. Okay, so far I know twenty-five. However, I still do not have the answer to my question. Okay.
Which are the critical ones between E and D? What I should prioritize if I need to do some prioritization? If I need to allocate resources, allocate money to make sure I finish this in 25 days. And this drives us to the second part. I will just erase this and this will drive us to the second part which is called, the backward pass.
And what is the backward pass? Now go with me. You need to imagine that this now became the start. This now became the finish. And now all arrows are on the opposite side. This arrow goes from this to this, this from this to this, and this to this. And the opposite up to here, because now I am going back to calculate the backward pass. Okay.
How do I do that? Go with me. The first step, twenty-five days, I put it down here. And why now I will fill delayed fields? Because remember, when I go from the end to the beginning, everything will happen at the latest possible time. This is exactly what I'm looking for now. So twenty-five is here. Then what I do, I put twenty-five here.
And instead of adding as I did on the forward pass, I will deduct twenty-five minus four, twenty-one. Then what happens? Imagine that this arrow is now on this side, and this arrow is going on this side. This twenty-one goes here, and this twenty-one goes here.
I'm doing the same. Twenty-one minus three is eighteen. Twenty-one minus eight is what? Thirteen. Okay? So I'm doing, remember? LF is LS plus duration. So LS is LF minus duration.
Minus duration. So it's easy like that. It's easy like that, late start. So what I'm doing, it's this 25 minus 4, 21. 25 minus 4, 21. And then what I'm doing, I'm moving this late start to the late finish of the task that comes what? Before. Okay. Then what do I do? Eighteen, here, goes here.
Eighteen minus four, fourteen. Fourteen come here. Fourteen minus three, eleven. Eleven come here. Eleven minus four, seven. Let me stop here because this is more complex. Let's stop here. Okay. Now, what I need to do, I need to do the same here. Thirteen that is here. Imagine that this arrow is moving in this direction and this direction. So what happens? Thirteen come here. thirteen come here. Then thirteen minus two is eleven.
Thirteen minus one, twelve. Twelve come here. Twelve minus two, ten. Ten come here. Remember? This arrow, ten come. Ten minus seven, three, Three come here. Three minus three zero. Okay, hold on. We still need to do this two here. But now we have the same problem. Remember, on the forward path, F and I, I picked, F and I picked the large one, seven and thirteen. I picked thirteen, remember?
Now, what do I need to do? Imagine now C. C has two options: eleven or seven, right? Because now I'm going on the other side. So which number will come here? I have two options. Seven or eleven. This and this. Which one goes? Always when you are on the forward pass, you use the largest, on the backward pass, you use the smallest. Always remember this, because you are always trying to do things as late as possible. When you move from start to finish, as early as you can.
When you are from finish to start as late as you can. So between eleven and seven, which is the smallest one. It's seven, right? Seven minus four is three. Three comes here, three minus one, two. Now let's do the very final step. You have two options to come to the start here. One is two. That can come here. The other one is zero which can come here. Which is the smallest one? Zero or two? It's zero.
And I need to tell you, every time you leave from zero here, you go and you come back and reach out to zero. You did it right. Because you close the loop of the process of the forward and backward. So what you just did, you just calculated the critical path. But now we need to identify, okay, Where is the critical path? Then it's so simple. It's so simple. The critical path is the path with the tasks where the top and the bottom are the same.
Zero one, two, three, not the same. One, five, three, seven, not the same. Five nine seven eleven not. Nine twelve eleven fourteen not. Twelve sixteen fourteen eighteen not. Sixteen nineteen eighteen twenty-one not. Five, seven, or eleven, thirteen not. Thirteen twenty-one thirteen twenty-one Whoops, it's the same! Let's put read here. Zero three, zero three, ops.
Three ten three ten ops. Ten twelve ten twelve. Twelve thirteen twelve thirteen. I already market this. Twenty-one twenty-five twenty-one twenty-five. I know the critical path. The critical path is B, D, G, I, K, and M. So these six tasks are the critical ones. Means this path. If I delay anything and I'm not able. Of course, I always imagine that I'm not able to recover later. It means I will change the finish date, it will not be twenty-five. And now one very thing, very easy thing to do. Every time that you are on the critical path. Both fields that are related to the float mean the lack the amount of time that you have free, is zero.
It means if you are on the critical path, You have absolutely no free or total float. You have no float. So then it's very easy. You put 0,0,0,0,0,0,0,0,0,0 and here. Okay! So we did this, but now we have a. Challenge. And what is the challenge?
I need to calculate. Okay. How much float do I have? How much float do I have for all these non-critical tasks? Because every task that is not critical has a float. Period. Has a float means has some time that you can use. But what is the difference between FF or free float, and TF total float?
First, what is important? The concept float. Float means the number of days, hours that you have available for you to do whatever you need without creating a challenge or damage on the twenty-five days. Ok? But what's the difference between the free and the total? So the free float is your own float. It means it's the float that a task has that belongs to the task that does not belong to anyone else. It's a float of that space. This means I'm not using a float that someone,
after me has, It's my own, means if I use that float, I will not damage anyone, anyone. No other task, for example, the free float of A is the amount of delay that A can have without damaging C E F B G D whatever. What is the total float? The total float. Is your float plus all, another float that you may find in front of you. With only one restriction.
You cannot delay the project. You can damage and create a challenge for every single task down the road. You cannot change this day. You do not use your own. The best example. Let me give you a perfect example. Imagine that I have in my pocket $10. And I am living with my parents and I depend on them. So I'm not independent yet. And they have 100. So what is my free float? It's ten because with this ten that I have in my pocket, I can use it. And I'm not damaging anyone. But what is my total float is my ten plus the hundred of my parents, 110. After I spend 110, my parents will go on that. This is absolutely the same concept. This means A can damage C, E, H, J, L. Everybody.
But it cannot damage the finish. It can use its total, its free float, plus all the other ones. This is so the concept of free float is, in some ways, an ownest float. You know, it's ownest because it belongs to you. But the total float is not so ownest because in the end you are transformed. Because as soon as you eat all the float, you are transforming all their tasks into critical because they don't have floats anymore because you ate that float. So now let's see, how do we calculate this
first one: Let's calculate the total float. Now let's only think about the total float. How do we calculate the total float? This is the easiest one to calculate. Basically, what do we do? We just calculate here the amount of float that we have on every single task. Twenty-one minus twenty-one is zero. This is why I put zero. Twenty-one minus nineteen means this has a total float of two, which means L has a total float. Let's not calculate the free float yet, it's basically
a delayed finish minus the early finish or the late start minus the early start. Because the duration is the same. So eighteen, sixteen, two. Fourteen, twelve, two. Eleven, nine, two. Okay, let's go. Here. Thirteen, seven. It's six. Right? Eleven five six. Right. Okay, now what do we do? Seven five two.
Three one two. Hear all zero because it's critical. This is the easiest. So it means. A has two days of the total float, C, has two days of the total float, E two days, H two days, J two days, L two days. And F six days. Okay. Now, what do we need to do? Let's calculate the free float. The free float is a little bit more tricky. So what do we need to compare? We need to compare the early finish of one task.
With the early start of the next one. Means this number with these numbers. So the early finish with the early start. And when you compare these two, you calculate that the free float is simply, simply the early start of the following minus the early finish of you.
OK. I personally am not a big fan of formulas. I'm much more akin to understanding. Och, so look at this. Look this. Nineteen is the early. But this one. Will start only on twenty-one. So there are two days here, but these two days belong to L because it's the last one in the chain. So the free float of L is two days because of the early start of this, twenty-one minus early finish here, nineteen is equal to two. Okay. Now let's do this. Now let's compare this number with this because now I want to calculate the free float of J, so sixteen minus sixteen is zero. So let's try to understand the meaning of what I did.
J has no free float, which means J has no money in its pocket. Every single money or float that J has, comes from stealing the float of L. And look this is the same here. Twelve, twelve, free float: zero Nine, nine, free float: zero. All good. Now we need just to calculate. This here. So now let's see. Five, five, five, and five. Zero to.
One, one. Zero to. It means all the floats that A, C, E, H, and J they have. Are by using this free float of L. Now let's calculate the free float of F. Again, the early start of the successor. Thirteen minus early finish of yourself, seven. It's equal to six, the free float to six. So look what is interesting here. Let me just change the color, the tasks F
and L are the only ones that have their own float, means F, M, L, F, even more, six days. It means if you need to delay this one up to six days to benefit and make sure that you can do this. Great strategy. Great, because you have six days of free float here like you have two days here. However, remember if A for any reason. Is late.
By two days. What happens? What happens if A, instead of one day becomes three? Just just to speculate what will happen. It will eat the float and suddenly everything here. Will become critical. This is why the critical path changes all the time. When you start executing, things are becoming more critical. This is why we always say that usually at the end of a project, everything is critical because In the beginning, people just eat all the possible float
that may exist and in the end you are just with everything is zero or even negative means. You need to find ways of recovering to finish this on time. Look, I know it's this is very basic and this is very simple. So why do I spend this? Because it's very important that you understand in your mind the mathematics behind this. And then when you know this, you can use any software you want to calculate this, any software, but these will give you the rationale. And what I did?
You can download this to exercise if you want, just to memorize, because I know it's you know, it's a lot of numbers. And also I prepared for you the answers and you can download them in the link here and you can practice that. This is an absolutely simple one you can find on the web. Many of them and I'm not saying that with this, you will become a master in the project management, but this is one tool that will give you some rationale when you are in the network to understand where you should focus on. If you enjoy this video, subscribe to the channel and click on the Bell button to receive notifications of future videos.