Critical Path in Project Management


Critical Path in Project Management

Simon
Let’s unpack the critical path—the idea behind that button in project-management software. It’s one of the oldest and most useful scheduling concepts, but it’s easy to click a tool without understanding what it calculated. Knowing the logic helps you see which work really affects the project finish date.

Hope
And it still matters even when a project is changing quickly. A network schedule gives you a way to reason about how the tasks connect, where delays could matter, and where you might focus resources.

Simon
We’ll use a simple network with finish-to-start relationships: a task can start once its predecessor finishes. The task durations are A, one day; B, three; C, four; D, seven; E, four; F, two; G, two; H, three; I, one; J, four; K, eight; L, three; and M, four.

Hope
And the links matter as much as the durations. For example, K depends on both F and I, while M depends on both K and L. Those “both” relationships are where we need to pay special attention: a task with two predecessors can’t begin until both are ready.

Simon
Each task has four useful schedule values: ES, EF, LS, and LF. ES means Early Start—the earliest the task could begin if everything before it goes as planned. EF is Early Finish, calculated as Early Start plus the task duration.

Hope
So if a task has an Early Start of day ten and lasts eight days, its Early Finish is day eighteen. We’re using a continuous timeline here, so we’re adding durations rather than inserting an extra day between tasks.

Simon
The other pair is Late Start and Late Finish. These are the latest times a task can start or finish without pushing the project’s finish later. Late Finish equals Late Start plus duration, or, working backward, Late Start equals Late Finish minus duration.

Hope
That gives us two passes through the network. The forward pass finds the earliest dates, moving from the start toward the finish. The backward pass finds the latest dates, moving from the finish back toward the start.

Simon
Let’s do the forward pass first. At the start, we use zero. A and B can both begin at zero, so A finishes at one and B finishes at three: zero plus one, and zero plus three.

Hope
C follows A, so C starts at one and finishes at five after its four-day duration. D follows B, so it starts at three and finishes at ten after seven days.

Simon
From C, the network branches. E and F can both start at day five. E lasts four days, so it finishes at nine; F lasts two, so it finishes at seven. E then leads to H, which runs from day nine to day twelve, and H leads to J, which runs from twelve to sixteen.

Hope
That branch continues through L. L starts at sixteen, lasts three days, and finishes at nineteen. Meanwhile, the other branch from B goes through D, then G, then I: D finishes at ten, G runs from ten to twelve, and I runs from twelve to thirteen.

Simon
Now consider K, which needs both F and I. F is ready at seven, but I isn’t ready until thirteen. K can’t start at seven and wait for I; its earliest start is the later of those two dates, day thirteen. It lasts eight days, so it finishes at twenty-one.

Hope
That’s the forward-pass rule at a merge: use the largest predecessor Early Finish. The same logic applies to M, which needs both K and L. K finishes at twenty-one and L at nineteen, so M starts at twenty-one, lasts four days, and finishes at twenty-five.

Simon
So the earliest finish for the whole project is day twenty-five. But that doesn’t yet tell us which tasks are critical, or whether we could delay some work without changing that finish. For that, we need the backward pass.

Hope
We begin at the finish with M’s Late Finish at twenty-five. M lasts four days, so its Late Start is twenty-one. Moving backward, K and L each need to be finished by day twenty-one, because both feed into M.

Simon
K lasts eight days, so its Late Start is thirteen. L lasts three, so its Late Start is eighteen. Moving back along the E-H-J-L branch, J must finish by eighteen, so it starts by fourteen; H must finish by fourteen, so it starts by eleven; and E must finish by eleven, so it starts by seven.

Hope
Now work backward through the other side. I must finish by K’s Late Start, day thirteen, so I starts by twelve. G finishes by twelve and starts by ten; D finishes by ten and starts by three. F also must finish by thirteen, so its Late Start is eleven.

Simon
At a backward-pass split, use the smallest Late Start among the following tasks. C feeds both E and F: E’s Late Start is seven, and F’s is eleven. C therefore needs to finish by seven, giving it a Late Start of three.

Hope
Finally, A must finish by C’s Late Start of three, so A’s Late Start is two. B must finish by D’s Late Start of three, so B’s Late Start is zero. Getting back to zero at the start is a useful check that the forward and backward calculations line up.

Simon
Now compare each task’s early and late dates. A critical task has no gap between them: its Early Start matches its Late Start, and its Early Finish matches its Late Finish. In this network, that identifies B, D, G, I, K, and M.

Hope
Those tasks form the critical path: B to D to G to I to K to M. Their durations add up to three plus seven plus two plus one plus eight plus four, which is twenty-five days. If one of those tasks is delayed and the time isn’t recovered elsewhere, the project finish moves.

Simon
That’s why the path is called critical: it’s the chain that determines the project’s earliest completion in this network. If you’re prioritizing attention or resources to protect the twenty-five-day finish, these tasks deserve particular focus.

Hope
But tasks outside the critical path can have some flexibility, called float. Total float is how much a task can move later without delaying the project finish. In this example, you can calculate it as Late Start minus Early Start, or Late Finish minus Early Finish.

Simon
A, C, E, H, J, and L each have two days of total float. F has six days. The critical-path tasks have zero total float. That doesn’t mean a noncritical task can be ignored; it means there is some available time before a delay affects the overall finish.

Hope
Free float is narrower. It’s how much a task can be delayed without delaying the earliest start of its immediate successor. For a task with one successor, compare the successor’s Early Start with the task’s Early Finish; with multiple successors, use the earliest successor start.

Simon
For example, L finishes at nineteen, while M can start at twenty-one, so L has two days of free float. F finishes at seven, while K can’t start until thirteen, so F has six days of free float.

Hope
By contrast, A, C, E, H, and J have zero free float: each is scheduled to finish exactly when its next task can start. They still have two days of total float, but using that float pushes work downstream. So they’re using time that exists elsewhere in the chain rather than having free time of their own.

Simon
A helpful way to remember the distinction is that free float won’t delay the next task’s earliest start, while total float can affect tasks downstream but still won’t delay the project finish. If you use up total float, those downstream tasks may lose their flexibility.

Hope
And the critical path can change as the project unfolds. If delays consume available float, a task that wasn’t critical may become critical. That’s one reason the schedule needs to be understood and revisited—not just calculated once.

Simon
Software can calculate all these dates, and a computer is essential for a network with thousands of tasks. But learning the forward pass, backward pass, and float calculations lets you understand what the software is telling you and make better judgments about where to focus.

Hope
So the core method is: move forward using the largest predecessor finish at merges, move backward using the smallest following start at splits, compare early and late dates to find the critical path, and use float to understand the flexibility around it. That’s the reasoning behind the button.