Critical Path in Project Management
- 45Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
- spaceFlip card
- KI knew it
- DI didn't know it
- ←Previous card
- →Next card
What is the purpose of the Critical Path Method (CPM)?
To analyze a project network, determine its completion time, and identify activities that directly govern the finish date.
Or swipe the card
45 cards
What is the purpose of the Critical Path Method (CPM)?
To analyze a project network, determine its completion time, and identify activities that directly govern the finish date.
In CPM, what does a path represent?
A connected sequence of tasks running from the project start to the project finish.
Why are tasks on the critical path important when allocating resources?
Delays to critical tasks can delay the project finish, so they are important targets for prioritization.
What does a finish-to-start dependency mean?
A successor task cannot start until its predecessor task has finished.
Why should project managers understand CPM calculations instead of relying only on software?
Understanding the calculations reveals the reasoning behind the software’s results and helps managers interpret the schedule.
How can critical-path analysis be useful in a dynamic project environment?
It helps show how tasks relate to the project finish and where schedule attention may matter most.
What does Early Start (ES) mean?
The earliest a task can start if preceding work and dependencies allow it to proceed as soon as possible.
What does Early Finish (EF) mean?
The earliest a task can finish, based on its Early Start and duration.
What does Late Start (LS) mean?
The latest a task can start without delaying the project finish.
What does Late Finish (LF) mean?
The latest a task can finish without delaying the project finish.
How do you calculate Late Start from Late Finish?
LS=LF−duration
What do the early and late dates represent in a CPM network?
Early dates show when tasks can happen as soon as possible; late dates show when they can happen as late as possible without delaying the project.
In a forward pass, which network direction and dates do you calculate?
Move from project start to finish and calculate the early dates: ES and EF.
What starting value is used for the forward pass in the example?
The project starts at time 0, so the initial tasks have ES =0.
How do you calculate a task’s ES when it has multiple predecessors?
Use the largest EF among its predecessors.
How do you calculate EF during the forward pass?
Add the task duration to its ES: EF=ES+duration.
In a backward pass, which network direction and dates do you calculate?
Move from project finish to start and calculate the late dates: LF and LS.
What value begins the backward pass in the example?
The project duration, 25 days, is used as the final task’s LF.
How do you determine the LF of a task with multiple successors?
Use the smallest LS among its successors.
What check can help confirm that the forward and backward passes have been completed consistently?
The backward calculation should reach the project start at time 0.
What are the task durations along the example branch A–C–E–H–J–L?
A: 1 day; C: 4 days; E: 4 days; H: 3 days; J: 4 days; L: 3 days.
What are the task durations along the example branch B–D–G–I–K–M?
B: 3 days; D: 7 days; G: 2 days; I: 1 day; K: 8 days; M: 4 days.
What are the forward-pass ES/EF pairs for A, C, E, H, J, and L?
A: 0/1; C: 1/5; E: 5/9; H: 9/12; J: 12/16; L: 16/19.
What are the forward-pass ES/EF pairs for B, D, G, I, K, and M?
B: 0/3; D: 3/10; G: 10/12; I: 12/13; K: 13/21; M: 21/25.
What is task F’s duration and its early timing in the example?
F takes 2 days, has ES =5, and has EF =7.
Why does K have ES =13 in the example?
K depends on both F and I; F finishes at 7, while I finishes at 13, so K must wait until 13.
Why does M have ES =21 in the example?
M depends on both L and K; L finishes at 19 and K at 21, so M must wait until 21.
What is the example project’s total duration?
25 days.
Which tasks make up the critical path in the example?
B–D–G–I–K–M.
How can you identify a critical task by comparing its early and late dates?
Its ES equals its LS, and its EF equals its LF.
What float does a critical task have in the example?
Zero free float and zero total float.
What is the schedule consequence of delaying a critical task?
Unless the delay is recovered, the project finish date moves later.
Why does a project’s critical path identify the path that governs its finish?
The project cannot finish until all required paths are complete, and the longest-duration path sets the earliest possible finish.
How can the critical path change while a project is being executed?
As delays consume available float, previously noncritical tasks or paths can become critical.
What does float mean in a project schedule?
The amount of time a task can be delayed, within the relevant limits, without delaying the project finish.
What is total float?
The amount a task can be delayed without delaying the project finish, even if that delay affects later tasks.
How do you calculate total float using early and late dates?
TF=LS−ES, or equivalently, TF=LF−EF.
What is free float?
The amount a task can be delayed without delaying the early start of its successor.
How do you calculate free float for a task with one successor?
FF=ESsuccessor−EFtask.
How does free float differ from total float?
Free float cannot delay a successor’s early start; total float can affect successor timing but cannot delay the project finish.
What are the total float values for A, C, E, H, J, and L in the example?
Each has 2 days of total float.
What are the total float and free float of F in the example?
F has 6 days of total float and 6 days of free float.
What are the total float and free float of L in the example?
L has 2 days of total float and 2 days of free float.
What are the free floats of A, C, E, H, and J in the example?
Each has 0 days of free float.
How can using total float on one task affect other tasks?
It can consume schedule allowance downstream, reducing or eliminating other tasks’ float and potentially making them critical.