Critical Path in Project Management
- 42Unfamiliar
- 0Learning
- 0Familiar
- 0Mastered
42 questions
- 1The Critical Path Method identifies the sequence of tasks that determines the project's_____date.
Hint
Think about the project milestone that would move later if a critical task were delayed.
Answer
finish
- 2A path in a project network is a sequence of tasks connecting the project_____to its finish.
Hint
It is the point where the project begins.
Answer
start
- 3Tasks on the critical path cannot be delayed without delaying the project, unless the delay is_____later.
Hint
The delay must be made up elsewhere in the schedule.
Answer
recovered
- 4When deciding which tasks to prioritize for resources, the critical path helps identify the tasks with the greatest impact on the project's_____.
Hint
Consider the scheduled endpoint of the project.
Answer
finish date
- 5The critical path can help explain the relevance of activities throughout the project, even in a_____environment.
Hint
The content describes an environment where conditions can change.
Answer
dynamic
- 6The four schedule fields used in the Critical Path Method are Early Start, Early Finish, Late Start, and Late_____.
Hint
The missing field is abbreviated LF.
Answer
Finish
- 7A finish-to-start dependency means that a successor task can start only after its predecessor task_____.
Hint
The relationship links the end of one task to the beginning of the next.
Answer
finishes
- 8Using project software to display the critical path is most useful when the project manager also understands the_____behind the result.
Hint
It is the reasoning that explains how the dates are calculated.
Answer
mathematics
- 9In the forward pass, the project manager moves from the project_____toward the finish.
Hint
This pass calculates the earliest possible dates in the direction tasks proceed.
Answer
start
- 10During the forward pass, the fields being calculated are Early Start and Early_____.
Hint
These are the top fields in the example network.
Answer
Finish
- 11Early Start is the best possible date a task can begin if everything happens_____.
Hint
It represents the most optimistic feasible start.
Answer
perfectly
- 12Early Finish is calculated by adding the task duration to its Early_____.
Hint
The calculation begins with the task's earliest possible beginning date.
Answer
Start
- 13If a task has an Early Start of 1000 and a duration of eight days, its Early Finish is_____.
Hint
Add the duration to the Early Start.
Answer
1008
- 14For a finish-to-start successor, the earliest start is the predecessor's Early_____.
Hint
The successor can begin as soon as the preceding task is complete.
Answer
Finish
- 15When a task depends on multiple predecessors in the forward pass, its Early Start is based on the_____predecessor Early Finish.
Hint
The task must wait until every predecessor is ready.
Answer
largest
- 16In the backward pass, calculations move from the project finish back toward the project_____.
Hint
This pass works in the reverse direction from the forward pass.
Answer
start
- 17The backward pass calculates the latest dates a task can occur without delaying the project, using Late Start and Late_____.
Hint
The missing date field is abbreviated LF.
Answer
Finish
- 18Late Start is calculated by subtracting task duration from Late_____.
Hint
Reverse the Early Finish calculation.
Answer
Finish
- 19When a task has multiple successors in the backward pass, its Late Finish is based on the_____successor Late Start.
Hint
The task must finish in time for every successor to meet its latest allowable start.
Answer
smallest
- 20In the example network, the project finish date is used as the initial Late Finish value for the final task, which is_____days.
Hint
It is the duration found by the forward pass.
Answer
25
- 21In the example network, the critical path is B, D, G, I, K, and_____.
Hint
This is the final task on the critical sequence.
Answer
M
- 22The example network's critical path contains_____tasks.
Hint
Count B, D, G, I, K, and M.
Answer
six
- 23The example network takes_____days from start to finish when its tasks follow the calculated schedule.
Hint
This is the Early Finish of the final task.
Answer
25
- 24Task K cannot start until both F and I finish; because their Early Finishes are seven and thirteen, K's Early Start is_____.
Hint
A task with multiple predecessors must wait for the one that finishes latest.
Answer
13
- 25Task K has an Early Start of 13 and a duration of eight days, giving it an Early Finish of_____.
Hint
Add K's duration to its Early Start.
Answer
21
- 26Task M depends on L and K; since their Early Finishes are nineteen and twenty-one, M's Early Start is_____.
Hint
M must wait for whichever predecessor finishes later.
Answer
21
- 27Task M starts on day 21 and lasts four days, so the project finishes on day_____.
Hint
Use the task's Early Start plus its duration.
Answer
25
- 28In the example, the Late Start and Late Finish for critical task K are_____and 21.
Hint
On a critical task, these dates match its Early Start and Early Finish.
Answer
13
- 29In the example, task F has a total float of_____days.
Hint
Compare its late and early dates, or its available time before K starts.
Answer
six
- 30In the example, task L has a total float of_____days.
Hint
Its Late Finish is 21 and its Early Finish is 19.
Answer
two
- 31Float is the amount of time a task can use without causing damage to the project's_____date.
Hint
It is the scheduled endpoint that the project must preserve.
Answer
finish
- 32Free float is the amount of time a task can be delayed without affecting any_____task.
Hint
It does not consume time available to tasks later in the network.
Answer
other
- 33Total float is the amount of time a task can use without delaying the overall project, even if it affects tasks_____in the network.
Hint
These tasks follow the one using the float.
Answer
later
- 34Free float is calculated by subtracting a task's Early Finish from the Early Start of its_____.
Hint
This is the task that follows it.
Answer
successor
- 35Total float can be calculated as Late Finish minus Early Finish, or Late Start minus Early_____.
Hint
Compare the two corresponding start-date fields.
Answer
Start
- 36A task on the critical path has_____free float and total float.
Hint
There is no unused time available before the project finish would be affected.
Answer
zero
- 37In the example, F's Early Finish is 7 and K's Early Start is 13, so F has_____days of free float.
Hint
Subtract F's Early Finish from the Early Start of its successor K.
Answer
six
- 38In the example, L's Early Finish is 19 and M's Early Start is 21, so L has_____days of free float.
Hint
The gap between L finishing and M starting belongs to L.
Answer
two
- 39In the example, A, C, E, H, and J have no free float, while their calculated total float is_____days each.
Hint
Their total float is available only by using time that may affect following tasks.
Answer
two
- 40If a task uses up float that would otherwise be available to later tasks, those tasks can become_____.
Hint
They lose their remaining scheduling flexibility.
Answer
critical
- 41As float is consumed during project execution, the critical path can_____.
Hint
The set of tasks with no remaining schedule flexibility may not stay the same.
Answer
change
- 42If available float is exhausted near the end of a project, recovering the schedule may require finding ways to finish_____.
Hint
The goal is to preserve the planned project finish date.
Answer
on time