Critical Path in Project Management

  • 42Unfamiliar
  • 0Learning
  • 0Familiar
  • 0Mastered
Topic: Critical Path Basics
The Critical Path Method identifies the sequence of tasks that determines the project's
date.

42 questions

  1. 1
    The Critical Path Method identifies the sequence of tasks that determines the project's
    _____
    date.
    Hint

    Think about the project milestone that would move later if a critical task were delayed.

    Answer

    finish

  2. 2
    A path in a project network is a sequence of tasks connecting the project
    _____
    to its finish.
    Hint

    It is the point where the project begins.

    Answer

    start

  3. 3
    Tasks on the critical path cannot be delayed without delaying the project, unless the delay is
    _____
    later.
    Hint

    The delay must be made up elsewhere in the schedule.

    Answer

    recovered

  4. 4
    When deciding which tasks to prioritize for resources, the critical path helps identify the tasks with the greatest impact on the project's
    _____
    .
    Hint

    Consider the scheduled endpoint of the project.

    Answer

    finish date

  5. 5
    The critical path can help explain the relevance of activities throughout the project, even in a
    _____
    environment.
    Hint

    The content describes an environment where conditions can change.

    Answer

    dynamic

  6. 6
    The four schedule fields used in the Critical Path Method are Early Start, Early Finish, Late Start, and Late
    _____
    .
    Hint

    The missing field is abbreviated LF.

    Answer

    Finish

  7. 7
    A finish-to-start dependency means that a successor task can start only after its predecessor task
    _____
    .
    Hint

    The relationship links the end of one task to the beginning of the next.

    Answer

    finishes

  8. 8
    Using project software to display the critical path is most useful when the project manager also understands the
    _____
    behind the result.
    Hint

    It is the reasoning that explains how the dates are calculated.

    Answer

    mathematics

  9. 9
    In the forward pass, the project manager moves from the project
    _____
    toward the finish.
    Hint

    This pass calculates the earliest possible dates in the direction tasks proceed.

    Answer

    start

  10. 10
    During the forward pass, the fields being calculated are Early Start and Early
    _____
    .
    Hint

    These are the top fields in the example network.

    Answer

    Finish

  11. 11
    Early Start is the best possible date a task can begin if everything happens
    _____
    .
    Hint

    It represents the most optimistic feasible start.

    Answer

    perfectly

  12. 12
    Early Finish is calculated by adding the task duration to its Early
    _____
    .
    Hint

    The calculation begins with the task's earliest possible beginning date.

    Answer

    Start

  13. 13
    If a task has an Early Start of 1000 and a duration of eight days, its Early Finish is
    _____
    .
    Hint

    Add the duration to the Early Start.

    Answer

    1008

  14. 14
    For a finish-to-start successor, the earliest start is the predecessor's Early
    _____
    .
    Hint

    The successor can begin as soon as the preceding task is complete.

    Answer

    Finish

  15. 15
    When a task depends on multiple predecessors in the forward pass, its Early Start is based on the
    _____
    predecessor Early Finish.
    Hint

    The task must wait until every predecessor is ready.

    Answer

    largest

  16. 16
    In the backward pass, calculations move from the project finish back toward the project
    _____
    .
    Hint

    This pass works in the reverse direction from the forward pass.

    Answer

    start

  17. 17
    The backward pass calculates the latest dates a task can occur without delaying the project, using Late Start and Late
    _____
    .
    Hint

    The missing date field is abbreviated LF.

    Answer

    Finish

  18. 18
    Late Start is calculated by subtracting task duration from Late
    _____
    .
    Hint

    Reverse the Early Finish calculation.

    Answer

    Finish

  19. 19
    When a task has multiple successors in the backward pass, its Late Finish is based on the
    _____
    successor Late Start.
    Hint

    The task must finish in time for every successor to meet its latest allowable start.

    Answer

    smallest

  20. 20
    In the example network, the project finish date is used as the initial Late Finish value for the final task, which is
    _____
    days.
    Hint

    It is the duration found by the forward pass.

    Answer

    25

  21. 21
    In the example network, the critical path is B, D, G, I, K, and
    _____
    .
    Hint

    This is the final task on the critical sequence.

    Answer

    M

  22. 22
    The example network's critical path contains
    _____
    tasks.
    Hint

    Count B, D, G, I, K, and M.

    Answer

    six

  23. 23
    The example network takes
    _____
    days from start to finish when its tasks follow the calculated schedule.
    Hint

    This is the Early Finish of the final task.

    Answer

    25

  24. 24
    Task K cannot start until both F and I finish; because their Early Finishes are seven and thirteen, K's Early Start is
    _____
    .
    Hint

    A task with multiple predecessors must wait for the one that finishes latest.

    Answer

    13

  25. 25
    Task K has an Early Start of 13 and a duration of eight days, giving it an Early Finish of
    _____
    .
    Hint

    Add K's duration to its Early Start.

    Answer

    21

  26. 26
    Task M depends on L and K; since their Early Finishes are nineteen and twenty-one, M's Early Start is
    _____
    .
    Hint

    M must wait for whichever predecessor finishes later.

    Answer

    21

  27. 27
    Task M starts on day 21 and lasts four days, so the project finishes on day
    _____
    .
    Hint

    Use the task's Early Start plus its duration.

    Answer

    25

  28. 28
    In the example, the Late Start and Late Finish for critical task K are
    _____
    and 21.
    Hint

    On a critical task, these dates match its Early Start and Early Finish.

    Answer

    13

  29. 29
    In the example, task F has a total float of
    _____
    days.
    Hint

    Compare its late and early dates, or its available time before K starts.

    Answer

    six

  30. 30
    In the example, task L has a total float of
    _____
    days.
    Hint

    Its Late Finish is 21 and its Early Finish is 19.

    Answer

    two

  31. 31
    Float is the amount of time a task can use without causing damage to the project's
    _____
    date.
    Hint

    It is the scheduled endpoint that the project must preserve.

    Answer

    finish

  32. 32
    Free float is the amount of time a task can be delayed without affecting any
    _____
    task.
    Hint

    It does not consume time available to tasks later in the network.

    Answer

    other

  33. 33
    Total float is the amount of time a task can use without delaying the overall project, even if it affects tasks
    _____
    in the network.
    Hint

    These tasks follow the one using the float.

    Answer

    later

  34. 34
    Free float is calculated by subtracting a task's Early Finish from the Early Start of its
    _____
    .
    Hint

    This is the task that follows it.

    Answer

    successor

  35. 35
    Total float can be calculated as Late Finish minus Early Finish, or Late Start minus Early
    _____
    .
    Hint

    Compare the two corresponding start-date fields.

    Answer

    Start

  36. 36
    A task on the critical path has
    _____
    free float and total float.
    Hint

    There is no unused time available before the project finish would be affected.

    Answer

    zero

  37. 37
    In the example, F's Early Finish is 7 and K's Early Start is 13, so F has
    _____
    days of free float.
    Hint

    Subtract F's Early Finish from the Early Start of its successor K.

    Answer

    six

  38. 38
    In the example, L's Early Finish is 19 and M's Early Start is 21, so L has
    _____
    days of free float.
    Hint

    The gap between L finishing and M starting belongs to L.

    Answer

    two

  39. 39
    In the example, A, C, E, H, and J have no free float, while their calculated total float is
    _____
    days each.
    Hint

    Their total float is available only by using time that may affect following tasks.

    Answer

    two

  40. 40
    If a task uses up float that would otherwise be available to later tasks, those tasks can become
    _____
    .
    Hint

    They lose their remaining scheduling flexibility.

    Answer

    critical

  41. 41
    As float is consumed during project execution, the critical path can
    _____
    .
    Hint

    The set of tasks with no remaining schedule flexibility may not stay the same.

    Answer

    change

  42. 42
    If available float is exhausted near the end of a project, recovering the schedule may require finding ways to finish
    _____
    .
    Hint

    The goal is to preserve the planned project finish date.

    Answer

    on time