Critical Path in Project Management
Critical Path Method: Scheduling and Float
Purpose of the Critical Path
The Critical Path Method (CPM) identifies the longest-duration sequence of dependent activities from a project’s start to its finish. This sequence determines the earliest possible project completion date, given the activity durations and dependencies.
A task on the critical path has no scheduling flexibility: if it is delayed and the delay is not recovered, the project finish date is delayed. Tasks outside the critical path may have some float—time they can be delayed without delaying the overall project.
CPM is useful even when scheduling software is available. Understanding the calculations helps project managers interpret software results, prioritize work, and decide where limited resources are most important. In large projects, software performs the calculations across many activities, but the underlying logic remains the same.
Activity Network in the Example
The example uses finish-to-start dependencies: a successor activity cannot begin until its predecessor has finished. The time scale begins at time 0, and durations are treated as continuous elapsed time.
The source describes the example as having twelve tasks, but the activities labeled A through M comprise thirteen activities:
A: duration 1 day; precedes C.
B: duration 3 days; precedes D.
C: duration 4 days; follows A and precedes E and F.
D: duration 7 days; follows B and precedes G.
E: duration 4 days; follows C and precedes H.
F: duration 2 days; follows C and precedes K.
G: duration 2 days; follows D and precedes I.
H: duration 3 days; follows E and precedes J.
I: duration 1 day; follows G and precedes K.
J: duration 4 days; follows H and precedes L.
K: duration 8 days; follows both F and I and precedes M.
L: duration 3 days; follows J and precedes M.
M: duration 4 days; follows both K and L.
The network can be summarized as:
Start branches to A and B.
A leads to C, which branches to E and F.
E leads through H and J to L.
B leads through D and G to I.
F and I must both finish before K begins.
K and L must both finish before M begins.
M leads to the project finish.
At a merge point, the successor must wait for all its predecessors. This is why K cannot start until both F and I are complete, and M cannot start until both K and L are complete.
Four Timing Values
Each activity is associated with four timing values:
Early Start (ES): The earliest time the activity can begin, assuming preceding work proceeds as planned.
Early Finish (EF): The earliest time the activity can finish.
Late Start (LS): The latest time the activity can begin without delaying the project finish.
Late Finish (LF): The latest time the activity can finish without delaying the project finish.
The forward-pass relationship is:
The corresponding backward-pass relationship is:
Early dates describe the earliest feasible schedule; late dates describe the latest permissible schedule that still preserves the project finish date.
Forward Pass: Finding Early Dates
A forward pass moves through the network from start to finish. It calculates ES and EF, without using the late-date fields.
Forward-pass rules
Activities with no predecessors begin at time 0.
For an activity with one predecessor, its ES equals that predecessor’s EF.
For an activity with multiple predecessors, its ES is the largest predecessor EF, because it must wait for the last predecessor to finish.
Calculate each EF by adding the activity’s duration to its ES.
Applying the forward pass
The initial activities begin at time 0:
A: ES 0, EF 0+1=1.
B: ES 0, EF 0+3=3.
Their successors then receive the predecessor’s EF as their ES:
C follows A: ES 1, EF 1+4=5.
D follows B: ES 3, EF 3+7=10.
E follows C: ES 5, EF 5+4=9.
F follows C: ES 5, EF 5+2=7.
G follows D: ES 10, EF 10+2=12.
H follows E: ES 9, EF 9+3=12.
I follows G: ES 12, EF 12+1=13.
J follows H: ES 12, EF 12+4=16.
L follows J: ES 16, EF 16+3=19.
K depends on both F and I. F finishes at time 7, while I finishes at time 13. K must wait until both are complete, so its ES is the larger value:
Thus, K has ES 13 and EF 13+8=21.
M depends on both K and L. K finishes at time 21, while L finishes at time 19. M must wait until both are complete:
Thus, M has ES 21 and EF 21+4=25.
The project’s earliest possible completion is therefore time 25, or 25 days after the time-0 start.
In a forward pass, a merge uses the largest predecessor EF because the activity cannot start until its slowest-to-finish predecessor is complete.
Backward Pass: Finding Late Dates
A backward pass starts at the project finish and works back toward the start. It calculates LF and LS, showing how late each activity can occur without changing the project completion date.
The finish activity’s LF is set to the project duration. In this example, M must finish by time 25.
Backward-pass rules
Set the final activity’s LF to the project finish time.
Calculate LS by subtracting the activity duration from LF.
For an activity with one successor, its LF equals that successor’s LS.
For an activity with multiple successors, its LF is the smallest successor LS, because it must finish in time for the successor with the earliest required start.
Applying the backward pass
For M:
M: LF 25, LS 25−4=21.
K and L must finish in time for M to start at time 21:
K: LF 21, LS 21−8=13.
L: LF 21, LS 21−3=18.
Continuing backward:
J must finish by L’s LS of 18: LF 18, LS 18−4=14.
H must finish by J’s LS of 14: LF 14, LS 14−3=11.
E must finish by H’s LS of 11: LF 11, LS 11−4=7.
F and I must finish by K’s LS of 13:
F: LF 13, LS 13−2=11.
I: LF 13, LS 13−1=12.
G must finish by I’s LS of 12:
G: LF 12, LS 12−2=10.
D must finish by G’s LS of 10:
D: LF 10, LS 10−7=3.
C has two successors, E and F. It must finish in time for whichever successor requires it first. E’s LS is 7 and F’s LS is 11, so C’s LF is the smaller value:
Therefore, C has LS 7−4=3.
A must finish by C’s LS of 3:
A: LF 3, LS 3−1=2.
B must finish by D’s LS of 3:
B: LF 3, LS 3−3=0.
At the project start, the possible late starts are 2 for A and 0 for B. The smaller value is 0, which matches the original start time and confirms that the forward and backward calculations close consistently.
In a backward pass, a merge uses the smallest successor LS because the activity must be completed in time for the successor with the tightest schedule.
Identifying the Critical Path
An activity is critical when its early and late dates are the same. Equivalently, its total float is zero.
Comparing the early and late dates identifies these critical activities:
B: ES 0, EF 3; LS 0, LF 3.
D: ES 3, EF 10; LS 3, LF 10.
G: ES 10, EF 12; LS 10, LF 12.
I: ES 12, EF 13; LS 12, LF 13.
K: ES 13, EF 21; LS 13, LF 21.
M: ES 21, EF 25; LS 21, LF 25.
The critical path is:
Its duration is:
A delay to any of these activities delays the project finish unless the delay is recovered elsewhere. The path from A through C, E, H, J, L, and M is shorter, so those activities have some scheduling flexibility. However, that flexibility can be used up as the work progresses.
Total Float and Free Float
Float is the amount of time an activity can be delayed under a specified condition. It is often measured in days or hours.
Total float
Total float (TF) is the amount an activity can be delayed without delaying the project finish. It can be calculated from either the start values or the finish values:
For example, L has ES 16 and LS 18, so its total float is:
Total float is not necessarily “owned” by one activity in isolation. Using it can reduce the flexibility available to later activities, and can make those activities critical.
Free float
Free float (FF) is the amount an activity can be delayed without delaying the early start of any immediate successor. For an activity with one successor:
For an activity with multiple successors, the comparison uses the earliest successor ES.
For example:
L finishes early at time 19, while M can start early at time 21. L has 21−19=2 days of free float.
F finishes early at time 7, while K can start early at time 13. F has 13−7=6 days of free float.
J finishes at time 16, and L’s early start is time 16. J has no free float.
Free float is sometimes described as an activity’s “own” float because using it does not push an immediate successor later. Total float may include flexibility that exists farther downstream: using it can shift successor activities while still preserving the overall project finish.
Example Results by Activity
A: ES 0, EF 1; LS 2, LF 3; total float 2 days; free float 0 days.
B: ES 0, EF 3; LS 0, LF 3; total float 0 days; free float 0 days.
C: ES 1, EF 5; LS 3, LF 7; total float 2 days; free float 0 days.
D: ES 3, EF 10; LS 3, LF 10; total float 0 days; free float 0 days.
E: ES 5, EF 9; LS 7, LF 11; total float 2 days; free float 0 days.
F: ES 5, EF 7; LS 11, LF 13; total float 6 days; free float 6 days.
G: ES 10, EF 12; LS 10, LF 12; total float 0 days; free float 0 days.
H: ES 9, EF 12; LS 11, LF 14; total float 2 days; free float 0 days.
I: ES 12, EF 13; LS 12, LF 13; total float 0 days; free float 0 days.
J: ES 12, EF 16; LS 14, LF 18; total float 2 days; free float 0 days.
K: ES 13, EF 21; LS 13, LF 21; total float 0 days; free float 0 days.
L: ES 16, EF 19; LS 18, LF 21; total float 2 days; free float 2 days.
M: ES 21, EF 25; LS 21, LF 25; total float 0 days; free float 0 days.
A, C, E, H, and J each have 2 days of total float but no free float. Their delays can affect the timing of successors even though the project can still finish by time 25. F has 6 days of both total and free float, while L has 2 days of both. The critical activities have zero total float and zero free float.
Why the Critical Path Can Change
The critical path describes the schedule based on the current activity durations and dependencies. As work proceeds, delays may consume available float. For example, if A takes longer than planned, some of C’s available total float is used. As float is consumed, previously noncritical activities can become critical.
This means that the critical path should be monitored throughout the project rather than treated as a permanent label. Near project completion, several activities may have little or no remaining flexibility because earlier delays have used up their float. Negative float can indicate that the current plan cannot meet a required finish date without changes or recovery measures.
The calculation helps guide prioritization: resources and attention are especially important for activities that are critical or are rapidly consuming their available float. Software can calculate and update the schedule, but understanding the forward pass, backward pass, and float explains why those activities matter.

Ask anything
We've read this whole study set, so questions about it get the best answers.